An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. FUTURE EXPLOITATION OF THE EAST AREA Cooling and Ventilation issues EN-CV Michel OBRECHT

  2. Objectives • Ventilation • Cooling • Conclusion Cooling and Ventilation issues

  3. Ventilation : • Upgrade of the existing HVAC system for the next 25 years • Installation of air conditioning system for the primary zones • Cooling : • Separation of the cooling water circuit for the primary zones Objectives

  4. HVAC existing system : • Main Building : • heating system connected to the overheated water network • Distribution network • 8 Air Handling Units : 560 kW 80.000 m3/h • Radiant panels : 625 kW • Ratio : 0,39 W/m3*K • (SIA 380 standard : Ratio : 0,07 W/m3*K, 18% of existing) • Barracks and Offices : • 9 split system : 45 kW Ventilation : Upgrade of the existing HVAC system for the next 25 years

  5. HVAC existing system : Ventilation : Upgrade of the existing HVAC system for the next 25 years

  6. HVAC existing system : Ventilation : Upgrade of the existing HVAC system for the next 25 years

  7. Heat deperditions : improvements are needed for air tightness and insulation In order to avoid waste of energy and to improve ambient conditions, the insulation and the air tightness of the building has to be improved. Ventilation : Upgrade of the existing HVAC system for the next 25 years

  8. Proposed solution : • keep the existing configuration • improve the thermal performance of the building to as build situation • replace : • the 8 AHU • the overheated distribution network • the electrical installation • the instrumentation and PLC • the barracks HVAC system • Cost estimation : 985 kCHF Ventilation : Upgrade of the existing HVAC system for the next 25 years

  9. No existing system Proposed solution : similar to nTOF target zone Primary zone in underpressure <50 Pa HVAC system including HEPA filtration on air extraction Cost estimation : 260 kCHF Without proper air tightness, the underpressure and the static confinment shall not be achieved nor guaranteed Ventilation : Installation of air conditioning system for the primary zones

  10. RP requirement : avoid contamination of external demineralised water network User requirement : maintain the existing inlet temperature (25°C in summer) head loads : 700 kW Cooling : Separation of the cooling water circuit for the primary zones

  11. Proposed solution : • Installation of a seperate water circuit for primary beams • Including a new cooling station separated from the existing one • Cost estimation : 1.200 kCHF • Study to estimate water activation to be performed by RP • To be validated : • Operating modes (drains, access, maintenance, ...) • Location of new cooling towers, heat exchangers, pumps, ... Cooling : Separation of the cooling water circuit for the primary zones

  12. Conclusion • Cost estimation : • Upgrade of the existing HVAC system 985 kCHF • Installation of air conditioning system for the primary zones 260 kCHF • Dedicated cooling circuit for the primary zones 1.200 kCHF • Manpower : 1,25 FTE over 12 months • Taking into account the CV workload until the end of LS1 and priorities defined for that period, the project cannot start in the coming months • Related points : • Building infrastructure improvement • Barracks refurbishment Cooling and Ventilation issues

  13. Cooling and Ventilation issues Thank you for your attention