Production planning
Download
1 / 29

Production Planning - PowerPoint PPT Presentation


  • 73 Views
  • Uploaded on

Production Planning. Devaki Nadkarni. Decision Level. Decision Process. Forecasts needed. Allocates production among plants. Annual demand by item and by region. Corporate. Determines seasonal plan by product type. Monthly demand for 15 months by product type. Plant manager.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Production Planning' - hoai


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Production planning

Production Planning

Devaki Nadkarni


Production planning1

Decision Level

Decision Process

Forecasts needed

Allocates

production

among plants

Annual demand by

item and by region

Corporate

Determines

seasonal plan by

product type

Monthly demand

for 15 months by

product type

Plant manager

Determines monthly

item production

schedules

Monthly demand

for 5 months by

item

Shop

superintendent

Production Planning


Objectives of production planning
Objectives of Production Planning

  • To deliver quality goods in required quantities to the customer in the required delivery schedule – to achieve maximum customer satisfaction and minimum possible cost.

  • To ensure maximum utilization of all resources.

  • To ensure production of quality products.

  • To minimize the product through-put time of production/manufacturing cycle time.

  • To maintain optimum inventory level.

  • To maintain flexibility in manufacturing operations.

  • To co-ordinate between labour and machines and various supporting departments.


Production Planning Horizons

Long-Range

(years)

Long-Range Capacity Planning

Medium-Range

(6-18 months)

Aggregate Planning

Short-Range

(weeks)

Master Production Scheduling

Very-Short-Range

(hours - days)

Production Planning and Control Systems

Pond Draining

Systems

Push

Systems (MRP)

Pull

Systems (JIT)

Focusing on

Bottlenecks


Production Planning: Units of Measure

Entire

Product Line

Long-Range Capacity Planning

Product

Family

Aggregate Planning

Specific

Product Model

Master Production Scheduling

Labor, Materials,

Machines

Production Planning and Control Systems

Pond Draining

Systems

Push

Systems

Pull

Systems

Focusing on

Bottlenecks


Aggregate planning
Aggregate Planning

Aggregate planning involves planning the best quantity to produce during time periods in the intermediate-range horizon (often 3 months to 18 months) and planning the lowest cost method of providing the adjustable capacity to accommodate production requirements.

  • It facilitates fully loaded facilities and minimizes overloading and under loading and keeps production cost low.

  • Adequate production capacity is provided to meet expected aggregate demand.

  • To manage change in production/ operations management by planning for production resources that adapt to the changes in customer demands.


Flowchart of Aggregate plan and Master Production Schedule

Resource base and technology

Market Environment

Capacity (facilities, material, labour and capital)

Forecast and customer order

Aggregate Production Plan

Master Production Schedule

Material Requirements

Capacity Requirements


Steps in aggregate capacity planning
Steps in Aggregate Capacity Planning

  • Prepare the sales forecast for each product that indicates the quantities to be sold in each time period.

  • Sum up the individual forecast into one aggregate demand.

  • Transform the aggregate demand for each time period into labour, materials, machines and other elements of production capacity required to satisfy aggregate demand.

  • Develop alternative resource schemes for supplying the necessary production to support the cumulative aggregate demand and choose the best that meets the objectives of the organisation.


Master production scheduling
Master Production Scheduling

The master production scheduling sets the quantity of each end item(finished product) to be completed in each time period of the short range planning horizon.

Objectives:

  • To schedule end items to be completed promptly and when promised to customers.

  • To avoid overloading or under-loading the production facility so that production facility is efficiently utilized at the optimum cost.


Functions of master production schedule
Functions of Master Production Schedule

  • Translating aggregate plans into specific end items.

  • Evaluating alternative schedules.

  • Generating material requirements.

  • Generating capacity requirements.

  • Facilitating information processing.

  • Maintaining valid priorities.

  • Utilizing capacity effectively.


The elements of MPS:

  • Demand management.

  • Lot sizing.

  • No. of products to be scheduled(product-mix).

    Symptoms of poorly designed MPS:

  • Overloaded facilities

  • Under-loaded facilities

  • Excessive inventory levels on some end items and frequent stock out on others.

  • Unrealistic schedules that production personnel do not follow.

  • Unreliable delivery promises to customers.

  • Excessive expediting or follow-up.


Capacity requirement planning
Capacity Requirement Planning

Capacity Requirement Planning is a techniques for determining what labour/personnel and equipment capacities are needed to meet the production objectives.

