1 / 15

5.1 Actions from 18 th Board meeting

5.1 Actions from 18 th Board meeting. Item 5.2.1.1.3 RSS Commissioning Plan: produced and circulated at Dec BEC Item 5.2.1.2 Aspen Workshop: to be postponed to 2008 (TW) Item 5.2.4.5 RFP solicitation to build & commission HRS

gerald
Download Presentation

5.1 Actions from 18 th Board meeting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 5.1 Actions from 18th Board meeting Item 5.2.1.1.3 RSS Commissioning Plan: produced and circulated at Dec BEC Item 5.2.1.2 Aspen Workshop: to be postponed to 2008 (TW) Item 5.2.4.5 RFP solicitation to build & commission HRS Postponed until feedback to KM from UC VC, Prof Roy Sharpe. Draft circulated at March BEC. Distributed to Board/SSWG and ready to circulate. • deadline for initial response (2 June?) • distribution ? Item 5.3.3.1 Science Productivity summary metrics from SSWG: No developments in light of suspension of full science ops. SSWG to consider before commencement of “Semester 1” & prior to Nov Board meeting 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  2. 5.2 Project Scientists Report 5.2.1 Summary of SSWG decisions: Image Quality DOD presented detailed IQ report to SSWG. Conclusions point to problem with SAC, particularly M4/M5. • Only way to get the observed field-dependent aberrations • Will potentially involve removal of SAC for realignment • Worst-case scenario could involve return to SAGEM, but option to align in SA much preferred • Will involve external expertise (e.g. Arek Swat, Larry Ramsey, John Booth, SAGEM) Motion: The SSWG thanks DOD for the effort led in IQ investigation and endorses the plan he has put forward to progress to a solution. 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  3. 5.2 Project Scientists Report 5.2.1 Summary of SSWG decisions: Near IR extension for RSS Andy Sheinis & Marsha Wolf presented Concept Design for the NIR extension of RSS • Development of option considered from Day 1 (provision for NIR beam provided by Ken Nordsieck) • Really a “Generation 1.5” instrument (will share part of existing RSS collimator) • Progress on sensitivity/background calculations since last meeting • Wavelength limit 1.54 to 1.71µm, depending on what is cooled • Debate on the capability/complexity of the instrument, and possible phased approach for adding additional capabilities • Cost ranges from $2.63M to $3.36M for proposed options and possibly less for less capability (TBD) • Funding proposed from combination of UW in-kind (part of Andy’s startup) and a bid for an NSF Major Research Instrument proposal. • Would not initially leverage SALT funding (until HRS completed) 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  4. 5.2 Project Scientists Report 5.2.1 Summary of SSWG decisions: Near IR extension for RSS (contd.) Motion: • SSWG reaffirms that HRS is the #1 priority for further instrument development • SSWG views favourably the construction of a NIR arm for RSS with design details yet to be agreed by the SSWG. The process for arriving at this agreement is the establishment of a SSWG subcommittee, to be constituted by the Project Scientist, to agree with the NIR Principal Investigator on the details of the instrument. • Contingent upon such an agreement, the SSWG will support the PI in his effort to raise funding, including providing support in his bid for an NSF MRI grant, including writing a letter of endorsement. The following persons have agreed to serve on the RSS-NIR subcommittee: DB (Chair), AS, RF, DOD, LWR, SD & TW 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  5. 5.2 Project Scientists Report 5.2.2 RSS Status Report • Report in Board papers (incl. Appendix by Steve Potter) • Many completion/commissioning issues • SALT Ops/SAAO assisting in these • Still involvement of RSS Team • Commitments of RSS Team members (e.g. Eric Burgh, Ken Nordiseck, Naseem Rangwala & Daniel Harbeck) to return at appropriate time for continued commissioning of RSS modes • Will happen once Payload subsystems/telescope is able to fully support RSS • Additional testing also required for modes before RSS goes “on-sky” with these (e.g. mechanism reliability tests) • ATP Process still underway • Biggest issue is the under-performance of the throughput of RSS, particularly in the UV-Vis 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  6. 5.2 Project Scientists Report 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  7. 5.2 Project Scientists Report 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  8. 