industrial distribution warehouse
Download
Skip this Video
Download Presentation
Industrial Distribution Warehouse

Loading in 2 Seconds...

play fullscreen
1 / 15

Industrial Distribution Warehouse - PowerPoint PPT Presentation


  • 96 Views
  • Uploaded on

Industrial Distribution Warehouse. Abigail Bush Joseph Friesenhahn Hank Hampton Ralph Morfin Rusty Staudt. Project Team. Project Overview. 3019 NE Loop 410 San Antonio, Texas At intersection of Loop 410 and IH35 12.048 acres Zoning - Industrial

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Industrial Distribution Warehouse' - hamish


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
industrial distribution warehouse

IndustrialDistribution Warehouse

Abigail Bush

Joseph Friesenhahn

Hank Hampton

Ralph Morfin

Rusty Staudt

December 7, 2013

project overview
Project Overview
  • 3019 NE Loop 410
  • San Antonio, Texas
  • At intersection of Loop 410 and IH35
  • 12.048 acres
  • Zoning - Industrial
  • Adjacent to Perrin Beitel Creek and its Tributary
  • Titan Perrin Creek Development, Phase II

Staudt

data collection
Data Collection
  • Review Data
    • Survey
    • Geotechnical
    • Tree Survey
  • Grading

Staudt

utility coordination
Utility Coordination
  • CPS
    • Overhead
      • Primary
      • Secondary
  • SAWS
      • 30” RCP Sewer Main
      • 30” CSC Water Main

Hampton

traffic analysis
Traffic Analysis
  • Traffic Impact Analysis
    • Phase I
  • TxDOT Permits
    • Driveway
    • Waterline on frontage
  • Paving Plan

Hampton

environmental
Environmental
  • Environmental Impact
  • SW3P
  • Erosion Control

Bush

hydrology and hydraulics
Hydrology and Hydraulics
  • Floodplain Development Permit
    • Parking lot with flood depth < 6”
    • Ineffective flow
  • Impact to WSEL

Bush

drainage
Drainage
  • Mandatory Detention Area
  • Evaluate existing facility
  • Stub out 2-24” pipes for development

Bush

building design
Building Design
  • Project consists of a 50,000-SF steel, build-to-suit office and distribution facility in Titan Perrin Creek

Friesenhahn

structure and foundation
Structure and Foundation
  • Structural Codes:
    • ASCE 7-05
    • AISC 13th Edition
    • IBC 2009
  • Slab on Grade

Friesenhahn

additional services
Additional Services
  • Fire Protection Plan
  • Landscape Architecture

Morfin

project schedule
Project Schedule

May

March

January

February

April

Preliminary

Intermediate

Final

Morfin

ad