MAKRAN COASTAL HIGHWAY

Loading in 2 Seconds...

play fullscreen
1 / 27

MAKRAN COASTAL HIGHWAY - PowerPoint PPT Presentation


  • 69 Views
  • Uploaded on

MAI KOLACHI. MAKRAN COASTAL HIGHWAY. NDMA. LYARI EXPRESSWAY. RAN PATHANI. WORK METHODOLOGY. FOR REMOVAL OF COLLAPSED PORTION AT SHERSHAH BRIDGE SITE. RBOD - II. SUKKUR BARRAGE. 25 Jun 2007. NHA ACHIEVEMENTS. MAJOR ACHIEVEMENTS OF FWO. AIM.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' MAKRAN COASTAL HIGHWAY' - holmes-hatfield


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

MAI KOLACHI

MAKRAN COASTAL HIGHWAY

NDMA

LYARI EXPRESSWAY

RAN PATHANI

WORK METHODOLOGY

FOR REMOVAL OF COLLAPSED PORTION

AT SHERSHAH BRIDGE SITE

RBOD - II

SUKKUR BARRAGE

25 Jun 2007

slide4

AIM

TO PRESENT WORK METHODOLOGY FOR REMOVAL OF COLLAPSED PORTION AT SHERSHAH BRIDGE SITE

slide17

SHERSHAH BRIDGE

WORKING METHODOLOGY

slide18

SHERSHAH BRIDGE

WORKING ORGANIZATION

  • FIELD CONTROL CENTRE
  • (GROUP COMMANDER)
  • COL BASIM (NLC)
  • COORD OFFICER

DEMOLITION GROUP – I

(LT COL SAEED)

DEMOLITION GROUP – II

(LT COL TAHIR)

SUPPORT GROUP

(LT COL MANSOOR)

DEMOLITION TEAM – A

(IC – JCO)

(2 x NCOs, 10 x OR)

DEMOLITION TEAM – C

(IC – JCO)

(2 x NCOs, 10 x OR)

COORD TEAM

(IC - JCO)

DEMOLITION TEAM – B

(IC – JCO)

(2 x NCOs, 10 x OR)

DEMOLITION TEAM – D

(IC – JCO)

(2 x NCOs, 10 x OR)

TPT / PLANT MGMT TEAM

(IC – JCO)

(3 x NCOs, REQ OP)

TOTAL 60 – 70 PERSONS

slide19

SHERSHAH BRIDGE

DEMOLITION METHODOLOGY

slide20

SHERSHAH BRIDGE

DEMOLITION METHODOLOGY

slide21

SHERSHAH BRIDGE

DEMOLITION METHODOLOGY

slide22

SHERSHAH BRIDGE

DEMOLITION METHODOLOGY

slide23

SHERSHAH BRIDGE

DEMOLITION METHODOLOGY

slide24

SHERSHAH BRIDGE

DEMOLITION METHODOLOGY

slide25

SHERSHAH BRIDGE

PROPOSED LIST OF PLANT / EQUIPTMENT

slide26

SHERSHAH BRIDGE

SUPPORT GROUP