1 / 21

Road to Mission Concept Review ACE Workshop March 2009

Road to Mission Concept Review ACE Workshop March 2009. Bob Smith Earth Systematic Missions Program Office DESDynI Mission Manager. When does ACE want to be here?. ACE wants to be here. NASA’s Project Lifecycle. ACE is here. Purpose of MCR. NPR 7120.5D MCR Definition.

herne
Download Presentation

Road to Mission Concept Review ACE Workshop March 2009

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Road to Mission Concept ReviewACE Workshop March 2009 Bob Smith Earth Systematic Missions Program Office DESDynI Mission Manager

  2. When does ACE want to be here? ACE wants to be here NASA’s Project Lifecycle ACE is here

  3. Purpose of MCR NPR 7120.5D MCR Definition Per GSFC STD 1001B At the MCR, the project demonstrates to the review panel that the: • proposed mission meets the science objectives • proposed mission is feasible • proposed mission and operations design concepts are viable, • preliminary plan for development lifecycle activities suitably illustrates reasonable execution of the mission within resource budgets and other foreseen constraints • The MCR affirms the mission need and examines the proposed mission's objectives and the concept for meeting those objectives. • Key technologies are identified and assessed. • ROM budget and schedules are presented. NASA Procedural Requirement 7120.5D - NASA Space Flight Program and Project Management Req’s GSFC STD 1001B - Criteria for Flight Project Critical Milestone Reviews

  4. Required documents for MCR (from 7120.5D) • Draft Level 1 Requirements • Preliminary Formulation Authorization Document • Mission Concept Report (baselined at MDR) • Integrated Baseline - Draft • Baselined Work agreements for next phase • Preliminary Review Plan (per GSFC STD-1001B) Although not required, you should have the following documents: • Summary of trade studies already performed • Draft Mission Requirements Document • Draft Concept of Operations • Draft New Technology Development plan

  5. NPR 7123 requirements for MCR NASA Procedural Requirement 7123.1A - NASA Systems Engineering Processes and Requirements

  6. No Technology Performance Available/ Meets Risks Requirements Acceptable 12 11 Finalize Concept and Develop Report Peer Review PMRD – Refined and Validated Req’s ROM Costs Strawman Mission Concept 14 13 Study Guidelines: the study process Form Study Team and Develop Study Plan 1 Identify & Prioritize Key Design Parameters Strawman Develop Strawman End-to-End Mission Concept Mission Preliminary Top-Level System Needs and System Mission Concept(s) Objectives Requirements Req’ts Flow Down Develop Concept Evaluation Criteria Definition 2 8 4 6 7 5 Constraints& Iterate Requirements a nd Concepts Assumptions 3 No No System ROM Costs Cost/Performance/ Yes Yes Within Margins Guidelines vs. Requirements Evaluations 9 10 Yes Mission Concept Review 15

  7. Study Guidelines: study schedule should include these activities • Detailed mission concept definition • Sensitivity analyses (science measurement requirements and instrument performance parameters) • Cost estimates • Risk assessments • System impacts of new technology infusion • Concept validation • Mission trade space modeling • Study reports and archived models • Level 1 requirement definition • Temporal and spatial resolution requirements. • Measurement accuracy requirement as a function of spatial resolution. • Effect of orbit selection on mission performance. • Mission lifetime. • Other science requirements achievable by potential instrument combinations that could extend the mission applicability to other science questions. • Measurement(s) to be made • Science rationale (How measurements contribute to science question(s)) • Related measurements of complementary value • Define roles for international partners • Define a baseline instrument concept, including the rationale and key instrument performance parameters • Identify alternative instrument concepts • Define a spacecraft concept, including key spacecraft performance parameters • Identify launch requirements • Identify Supporting R&A investments • Identify Specific cal/val requirements • Generate a detail cost estimate for instrument, Ground System, MO& DA, Science, Project Management, Systems Engineering, and Flight Assurance. Parametric estimate for spacecraft. • Develop a detailed mission schedule (at least WBS Level 3 for instrument)

  8. Recent relevant MCR’s and their outcomes • SMAP: June 23, 2008 • HQ decision was delayed due to project costs over HQ budget. • ICESAT-II: February 10, 2009 • Delta MCR is planned • Earth Science Directorate and the Project did not have a clear agreement on mission objectives and requirements • Significant changes to the baseline are planned to be studied in Phase A • The estimated Life Cycle Cost (LCC) for the baseline mission exceeds the goal established by the ESD.

  9. Conclusion • Pre-Phase A is an iterative process. • Make it convergent • Explore the optimum range of cost, schedule, and capability that will maximize the science/cost ratio • Agreement on mission objectives & constraints is crucial • Define the best mission that fits within the allocated resources and is able to bring the mission to Phase A maturity. • Start preparing ~6 months prior to MCR 9

  10. Backup slides

  11. Level 1 Requirements Change Log ii Table of Contents iii 1.Scope 1 2.Science Definition 1 2.1. Science Objectives 1 2.2. Implementation Approach 2 3.Project Definition 3 3.1. Project Org and Management 3 3.2. Project Acquisition Strategy 4 4.Performance Requirements 5 4.1. Science Requirements 5 4.2. Instrument Requirements 5 4.3. Observatory and Ops Requirements 5 4.4. Launch Requirements 5 4.5. Science Meas. Validation Req’s 6 4.6. Data Product Requirements 6 5. Program Requirements 6 5.1. Budget Requirements 6 5.2. Cost Management and Scope Reduction 7 5.3. Schedule Requirements 7 5.4. External Agreement Definition 7 5.5. Multi-Mission Facilities Req’s 7 5.6. Safety Requirements 7 6. Education and Public Engagement Requirements 7 7. Mission Success Criteria 8 7.1. Mission fully successful criteria 8 7.2. Mission minimally successful 8 8.Approvals 9 9.Concurrences 9

  12. STD 1001B MCR Success Criteria 3.2       Success Criteria The GSFC – STD 1001 criteria for a successful MCR are as follows:

  13. GSFC STD 1001 MCR Evaluation Factors

  14. GSFC STD 1001 MCR Evaluation Factors

  15. GSFC STD 1001 MCR Evaluation Factors

  16. Required Project Technical Products Minimal Project Technical Products are required for MCR per 7120.5D: A> Prelim Level 1 Rqts B> Prelim Mission Concept Report C>Draft Integrated Baseline

  17. Project Documents Requirements for MCR and beyond Prelim NPR 7120.5D does not require any Project Control Plans, however, GSFC STD-1001B requires item #8 – Preliminary Review Plan including Engineering Peer Review Plan to be provided

  18. ICESat II - Top Level Schedule Status as of: 08/22/08

  19. ICESat II – MCR Preparation Schedule Status as of: 08/22/08

  20. ICESat II - Mission Studies Schedule Status as of: 08/22/08

  21. ICESat II - Instrument Studies Schedule Status as of: 08/22/08

More Related