It involves activities such as

  • Assessing existing capacity and forecasting future capacity needs

  • Identifying alternative ways to modify capacity

  • Evaluating financial, economical and technological capacity alternatives to avoid bottlenecks.

  • Plan capacity to achieve the production schedule


Material requirements planning mrp
Material Requirements Planning (MRP)

Material Requirements Planning (MRP) is a system for planning the future requirements of dependent demand items.


Material requirements planning
Material Requirements Planning

Functions:

  • Order planning and control.

  • Priority planning and control.

  • Provision of a basis for planning capacity requirements and development of broad business plans.

    Successful implementation of MRP results into reduced levels of average inventory, optimum utilisation of human and capital resources, workforce planning, improved vendor relations, better capital investment decisions, reduced delivery lead times.


Make or buy decision
Make or Buy Decision

Considerations

  • Economic considerations.

  • Non economic considerations

    • Availability of supply and alternative sources of supply for components and sub-units.

    • Control of trade secrets and design secrets.

    • Quality and reliability considerations.

    • Delivery schedules to be met.

    • Reliability of supply of external suppliers.

    • Availability of manufacturing capacity (in-house)


Independent vs dependent demand
Independent vs. Dependent Demand

Independent Demand Items

Dependent DemandItems

A

C(2)

B(4)

D(2)

E(1)

D(3)

F(2)


Production planning hierarchy

Firm orders

from known

customers

Forecast of demand from random

customers

Aggregate Product Plan

Inventory transactions

Master Production Schedule (MPS)

Engineering design changes

Bill of Materials (BOM) file

Inventory records file

Material RequirementsPlanning (MRP)

Reports

Production Planning Hierarchy



Materials requirements planning mrp1
Materials Requirements Planning (MRP)

  • Computer based system

  • Explodes Master Schedule (MPS) into required amounts of raw materials and subassemblies to support MPS

  • Nets against current orders and inventories to develop production and purchased material ordering schedules


Material requirements planning1
Material Requirements Planning

  • How much of an item is needed?

  • When is an item needed to complete

    • a specified number of units...

    • in a specified period of time?

  • Dependent demand drives MRP


Objectives of mrp
Objectives of MRP

  • Improve customer service

  • Reduce inventory investment

  • Improve plant operating efficiency


Mrp computer program
MRP Computer Program

  • Begins with number of end items needed

  • Add service parts not included in MPS

  • Explode MPS into gross requirements by consulting bill of materials file

  • Modify gross requirements to get net requirements:

  • Net Requirements = Gross Requirements + Allocated Inventory

    + Safety Stock

    - Inventory On Hand

  • Offset orders to allow for lead time


Outputs of mrp
Outputs of MRP

  • Planned order schedule - quantity of material to be ordered in each time period

  • Changes to planned orders - modifications to previous planned orders

  • Secondary outputs:

    • Exception reports

    • Performance reports

    • Planning reports


More mrp terminology
More MRP Terminology

  • Gross Requirements

    • These requirements are typically forecast for independent demand items

    • Today’s trend is to replace forecasts with blanket orders in order to reduce variability and shorten lead-time

    • The customer is offered a price discount for placing blanket orders


More mrp terminology1
More MRP Terminology

  • On-hand inventory

    • The inventory physically present in the facility

  • Allocated inventory

    • The inventory physically present in the facility but allocated to a particular work order or purchase order


More mrp terminology2
More MRP Terminology

  • Net requirements

    • A quantity of an item that must be purchased or manufactured in order to be able to fully deliver independent demand requirements in a timely fashion

    • Presence of positive net requirements signals that an order must be planned to be received in a given period

    • Net requirement quantities are subject to adjustments due to lot sizes considerations. This may lead to some orders being received early (inventory is held) or late (order backlog)


More mrp terminology3
More MRP Terminology

  • Planned order released

    • Quantities that must be planned to be released in some future periods in order to meet the requirements


More mrp terminology4
More MRP Terminology

  • Scheduled receipts

    • Quantities that will be received in some future periods as their corresponding orders have been released in the past

      • Planned order receipts become scheduled receipts at the time when they are released to the shop or to suppliers


More mrp terminology5
More MRP Terminology

  • Gross to Net logic:

    Net Requirements = Gross Requirements

    + Allocated Inventory

    + Safety Stock

    - Inventory On Hand