1 / 63

Lake Team 2001

Lake Team 2001. A rchitect: Robert Williamson, U.C. Berkeley E ngineers: Dominik Weiss, FHA, Switzerland Markus Mathys, FHA, Switzerland C onstruction Manager: Ravi Raghu, Stanford Owner: Peter Demian. Winter Quarter Presentation

hank
Download Presentation

Lake Team 2001

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lake Team 2001 Architect: Robert Williamson, U.C. Berkeley Engineers: Dominik Weiss, FHA, Switzerland Markus Mathys, FHA, Switzerland Construction Manager: Ravi Raghu, Stanford Owner: Peter Demian Winter Quarter Presentation March 16, 2001

  2. Site Context • Situated on Lake Geneva, Switzerland • Surrounded by the Alps • Nearly flat site

  3. Site Location • 10, 108 sq. ft. footprint • Clear view to the lake • Easily accessible by two roads

  4. Climate • 20°C mean temperature in summer • Annual snow fall – 30in • 3 months of continuous snowing (incentive to enclose the site before snowfall begins)

  5. Humus Good gravel Lake Geneva Water plate Soil Conditions • Soil conditions – excellent gravel • Easy to excavate • Safety regulations: 1:1 or 1:2 sloping allowed. Beyond that use sheet piles

  6. Equipment • Based on capacity and requirement • After analysis of different available equipments (Capacity 1.54m3) • Backhoe • Crane • Dump trucks • Concrete pump

  7. Equipment Mobile Crane – Boom 54m

  8. Site Plan • Bonus double access roads • Can divert traffic if needed and use the other side of the road • Mobile crane

  9. A New Design #1 Concept Development • Respond to the site • Create an icon for the University Surrounding mountains inspired the idea of protruding elements at various angles.

  10. A 1st Iteration Entrance Circulation Small Classrooms Auditorium Large Classrooms Lab Seminar Room Initial 1st floor plan

  11. A 2nd Iteration • Provides more assignable floor area for required spaces • Based on simpler structural system • Circulation is clearer • Less expensive Auditorium Large Classrooms Small Classrooms Seminar Rooms Storage Circulation

  12. Plans and Sections A 2nd Floor 3rd Floor 1st Floor Labs/Computer Room Small Classrooms Seminar Rooms Student Offices Faculty Offices Faculty Lounge Auditorium Large Classrooms Small Classrooms Seminar Rooms Storage

  13. E Mountain Concept general considerations • Auditorium • with firm seating 4kN/m2 • Other areas 5kN/m2 • Other areas • General 3kN/m2 • Balcony, stairs 4kN/m2 • Snow • On the flat roof 0.9kN/m2 • Wind • Max. wind load 1.4kN/m2

  14. E Mountain Concept 1st alternative: steel-concrete-composite 5.10m 6.70m 4.28m • Columns are made of structural steel • Ceilings are composite steel and concrete • Stabilization through an elevator core and two moment resisting frames in the facade. • Strip foundation 7.55m 8.23m 6.38m 14.0m Main girder Secondary girder 23.16m

  15. E Mountain Concept 1st alternative: steel-concrete-composite 5.10m 6.70m 4.28m • The red line are moment resisting frames • Are dimensioned for the blue loads • All other steel members are connected to the concrete 7.55m 8.23m 6.38m 14.0m Main girder Secondary girder 23.16m

  16. E Mountain Concept 1st alternative: steel-concrete-composite • Large steel members with smaller secondary girders • No extra columns in the auditorium Large Classrooms Steel member 4.65m 5.93m Auditorium 11.84m 4.45m

  17. E Mountain Concept 1st alternative: steel-concrete-composite • High construction height. The secondary girder on top of the main girder • The secondary girder between a main girder. Small construction height. 150mm 150mm Concrete flooring h=150mm 360mm Metal sheet 360mm Secondary girder h=360mm Main girder h=450mm 450mm 450mm

  18. E Mountain Concept 1st alternative: steel-concrete-composite • Connection between a main girder and two columns • Connection between a main girder and two secondary girder Concrete flooring h=150mm Screw (shear) column H=140mm Metal sheet Flat bar Secondary girder h=360mm Main girder Tongue with two screws Flat bar Main girder h=450mm Screw (shear) column H=140mm

  19. E Mountain Concept foundation alternative: • Plate foundation • Strip Foundation • The bed plate will be the foundation. If necessary there will be different heights of the plate. • Strip/spread foundation. Between the foundation a swimming bed plate columns columns Swimming bed plate 0.5m 0.5m 0.5m 0.5m 2.0m 2.0m Bed plate with different heights

