slide1
Download
Skip this Video
Download Presentation
Industrial Training Presentation

Loading in 2 Seconds...

play fullscreen
1 / 11

Industrial Training Presentation - PowerPoint PPT Presentation


  • 153 Views
  • Uploaded on

Industrial Training Presentation. Presentation Intro. Summary: I had my industrial training in VISL Bhadravathi,Karnatka . My work was focusing on finding energy saving opportunities in process. Presentation Topics: Details of my training Bhadravathi . Process Flow chart of Visl

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Industrial Training Presentation' - grover


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide2

Presentation Intro

  • Summary:
  • I had my industrial training in VISL Bhadravathi,Karnatka. My work was focusing on finding energy saving opportunities in process.
  • Presentation Topics:
  • Details of my training Bhadravathi.
  • Process Flow chart of Visl
  • Suggestion and Findings.
slide3

Training History

Work Sequence:

First 10 Days Understanding the Steel making at VISL and finding energy saving opportunities.

Next 7 Days Work had focused on developing strategies to save energy and workout technical feasibility of suggestions.

Last 4 Days Writing the final report to submit to VISL.

slide5

Work Contribution

  • Findings and Suggestions
    • .BOF Oxygen blowing end point determination. Due to manual determination of end of blow point of oxygen, lot of iron is getting wasted as slag. This reduces the yield factor of the BOF process and increases the amount of CO2 gas released into the atmosphere. If a dynamic model can be implemented on the basis of flue gas composition and temperature, productivity and the yield factor of BOF process can be significantly improved.
    • In Cooling Tower possibility 11.25 kW power generation with of 3 micro Hydel power plant .
slide6

Work Contribution

Micro Hydel power Plant from cooling Tower

Height of tower(H)= 4m

Discharge(Q) = 0.375m3/sec= 375l /s

Efficiency( )= .75

The Tower has three outlet so we suggested three Micro Hydel power Plant.

slide8

BOF Automation

End Point Detection using Dynamic Method

slide9

BOF Automation

End Point Detection using Dynamic Method

slide10

Conclusion

  • Industrial Training Objectives fulfilled.
  • Problems faced during training.
  • Project Fulfilment:
    • Importance of Project for VISL
    • Door still open for improvement.
    • .
  • Benefits from Training.