The need for planning implementation planning
Download
1 / 36

The Need for Planning: Implementation Planning - PowerPoint PPT Presentation


  • 172 Views
  • Uploaded on

The Need for Planning: Implementation Planning. William Tibben SITACS University of Wollongong. August 2002. Outline. Definition Important Questions that you need to ask during Implementation Planning Phase Building Project Networks What is a Critical Path and why are these important.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' The Need for Planning: Implementation Planning' - harrison-sullivan


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
The need for planning implementation planning

The Need for Planning: Implementation Planning

William Tibben

SITACS

University of Wollongong. August 2002


Outline
Outline

  • Definition

  • Important Questions that you need to ask during Implementation Planning Phase

  • Building Project Networks

  • What is a Critical Path and why are these important


Spectacular achievements are always preceded by calculated preparation gcrh 2002
‘…Spectacular achievements are always preceded by calculated preparation…’ (GCRH, 2002)


How long is a piece of string
How long is a piece of string? calculated preparation…’ (GCRH, 2002)

Management says we need a piece of string….but ‘how long is a piece of string?

Implementation Planning is required to define

  • how long the string will be,

  • where you will get the string,

  • who will cut it and

  • how much this will cost.


Definition
Definition calculated preparation…’ (GCRH, 2002)

  • ‘…Implementation Planning ensures the compatibility of the planning and budgeting processes to support …[strategic goals]…It prescribes commensurate milestones, resource requirements, schedules and performance criteria at both the program and task levels…’ (NASA, 1996)


The Crouch Diagram calculated preparation…’ (GCRH, 2002)

Why are we in business?

How do we do business?

Where are we now?

Where do we want to be?

  • Tactics

  • Resources

How do we get there?

How will we know we’ve arrived?


The Crouch Diagram calculated preparation…’ (GCRH, 2002)

Why are we in business?

How do we do business?

Where are we now?

Where do we want to be?

How do we get there?

  • Co-Ordination

  • Budgets

  • Controls

  • Reports

  • Milestones

How will we know we’ve arrived?


Implementation planning is an information intensive process
Implementation Planning is an Information Intensive Process calculated preparation…’ (GCRH, 2002)

There is a need to communicate both

  • the detail

  • the vision


Implementation planning is an information intensive process1
Implementation Planning is an Information Intensive Process calculated preparation…’ (GCRH, 2002)

  • Implementation Planning (Gray and Larson, 2002, p.89)

    • provides the basis of scheduling labour and equipment;

    • determines how much money is required

    • becomes an instrument that melds managers and groups together into meeting time, cost and performance objectives

    • answers the question how long is it going to take?


Information intensive process es are usually
Information Intensive Process calculated preparation…’ (GCRH, 2002)es are usually…

  • Information Intensive Processes are usually those that must deal with a high degree of uncertainty. We must try to fill this void (create certainty) with information.

  • With that we are plagued with the normal information management problems of communication, structuring information, information overload, tacit knowledge etc…


P ractical example of an implementation plan
P calculated preparation…’ (GCRH, 2002)ractical Example of an Implementation Plan

  • Northern Territory University’s Callista Project (Student Records System)


Essential question 1 courtesy of commworks 2001
Essential Question 1. calculated preparation…’ (GCRH, 2002)(Courtesy of Commworks, 2001)

  • What is the timeline for networkdeployment?


Essential question 2 does your budget support the timeline
Essential Question 2 calculated preparation…’ (GCRH, 2002) - Does your budget support the timeline?

Work package cost estimate

Gray & Larson, 2000, Figure 3-8


Essential question 2 does your budget support the timeline1

$6,000 calculated preparation…’ (GCRH, 2002)

5,000

4,000

Costs

3,000

2,000

Committed

Actual cost

1,000

Scheduled budget

Project Duration

Essential Question 2 - Does your budget support the timeline?

Gray & Larson, 2000, Figure 3-9


Essential question 3 have you accounted for all tasks required to deploy the network

Complete project calculated preparation…’ (GCRH, 2002)

1

Project

Major deliverables

2

Deliverable

Supporting deliverables

Subdeliverable

3

Lowest managementresponsibility level

4

Lowest subdeliverable

Grouping of work packagesfor monitoring progress andresponsibility

5

Cost account*

Work package

Identifiable work activities

Essential Question 3 - Have you accounted for all tasks required to deploy the network?

