1 / 26

Guidance on New CEs Emergency Repair Projects Operational Right-of-Way Limited Federal Funds

Guidance on New CEs Emergency Repair Projects Operational Right-of-Way Limited Federal Funds. Email questions to: OES@dot.state.oh.us. 1. EUM – March 2014. MAP-21. Congress mandated that certain actions be categorically excluded from requirements related to EA’s and EIS’s

gerald
Download Presentation

Guidance on New CEs Emergency Repair Projects Operational Right-of-Way Limited Federal Funds

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Guidance onNew CEsEmergency Repair ProjectsOperational Right-of-WayLimited Federal Funds • Email questions to: OES@dot.state.oh.us 1 EUM – March 2014

  2. MAP-21 • Congress mandated that certain actions be categorically excluded from requirements related to EA’s and EIS’s • Section 1315 (Emergency repairs) • Section 1316 (Operational right-of-way) • Section 1317 (Limited Federal funds) 2 EUM – March 2014

  3. FHWA Rulemaking • Amended 23 CFR 771.117(c) to add new CEs • (c)(9) Emergency Repair Projects (2/19/13) • (c)(22) Operational Right-of-Way (2/12/14) • (c)(23) Limited Federal Funds (2/12/14) • Rulemaking did not change procedural requirements for approval of projects • Environmental requirements under Federal and State statutes and regulations still apply • e.g. Endangered Species Act, Public Involvement, EJ EUM – March 2014

  4. LevelofImpacts EUM – March 2014

  5. Documentation The new CEs are considered to meet the c-list (undocumented CE) criteria, however… • FHWA required documentation to ensure a higher level of NEPA document is not warranted • No significant impacts will occur • No unusual circumstances exist • An Environmental Verification Form was developed in accordance with rulemaking • Only for projects that meet new CE criteria • Shows due diligence performed EUM – March 2014

  6. No Anticipated Impact • Actions related to Emergency Repairs (c)(9), Operational Right-of-Way (c)(22), and Limited Federal Funds (c)(23), are not anticipated to have impacts to: • Air Quality & Noise (conduct proper studies, as appropriate) • Hazardous Materials (limited to petroleum related underground storage tanks/releases) • Farmland • Drinking Water • No documentation required EUM – March 2014

  7. No Significant Impact Specific environmental resource areas require documentation to illustrate allowable thresholds are not exceeded • Waterway Permits • Nationwide or Regional General Permits • May include PCNs • Endangered Species • No Effect orMay Effect, But Not Likely to Adversely Effect • 100-year Floodplain • No substantial impacts EUM – March 2014

  8. No Significant Impact • Section 4(f)/6(f) • No permanent incorporation of land or conversion • No 4(f), No Use, orExceptions (e.g. Temporary No Use), and Maintenance or Temporary Non-Conforming Use • Cultural Resources • Minimal Potential to Cause Effect or No Historic Properties Affected EUM – March 2014

  9. EJ and PI • For Operational Right-of-Way (c)(22) and Limited Federal Funds (c)(23), the following applies • Follow OES EJ Guidance • If an EJ Analysis Report is needed or if impacts rise to disproportionate and adverse, cannot apply new CEs • PI is commensurate to project’s type and scope EUM – March 2014

  10. Guidance EUM – March 2014

  11. FHWA • Based on FHWA Ohio Division correspondence of 2/18/2014, the new CE’s can be applied to projects in accordance with 23 CFR 771.117(c) • OES Guidance and Environmental Verification Form was accepted EUM – March 2014

  12. Exempt per CE PA • If a project qualifies as an Exempt Action Type under the existing CE PA, it can be processed as such with no additional documentation • Complete Online CE Exempt Form Tab EUM – March 2014

  13. Exempt Exceeded • When a project exceeds the limits of an Exempt Action Type under the existing CE PA, it may meet the criteria of one of the new CE’s • Environmental Verification Form required • Include documentation in Project File • Potential impacts to environmental resources will follow coordination requirements per ODOT’s typical environmental process • If thresholds exceeded altogether, a higher level of NEPA document would be required 13 EUM – March 2014

  14. 771.117(c)(9)Emergency Repair Projects EUM – March 2014

  15. Definition • Transportation facilities damaged by an incident resulting in an emergency declared by the Governor of the State or a disaster or emergency declared by the President • Damage must be caused by a natural disaster or a catastrophic failure from an external cause • The repair occurs within existing right-of-way and in a manner that substantially conforms to pre-existing design, function, and location EUM – March 2014

  16. Process • Perform Damage Survey Assessment • The assessment will help determine if a higher level of NEPA document is warranted based on the context and intensity of impacts • Prepare Damage Survey Report (DSR) • Upload to the Project File • Upload Environmental Verification Form • Document Level Tab is left blank • Exempt Form Tab not generated • EUM – March 2014

  17. 771.117(c)(22)Operational ROW EUM – March 2014

  18. Definition • ROW disturbed for an existing transportation facility OR Is maintained for a transportation purpose • See guidance for specific definitions/examples • Portions of ROW that have not been disturbed or that are not maintained for a transportation purpose do not qualify as existing operational ROW EUM – March 2014

  19. Temporary ROW • Temporary easements and takings needed for construction purposes are covered even if that work is located outside existing operational ROW • Areas acquired as temporary easements or ROW for past projects are not considered part of the existing transportation facility • Easements end once the original project is complete EUM – March 2014

  20. Process • Upload all pertinent documentation to the Project File • Upload Environmental Verification Form • Document Level Tab is left blank • Exempt Form Tab not generated • EUM – March 2014

  21. 771.117(c)(23)Limited Federal Funds EUM – March 2014

  22. Definition • A project must receive federal transportation funds in order to qualify under this CE • May include funds from a variety of Federal sources, but only applies to FHWA actions • Projects receiving limited funds are those that: • Receive less than $5,000,000 OR • Have a total estimated cost of not more than $30,000,000 and Federal funds comprise less than 15% of the total estimated project cost • Includes all phases EUM – March 2014

  23. Re-Evaluation • When federal funds for the project increase beyond established thresholds • An FHWA action needed when changes occur • FHWA approvals or grants needed during construction • If federal funds are in excess of the established threshold, the project will not qualify under (c)(23) EUM – March 2014

  24. Process • Upload all pertinent documentation to the Project File • Upload Environmental Verification Form • Document Level Tab is left blank • Exempt Form Tab not generated • EUM – March 2014

  25. Future Updates EUM – March 2014

  26. More to Come… • Another Final Rule to follow soon… • Four new c-list CE’s • Three d-list moving to c-list • Develop new CE PA • BIG changes to Online CE • Feature sets illustrating changes are in-process EUM – March 2014

More Related