  20. C Mountain Concept Alternative 1

  21. C Mountain Concept Alternative 1

  22. C Mountain Concept Alternative 1 Total cost of the design alternative $5.28M

  23. C Mountain Concept Alternative 1 January1, 2015 June 15, 2015

  24. C Mountain Concept Alternative 1 • End construction – June 15th • Resource allocation considered in the schedule • Steel construction aids the fast completion • Can create a closure early to prevent weather delays • Lead time for procurement high

  25. E Mountain Concept 2nd alternative: concrete 5.10m 6.70m 4.28m • columns and plates made out of concrete • One elevation core and two shear walls to stabilize the building • The ceiling is jointed with the walls in the auditorium • Foundation plate 7.55m 8.23m 6.38m 14.0m 23.16m

  26. E Mountain Concept 2nd alternative: concrete 5.10m 6.70m 4.28m • As an example the load path for wind load • Clamped shear walls to guide the loads to the foundation 7.55m 8.23m 6.38m qWind 14.0m 23.16m

  27. E Mountain Concept 2nd alternative: concrete • Using the walls in the classrooms to support the ceiling of the auditorium • Just one column in the whole auditorium • Classroom walls made of concrete Large Classrooms Arched vault column 4.65m 5.93m Terrain Auditorium 11.84m 4.45m

  28. E Mountain Concept - Solution2nd alternative: concrete • Connection from a column to the ceiling • Connection from the wall to the ceiling of the auditorium 30cm column Reinforcement 30cm Reinforcement Wall classroom 35cm Ceiling 2nd floor 35cm column Ceiling auditorium

  29. C Mountain Concept Alternative 2 • Concrete framing system cheaper than the steel one • Trade off in time • Total cost of concrete alternative – 4.91m • Timeline – Jan 1st to Jul 13th

  30. C Mountain Concept Alternative 2 • Total framing cost of $612382 as opposed to $762109 for the steel framing

  31. A New Design #2 Concept Development • Central atrium can divide the building into a private sector and a public sector • All vertical movement can be contained within the circular atrium • Atrium creates a central gathering space

  32. 1st Iteration A E Auditorium Large Classrooms Small Classrooms Seminar Rooms Labs/Computer Room Student Offices Faculty Offices Storage

  33. 2nd Iteration A E • 2 cores will contribute to a better structural solution and result in a lower cost

  34. Atrium ConceptConstruction E Iteration: 1st alternative: 2nd alternative: steel-concrete- composite masonry-concrete

  35. Atrium Concept 1st alternative: steel-concrete-composite E 1st/2nd/3rd floor: • steel columns  vertical forces • moment resisting frames and diagonals  lateral and vertical forces

  36. Atrium Concept1st alternative: steel-concrete-composite E Slab: • main beams • built-up girders • concrete slab view spans: 6-8m spans: 7-11.6m section

  37. Atrium Concept1st alternative: steel-concrete-composite E View at shearwall: see detail Section through Auditorium:

  38. Atrium Concept1st alternative: steel-concrete-composite E • screw connections • no shear studs (partial composite action) • single span built-up girders

  39. Atrium Concept Alternative 1 C • Total framing cost of $786720 for the steel framing • Simpler exterior glazing • Total project cost – $5.4m • Timeline – Jan 1st to June 28th

  40. Atrium Concept Alternative 1 C • Constructibility issues • Partially Composite design recommended • 100% composite action not easy to construct • Connections in MRF not as critical because of no seismic effect

  41. Atrium Concept 2nd alternative: masonry-concrete E View to lake 1st Floor: • reinforced masonry • concrete slab and columns • main beams aboveauditorium atrium main beams

  42. Atrium Concept2nd alternative: masonry-concrete E 2nd / 3rd floor: • masonry • concrete slab and columns section

  43. Atrium Concept2nd alternative: masonry-concrete E Longitudinal section of auditorium: Detail of slab and main beam:

  44. Atrium Concept2nd alternative: masonry-concrete E Cross-section of slab and main beam above auditorium:

  45. Atrium Concept Details E Foundation below auditorium and large classrooms: General foundation:

  46. Atrium ConceptDetails E Glass dome above atrium:

  47. Atrium Concept Alternative 2 C • Total framing cost of $597589 as opposed to $786720 for the steel framing • Total project cost – 4.97m • Timeline – Jan 1st to august 12th

  48. Materials Choices C • Options considered for concrete – Precast vs. Cast in place • Precast economically infeasible

  49. Steel Vs Concrete Sequencing Issues Sequencing Issues C Erection Excavation

  50. New Designs at a glance C Cost Breakdown

More Related