Gray & Larson, 2000, Figure 3-3


Personal computer calculated preparation…’ (GCRH, 2002)prototype

Level1

Moreitems

1.0

1.3

1.1

1.4

1.2

Vendor,software,applications

Mouse,keyboard,voice

Microprocessorunit

Diskstorageunits

2

1.4.1

1.4.2

~

~

1.1.1

1.1.2

1.1.3

Internalmemoryunit

BIOS (basicinput/outputsystem)

3

Floppy

Optical

Hard

~

~

1.4.1.1

1.4.1.2

1.4.2.1

1.4.2.2

1.4.2.3

4

RAM

ROM

I/O

File

Utilities

~

~

~

~

~

Lowest manageablesubdeliverables

1.1.3.1

1.1.3.2

1.1.3.3

1.1.3.4

5

Chassisframe

Circuitboard

Read/writehead

Motor

Cost accountnumber

Cost 1.1.3.4.1 account Cost Cost account account Cost Cost account account Cost account Cost account

Design

Manufacturing

Production

Work packages WP1.1.3.4.2.1 WP1.1.3.4.2.2 WP1.1.3.4.2.3

Organization

Test

Purchasing

Budget byperiod

Software

Gray & Larson, 2000, Figure 3-3


Essential question 4 who will do the work required to deploy the network
Essential Question 4 calculated preparation…’ (GCRH, 2002) - Who will do the work required to deploy the network?


Essential Question 5 calculated preparation…’ (GCRH, 2002) - Do you have a strong Project Manager in place to coordinate aspects of deployment?


Essential question 6 who will manage all of the vendors needed for deployment
Essential Question 6 calculated preparation…’ (GCRH, 2002) - Who will manage all of the vendors needed for deployment?


Question
Question calculated preparation…’ (GCRH, 2002)

  • Are Implementation Planning processes the same for small projects as for large projects?


Project network

Risk calculated preparation…’ (GCRH, 2002)

Cost

High

Cost to fixrisk event

Chances of risksoccurring

Low

Project life cycle

Project Network

  • ‘…The project network represents ¾ of the planning process…’ (Gray and Larson , 2000, p. 90). Why?

Gray and Larson, 2000,

Figure 5-1


A calculated preparation…’ (GCRH, 2002)

B

C

Level 1 - Milestone Plan

D

E

F

Level 2 - Plans

Level 3 - Plans

WP-1

WP-4

WP-3

WP-2

Gray and Larson, 2000, p. 91


The project network melds managers workers together
The Project Network melds managers, workers…together calculated preparation…’ (GCRH, 2002)

  • Level 1 – Milestones – used by Project Management, Top management and the client.

  • Level 2 – Work packages shown in relation to each other for Department Managers

  • Level 3 – Work packages used by first-line managers


Lowest calculated preparation…’ (GCRH, 2002)element

Circuitboard

BP-10-1

AD-1-1D-1-2

DP-10-2

FS-22-2

KT-13-1

Designcostaccount

OrganizatioUnits

DesignWP D-1-1 SpecificationsWP D-1-2 Documentation

CS-22-1

Productioncostaccount

ProductionWP P-10-1 Proto 1WP P-10-2 Final Proto 2

BProto 15

Testcostaccount

Test systemsWP T-13-1 Test

ASpecificationsand documentation2

DFinalproto 24

FFinalsoftware2

KTest3

Softwarecostaccount

SoftwareWP S-22-1 Software preliminaryWP S-22-1 Software final version

CPreliminarysoftware3

Figure 4-2

Gray and Larson, 2000, p. 92


Legend calculated preparation…’ (GCRH, 2002)R = ResponsibilityC = ContributesA = Advises

OrganizationUnit/Individual

Activities

Gray and Larson, 2000,Figure 4-10


Constructing a network
Constructing a Network calculated preparation…’ (GCRH, 2002)

  • Networks flow typically left to right

  • An activity cannot begin until all preceding activities have been completed

  • Arrow on each network indicate precedence and flow. Arrows can cross over each other

  • Each activity should have a unique identification number

  • An activity number must be larger than that of any activities that precede it.

  • Looping is not allowed

  • Conditional statements are not allowed

  • A common start and end node clearly delineates start/finish respectively


B. calculated preparation…’ (GCRH, 2002)

Boil Jug

5

Approval

A.

C.

Rinse Pot

E.

Make Tea

F.

Serve Tea

1

1

5

1

D.

