Absorber Integration Issues

Absorber Integration Issues. Shigeru Ishimoto KEK. MICE CM21, Jun-06, 2008, Daresbury Lab., England. OUTLINE. 1) MICE Absorber Design by KEK & MIRAPRO 2) MICE Test Cryostat at KEK 3) Instrumentation 4) Grant-in-Aid Fund 5) Absorber Schedule 6) Summary and Plan. AFC Module with

hailey
Download Presentation

Absorber Integration Issues

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Absorber Integration Issues Shigeru Ishimoto KEK MICE CM21, Jun-06, 2008, Daresbury Lab., England

  2. OUTLINE 1) MICE Absorber Design by KEK & MIRAPRO 2) MICE Test Cryostat at KEK 3) Instrumentation 4) Grant-in-Aid Fund 5) Absorber Schedule 6) Summary and Plan

  3. AFC Module with MICE Absorber Mini-Flanges (In-Seal) G10 Supports LH2 IN 30 Pin Feedthrough

  4. MICE Test Absorber MLI wrapped MLI --- 1 layer Al-Mylar 9m x5 + Polyester Mesh x6 Window 1 layer Body 4 layers

  5. H2 gas tank (2000 l) Cryocooler Bendix 18 pin connector x2 TMP H2 press.transducer Top view of test cryostat

  6. KEK Design He/N2 OUT G-H2 OUT Tee  L-H2 IN He/N2 IN 30 Pin Feedthrough

  7. MICE Absorber Design by MIRAPRO

  8. MICE Absorber Design by MIRAPRO

  9. MICE Absorber Design by MIRAPRO

  10. MICE Absorber Design by MIRAPRO

  11. MICE Absorber Design by MIRAPRO

  12. MICE Absorber Design by MIRAPRO Hole for Heater 2 Holes for Heaters

  13. Support Flange for Pipe Welding

  14. Detail of Flange and G-10 Support G-10 (x8) t=1, W=25, L=90 mm Total ~ 0.2 W 34 SS f15.7 6.5 7 SS, t=1 34 Screws on AFC Magnet AL f14.8 From Absorber

  15. Instrumentation of Sensors & Heaters

  16. Grant-in-Aid Fund for MICE The MICE-Japan group have received funding for MICE of a few 100k euro for 3 years (from 2008 to 2010). We will contribute to MICE more than ever and will be able to construct LH2 absorbers and others. - Yoshi KUNO - Yoshitaka Kuno Osaka Leader of JICE-Japan Makoto Yoshida Osaka SciFi Akira Sato Osaka DAQ, Trigger Yasushi Arimoto Osaka Beam Monitor Koji Yoshimura KEK VLPC, Detector Shigeru Ishimoto KEK LH Absorber 2 LH Absorber in FY2008 1 LH Absorber body in FY2009

  17. Aspirational MICE Schedule m STEP I Febuary-May 2008 ? STEP II June 2008 STEP III.1 December 2008 STEP IV Delivery of 1st FC Oct 2009 STEP V Spring 2010 STEP VI Q4 2010 -- 2011

  18. MICE Absorber Schedule STEP V STEP IV STEP VI Spring 2010 Delivery of 1st FC Oct 2009 Q4 2010 -- 2011 CM21 Comments *Monpower at KEK & RAL *Needs colaboration with US group Information of window flange, LakeShore parts

  19. Summary and Plan 1) MICE Absorber Design by KEK & MIRAPRO - Design and Cost Estimation are finalizing - Information of Real windows is missing 2) MICE Test Cryostat at KEK - Ready for test MICE absorber 3) Instrumentation - Almost finalized, needs thermometer block design 4) Grant-in-Aid Fund - a few 100k euro for 3 years (from 2008 to 2010) 5) Absorber Schedule - manpower at KEK & RAL

  20. Thank you...