Timeline Leading to Development of the Beachside Sewer System – Phase I. October 2003 – Using Series 2003 Revenue Bonds, City acquired assets of Palm Coast Utility System from Florida Water Services including the utility “service area”

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Timeline Leading to Development of the Beachside Sewer System – Phase I' - giulio


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Timeline leading to development of the beachside sewer system phase i
Timeline Leading to Development of the Beachside Sewer System – Phase I

  • October 2003 – Using Series 2003 Revenue Bonds, City acquired assets of Palm Coast Utility System from Florida Water Services including the utility “service area”

  • July 2004 – McKim and Creed completed the “Beachside Master Plan”

  • January 2005 – Issued a Work Order to McKim and Creed to complete design of Beachside Master Pump Station and Force Main

  • February 2006 – Purchased property on A-1-A for the Master Pump Station site

  • December 2006 – City issued Series 2007 Revenue Bonds which included funds to construct Beachside Sewer System

  • October 2009 – Flagler County decided to abandon plans to construct Beverly Beach wastewater plant, instead connect to Palm Coast

  • November 2009 – Concept was presented to City Council

  • November 2009 – An easement to cross the intracoastal waterway was obtained from the Dunes Community Development District

  • February 2010 – First draft of an Interlocal Agreement between Palm Coast and Flagler was prepared by City staff

  • 2011–2012 – Beachside Sewer System is on the City council Goals and Objectives and shown as a “High Priority” project.

  • June 2012 – City Council approved the Interlocal Agreement with Flagler County