The Nature of Project Management. Characteristics of Projects : purpose, life cycle, interdependencies, uniqueness, and conflict. Project Management Process : planning (work breakdown structure), scheduling, and controlling.

hallam
Download Presentation

The Nature of Project Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Nature of Project Management • Characteristics of Projects: purpose, life cycle, interdependencies, uniqueness, and conflict. • Project Management Process: planning (work breakdown structure), scheduling, and controlling. • Selecting the Project Manager: credibility, sensitivity, ability to handle stress, and leadership. • Building the Project Team: Forming, Storming, Norming, and Performing. • Principles of Effective Project Management: direct people individually and as a team, reinforce excitement, keep everyone informed, manage healthy conflict, empower team, encourage risk taking and creativity. • Project Metrics: Cost, Time, Performance

  2. Work Breakdown Structure 1.0 Move the hospital (Project)1.1 Move patients (Task) 1.1.1 Arrange for ambulance (Subtask) 1.1.1.1 Prepare patients for move 1.1.1.2 Box patients personnel effects1.2 Move furniture 1.2.1. Contract with moving company • • •

  3. Project Management Questions • What activities are required to complete a project and in what sequence? • When should each activity be scheduled to begin and end? • Which activities are critical to completing the project on time? • What is the probability of meeting the project completion due date? • How should resources be allocated to activities?

  4. Tennis Tournament Activities Activity Description Immediate Duration Designation Predecessor (days) Negotiate for Location A - 2 Contact Seeded Players B - 8 Plan Promotion C A 3 Locate Officials D C 2 Send RSVP Invitations E C 10 Sign Player Contracts F B,C 4 Purchase Balls and Trophies G D 4 Negotiate Catering H E,F 1 Prepare Location I E,G 3 Tournament J H,I 2

  5. Notation for Critical Path Analysis Item Symbol Definition Activity duration t The expected duration of an activity Early start ES The earliest time an activity can begin if all previous activities are begun at their earliest times Early finish EF The earliest time an activity can be completed if it is started at its early start time Late start LS The latest time an activity can begin without delaying the completion of the project Late finish LF The latest time an activity can be completed if it is started at its latest start time Total slack TS The amount of time an activity can be delayed without delaying the completion of the project

  6. Tennis Tournament Activity on Node Diagram TS ES EF LS LF A2 C3 D2 G4 START E10 I3 J2 B8 F4 H1

  7. Incorporating Uncertainty in Activity times F(D) P(D<A) = .01 P(D>B) = .01 TIME A M D B optimistic most pessimistic likely

  8. Formulas for Beta Distribution of Activity Duration Expected Duration Variance Note: (B - A )= Range or

  9. Activity Means and Variances for Tennis Tournament Activity a m b ET Variance A 1 2 3 2 4/36 B 5 8 11 8 36/36 C 2 3 4 3 4/36 D 1 2 3 2 4/36 E 6 9 18 10 144/36 F 2 4 6 4 16/36 G 1 3 11 4 100/36 H 1 1 1 1 0 I 2 2 8 3 36/36 J 2 2 2 2 0

  10. Uncertainly Analysis Assumptions 1. Use of Beta Distribution and Formulas For D and V 2. Activities Statistically Independent 3. Central Limit Theorem Applies ( Use “student t” if less than 30 activities on CP) 4. Use of Critical Path Activities Leading Into Event Node Result Project Completion Time Distribution is Normal With: For Critical Path Activities For Critical Path Activities

  11. Completion Time Distribution for Tennis Tournament Critical Path ActivitiesDV A 2 4/36 C 3 4/36 E 10 144/36 I 3 36/36 J 20 = 20 188/36 = 5.2 =

  12. Question What is the probability of an overrun if a 24 day completion time is promised? Days 24 P (Time > 24) = .5 - .4599 = .04 or 4%

  13. Activity Cost-time Tradeoff Cost Crash C* Slope is cost to expedite per day Normal C D* D Activity Duration (Days)

  14. Cost-Time Estimates for Project

  15. Progressive Crashing B A D C

  16. Progressive Crashing • Using Normal Times, What is the critical path? A-B-D : 10 days (Critical Path) A-C-D : 9 days • Using Normal Times, How long is the project expected to take? Critical Path Time : 10 days • Using Normal Times, How much will the project cost? Normal Cost to complete A,B,C,D = 6+9+6+5=$26

  17. Progressive Crashing