An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Olin Chemical Superfund Site Public MeetingOctober 19, 2009AGENDA • Welcome/Opening Remarks – Michael Newhouse, Board of Selectmen • Introductions • Olin Chemical Site Overview - Jim DiLorenzo, US EPA Project Manager • Brief History • Superfund Process • Remedial Investigation • WERC (Wilmington Environmental Restoration Committee) – Martha Stevenson • Update • Public Participation - Sarah White, EPA Community Involvement Coordinator • Site documents • Community Relations Plan

  2. Olin Chemical Superfund Site

  3. October 1952 (Pre-Development)

  4. 1963 National Polychemicals, Inc.

  5. 1967National Polychemicals, Inc.

  6. Operational History • 1953 to 1986 – Manufactured specialty chemicals for the rubber/plastics industry. • 1953 to mid-1960s - Liquid wastes discharged to unlined pits and Lake Poly. • Late-1960s – Treated liquid wastes discharged to lined lagoons and municipal sewer. • 1975 to 1986 - Sludges periodically excavated from lined lagoons and created calcium sulfate landfill.

  7. State DEP Studies • Numerous studies from the late 1980s to 2005. • 500+ soil samples. • 100+ sediment samples. • Hundreds of surface water samples. • Thousands of groundwater samples from 120+ monitoring wells.

  8. State DEP Studies Result Contaminants identified to date with the most frequency by media include; • Soil: chromium, trimethylpentenes, Opex, Kempore, BEHP, NDPA, calcium, sulfate, sodium and ammonia • Sediment: chromium and BEHP • Surface Water: chromium, aluminum, sulfate, ammonia and NDMA • Groundwater: chromium, aluminum, sulfate, trimethylpentenes, BEHP, NDPA and NDMA

  9. Completed Clean-ups • Removed manufactured wastes including tanks and drums. • Excavated sludge from former lagoons, pits, Lake Poly, and drainage ditches. • Capped the calcium sulfate landfill. • Constructed Plant B for product recovery. • Constructed slurry wall/temporary cap. • Created conservation area.

  10. Why More Studies • DEP studies focused on source areas. • Numerous data gaps (spatial and analytes). • Superfund is a “risk-based” clean-up program. • Must consider: • All impacted areas & media • All potential chemicals • Community acceptance • Remedial technologies • Enforcement/$

  11. EPA/PRP Settlement • Approved by EPA on June 28, 2007. • AOC: legal requirements. • RI/FS SOW: technical requirements. • 3 Potentially Responsible Parties (PRPs): • Olin Corporation(owned 1980 to current) • American Biltrite, Inc.(owned prior to 1968) • Stepan Company(owned 1968 to 1980) • Requires PRPs to perform the study. • Requires PRPs to pay for EPA oversight. • This is not an agreement to clean-up the Site.

  12. Key Superfund Reports • Interim Response Steps Work Plan(August 2007) • Proposal for Plant B, slurry wall/cap and DAPL pilot. • Focused Remedial Investigation Report (Oct. 2007) • Compilation of existing data, evaluations and risk assessments. • Semi-Annual Status Reports (4 completed to date) • Summary of data and evaluations each July/January. • **RI/FS Work Plan(August 2009) • Proposal for Superfund investigations.

  13. RI/FS Work Plan Components • Remedial Investigation ← • Comprehensive site characterization • Human health and ecological risk assessments • Feasibility Study • Evaluate remedial technologies • Compare alternatives • Proposed Cleanup Plan • Record of Decision • Remedial Design/Action

  14. Olin Site Current Study Area

  15. Target Analyte List 242 chemicals

  16. Soil Samples • Gaps – Analytical and spatial • Single event • 134 surface soil (0 – 1ft) • 77 borings for soil (1ft to rock) • Up to 242 analysis/sample • Locations selected based on existing data, facility layout, potential exposure areas and spatial coverage. • Completed in September

  17. Upper South Ditch Samples • Surface Water/Sediment Samples • Gaps – Age of data and analytical • High and low flow events • Three areas of study • On-property • Upper South Ditch • Maple Meadow Brook • MMB and Sawmill • Nearby drainage areas • West Ditch • East Ditch/New Boston • North Pond • Landfill Brook • 24 sample locations/pairs • Temperature profiling • Up to 242 analysis/sample 5 sample locations

  18. East and West Ditch Drainage Areas 8 sample locations + Pending North Pond 11 sample locations Maple Meadow Brook Drainage Area

  19. Groundwater Samples • Private wells • Gaps – Plume edges and analytical • 207 existing monitoring wells • 15 – 20 new wells to be installed • Two sampling events planned • 189 samples in the 1st event • Up to 242 analysis/sample Pre-Superfund plume

  20. Private Wells • Two areas with wells • MMB/Butters Row Road • Cook/Burnham/Border • Sampled in Fall 2008 • Total of 11 wells • NDMA detected in two wells on Cook Ave. in the low part per trillion range • No unacceptable risk • No restrictions on use • Continue active testing • Take action if levels rise • New monitoring well

  21. NDMA in Groundwater • N-nitrosodimethylamine • Class B2 carcinogen • Most common use was rocket fuel • Byproduct of chlorination • At Olin, byproduct formed in the aquifer from chemicals such as hydrazine and formaldehyde • EPA priority pollutant and emerging contaminant of concern • No federal or state standards • Not common in Superfund • Toxic in the part per trillion range • Detected in town wells in 2003 • Most toxic and mobile compound

  22. Pooled in 4 valleys Estimated to be 25 million gallons Pending pilot pump test Dense Aqueous-Phase Liquid (DAPL)

  23. Other Activities • Plant B continues to operate • Monitoring of the slurry wall/containment area continues • Status reports to EPA twice a year

  24. Schedule • Soil sampling is done. • Surface water and sediment sampling this fall and spring 2010. • New wells installed this fall. Groundwater testing in the spring and fall 2010. • Data evaluations, risk assessments and supplemental field work into 2011. • Proposed cleanup plans in 2012 and/or 2013.

  25. WILMINGTON ENVIRONMENTAL RESTORATION COMMITTEE(WERC)

  26. Community Involvement • Informational meetings and fact sheets • Public hearings on proposed plans • Wilmington Town officials - Geoinsight • Wilmington Environmental Restoration Committee – WERC – Cambridge Environmental • EPA web – www.epa.gov/region1/superfund/sites/olin • Contacts: • Sarah White (EPA Community Relations Coordinator) (617) 918-1026 white.sarah@epa.gov • Jim DiLorenzo (EPA Project Manager) (617) 918-1247 dilorenzo.jim@epa.gov • Joe Coyne (MassDEP Project Manager) (617) 348-4066 Joseph.Coyne@state.ma.us