DES 606: Watershed Modeling with HEC-HMS. Baseflow and Diversion Theodore G. Cleveland, Ph.D., P.E. 16 OCT 11. Baseflow. The hydrograph is comprised of two principal parts The storm flow component is called the direct runoff hydrograph The base flow (background) component. Baseflow.

Download Presentation

DES 606: Watershed Modeling with HEC-HMS

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Des 606 watershed modeling with hec hms

DES 606: Watershed Modeling with HEC-HMS

Baseflow and Diversion

Theodore G. Cleveland, Ph.D., P.E.

16 OCT 11


Baseflow

Baseflow

  • The hydrograph is comprised of two principal parts

    • The storm flow component is called the direct runoff hydrograph

    • The base flow (background) component.


Baseflow1

Baseflow

  • The hydrograph is comprised of two principal parts: a base flow (background) component and a storm flow component. The storm flow component is called the direct runoff hydrograph

  • (DRH). The DRH is the hydrograph resulting from excess precipitation over the watershed

  • after the losses (abstractions) are removed. It is believed that the lag time from beginning of

  • precipitation to the peak of the DRH, the shape of the DRH) and the decay pattern of the

  • DRH are related to the characteristics of the basin as well as the rainfall pattern. Various

  • approaches to model such relations are in common use.


Incomplete specifications

Incomplete Specifications

  • Parts of HMS model are not connected

    • Sub-basins not connected to other elements

    • Data missing

      • Rainfall gages missing

      • Record lengths inconsistent

  • Troubleshooting these kinds of problems is really learning how to interpret the HMS message log


Incomplete specifications1

Incomplete Specifications


Incomplete specifications2

Incomplete Specifications


Incomplete specifications3

Incomplete Specifications

The warning seems to be

associated with missing data.

We will need to import data into the project.


Incomplete specifications4

Incomplete Specifications

Repair the data files, then re-run


Incomplete specifications5

Incomplete Specifications

Fix again, and re-run – this run has

no warnings.


Clobbered hms dss files

Clobbered HMS-DSS files

  • As analyst changes components and re-runs sometimes the DSS database gets clobbered.

    • This situation will usually throw errors that prevent the run form completing.

    • Easiest solution is to stop and restart HMS

      • Hopefully you have been saving files so recovery is possible.


Des 606 watershed modeling with hec hms

  • Previous model, attempted to save with new filename.

    • Did not save, however HMS does not report failed save outside of log file


Des 606 watershed modeling with hec hms

  • Previous model, attempted to save with new filename.

    • Attempted re-run of project (using new name) throws errors shown.

    • Solution is to import data from prior model, or start over.


How to fix restart hms

How to Fix – Restart HMS


Import prior project

Import Prior Project


Select prior run 1

Select Prior Run 1


Select run 1

Select Run 1

The restart clears the computer memory

And resets HEC-HMS paths

There may be other ways to reset –

this one is known to work


Poor conceptualization

Poor Conceptualization

  • Hardest to detect and repair

    • If have data, then can use to guide repairs

    • Without data

      • use rules-of-thumb appropriate for locale

        • 3cfs/acre/in-hr

        • Tlag(hrs) = SQRT(AREA(sq.mi.)

      • use check-sums

        • Is loss what was anticipated?

        • Do flow peaks seem about correct?


Summary

Summary

  • Troubleshooting HEC-HMS projects needed to make simulation model what analyst thinks is modeling

  • Three modes of trouble

    • Incomplete specifications

    • Clobbered DSS file paths

    • Poor Conceptualization


Summary1

Summary

  • Hints to help make troubleshooting easier

    • Name projects and components; avoid default naming

      • I didn’t follow for the course, but some examples show named components.

    • Maintain Excel data files as project

      • Use external (to HMS) preparation as a backup device.

    • Use HMS backup feature.

    • If recovery is needed, can use these files and cut-and-paste to recover work.

    • Maintain separate projects for substantial changes

      • This is my personal preference, the ANALYSIS tools in HMS are intended to perform such tracking for you


Summary2

Summary

  • These hints should handle the bulk of the incomplete specification and DSS clobbering failure modes.

  • Conceptualization is harder


Summary3

Summary

  • Conceptualization hints

    • Sketch (on paper) the watershed and components; keep a copy handy as build the project.

    • Parameter estimate external to HMS as much as practical; note estimates on the sketch.

    • Keep a simulation log (on paper) as you make minor changes; major changes should be separate project (my preference) or separate ANALYSIS (HMS tracking scheme)