Draughton 16 th April 2014. John Moore Chief Executive NYnet. Areas we will cover. BT rollout – Phase 1 Lessons learnt to date How to address final 10%? Phase 2 Phase 3 Demand stimulation. Reminder of our Vision. Access to high-quality broadband for 100% of North Yorkshire premises

Download Presentation

Draughton 16 th April 2014

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Draughton 16 th april 2014

Draughton16th April 2014

John Moore

Chief Executive

NYnet


Areas we will cover

Areas we will cover

BT rollout – Phase 1

Lessons learnt to date

How to address final 10%?

Phase 2

Phase 3

Demand stimulation


Reminder of our vision

Reminder of our Vision

Access to high-quality broadband

for

100% of North Yorkshire premises

by

2017


Draughton 16 th april 2014

To secure >> than average levels of broadband take-up, both residentially and by SMEs


Bt rollout phase 1

BT Rollout – Phase 1

Key contract terms (Intervention Area)

77% access to min 25Mbps

100% access to min 2Mbps

Completion by October 2014

Mostly FTTC

Some FTTP (3%)

cont …


Bt rollout phase 11

BT Rollout – Phase 1

Headlines

462+ of 670 cabinets completed

110,000+ of 150,000 total premises now able to access superfast speeds (25+Mbps)