Milk Sugar

1


Critical time path free slack
Critical Time Path calculated preparation…’ (GCRH, 2002) & Free Slack

  • The Critical Time Path is the longest path through the network. If one of the activities on this path is delayed the project completion time will be extended.

  • Free slack refers to those activities that are not critical and who’s start/finish time can be varied (e.g to suit resource allocation)


Calculating critical time path free slack
Calculating calculated preparation…’ (GCRH, 2002)Critical Time Path & Free Slack

  • Forward Pass (start with first activity)

    • How soon can an activity start? (Early Start – ES)

    • How soon can the activity finish? (Early Finish – EF)

    • How soon can the project finish?

  • Backward Pass (start with last activity)

    • How late can an activity finish? (late finish – LF)

    • How late can an activity start? (late start – LS)


ES EF calculated preparation…’ (GCRH, 2002)

0 Boil Jug

1 B. 6

SL

1 5 6

LS Dur LF

ES EF

ES EF

ES EF

ES EF

0 Approval

0 A. 1

4 Rinse Pot

1 C. 2

6 E. 11

0 Make Tea

11 F. 12

0 Serve Tea

SL

SL

SL

SL

0 1 1

5 1 6

6 5 11

11 1 12

LS Dur LF

LS Dur LF

LS Dur LF

LS Dur LF

ES EF

9 Milk Sugar

1 D. 2

Items that have SL = 0

are Critical Path Activities

Items that have SL >0 are

activities with Slack

SL

10 1 11

LS Dur LF


Scenario 1
Scenario calculated preparation…’ (GCRH, 2002)1

  • A Project leader for a television news organisation had been working on a major refurbishment of the operational area. The changes included new data cabling and new terminals for about 20 journalists. New video and audio facilities were to be provided to enable journalists to monitor news from other stations. The plan was to move all operations to another floor while work took place. Projects groups were surprised to learn one day that the project manger was redeployed and that the new project manager had been given the directive to get the work done over a single night. This was subsequently organised and executed 2 months later. Though the new installationsuffered minor ongoing commissioning problems for some months after, the change in project implementation schedule was generally viewed as a success.

  • Why was this so?


Why shorten the critical path
Why calculated preparation…’ (GCRH, 2002) shorten the critical path?

  • Imposed project finish date:

    • Unforeseen event

    • Political or marketing reason

      • The need to get a software product out in order to grab market share

  • Shortening the critical path will usually result in higher cost.


The cost equation

60 calculated preparation…’ (GCRH, 2002)

Total

costs

Optimumcost-timepoint

50

40

Low-costplan duration

point

30

Costs

Direct

costs

20

Indirect

costs

10

0

4

6

8

10

12

14

16

Project duration

The cost equation…

Direct Costs – labour, materials, equipment

Indirect costs – overheads such as administration, consultants, interest

Gray & Larson, 2000, Figure 6-1


How to shorten the critical path
How to shorten the Critical Path calculated preparation…’ (GCRH, 2002)

  • Reduce quality (not recommended)

  • Use better technology (machine, methods etc)

    • e.g Outsource

  • Work longer hours

  • Reassign labour to critical path activities (eg outsource non-critical activities to enable internal specialist staff to be redeployed).

    • A management and communication penalty exists if too many people are required to coordinate their activities within a single task.


References
References calculated preparation…’ (GCRH, 2002)

  • Gray, Clifford F and Larson, Erik W. 2000, Project management : the managerial process / Irwin/McGraw-Hill,Boston.

  • NASA, 1996 ‘NASA Strategic Management Handbook’, NASA. Available at: http://www.hq.nasa.gov/office/codez/strahand/implemen.htm Accessed on: 12 August 2002

  • Karunaratne, Ishan 2002, ‘Callista Implementation Project’, Northern Territory University, Available from: http://mindil.ntu.edu.au/ntu/apps/callistaimp.nsf/vwURL/Implementation+Planning?OpenDocument Accessed; on 12 August 2002

  • Commworks, 2001, ‘As you Implement: Planning for Deployment’. Commworks Available from http://www.commworks.com/Professional_Services/Implement/Planning_Deployment/ Accessed on 12 August 2002.

  • GCRHCorporation 2002, ‘Implementation Planning: When its Got to be Appropriate, Now’, GCRHCorporation, Midland Michigan. Available from http://www.rightanswer.com/english/plan.html Access on 12 August 2002.


ad