5.2 Project Scientists Report 5.2.2 RSS Status Report Throughput Possible explanations for poor performance: • “colour centres” in annealed NaCl blanks (throughput never measured) • Bad/degraded anti-reflection coating(s) • but KHN claims all witness samples OK • Underperformance of CCDs QE • but SALTICAM CCDs are OK (even at 340 nm) SSWG Motion: The SSWG recognizes the significant progress made by the RSS and SALT Ops. Teams in bringing RSS to its current state. It shares the disappointment of the Teams over the recently determined throughput problems, especially in the UV/blue where SALT/RSS was designed to have a significant advantage. The SSWG therefore asks the RSS PI to present a plan of action to the BEC, no later the June meeting, to: • Identify/locate the source/sources of throughput losses • Propose appropriate solutions to remedy these losses 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  9. 5.2 Project Scientists Report 5.2.2 RSS Status Report Cost to Completion Update No update before Board paper written, but the PI has subsequently sent the following: Nominal Dollars 2005 Q2 2005 Q3 Delta UW $3,768,363 $3,787,111 $18,748 SAAO $559,492 $605,231 $45,739 RU $975,251 $975,251 $0 Total $5,303,106 $5,367,593 $64,487 Base dollars (adjusted for CPI) 2005 Q2 2005 Q3 Delta UW $3,361,682 $3,375,563 $13,881 SAAO $503,786 $544,425 $40,639 RU $852,892 $849,984 -$2,908 Total $4,718,360 $4,769,972 $51,612 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  10. 5.2 Project Scientists Report 5.2.2 RSS Status Report Cost to Completion Update The UW delta is due mostly to: • ~$5000 fringe benefits holdover from last year • ~$5000 unexpected expenses to fix the slit mask cutter • an overrun of $2000 for longslit polishing • $1500 for a new focus linear stage to get extra travel • $3500 overrun by vendor (Alan Schier) for the beamsplitter. Unsure of SAAO delta ($45K) reasons. • Known small amounts in shipping/handling • Total in SALT cash actuals is only R50K (R46K non-detector HBS) • KHN mixed $ & Rands ? Remaining costs associated with commissioning and Mike Smith slitmask redesign work (budgeted) 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  11. 5.2 Project Scientists Report 5.2.3 SALTICAM Status Report • In routine operation with no major faults/problems • Autoguider now fully designed, parts in manufactures, crucial components ordered • Series of modifications/fixes will be implemented when SALTICAM removed for Autoguider fitting (currently scheduled for late Aug) • Will be offline for 4-6 weeks • Planning to install newly arrived replacement for Clemens/Reichart camera (“Buckleycam”) in place of SALTICAM, using a “contraption”, during this time • Will then allow RSS slitviewing • Important for RSS continued commissioning • No revisions to SALTICAM Cost-to-Completion 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  12. 5.2 Project Scientists Report 5.2.4 HRS Status Report • No progress to report from PS side • PI reported at SSWG on some developments re. quotations for specific items • Optical fabrication (KiwiStar Optics) • Aspects of mechanical design (farmed out items, like vacuum tank) • No progress on Contract draft • No specification document produced yet (PS has requested of the PI a single spec. document to be based largely on the Critical Design Review documents, specifically the FPRD, OCDD and ICD) • will form Annexure to contract • Potential UC funding cover, as discussed between KM and UC VC at inauguration, has drawn a blank • Following BEC resolution, PS drafted open RFP from SALT Board to build HRS. Was circulated to Board/SSWG. Ready to distribute freely. • Who to ? • Deadline for expressions of interest (2 June) ? • Potential involvement of other parties • Poland, ATC Edinburgh, MSSSO? 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  13. 5.2 Project Scientists Report 5.2.4 HRS Status Report • Price to be specified in Contract based on UC’s post-CDR? estimate, minus expended non-cash contributions associated with design reviews (estimated at $389K, TBC) • Including 20% contingency on remaining expenditure, total remaining amount required to build HRS is estimated at ~$2.2M. • Funds available: • $250K immediately (original Polish top-up) • ~$350K (imminent Göttingen contribution from SALTICAM sale) • ~$215K (additional funds from UCLAN, but only released once HRS begin construction) [£117K definite according to GEB] • Total potentially available (in ~months?) of ~$815K • Remaining UC non-cash ~$244K (TBC) • PS (& SSWG/Board?) keen to learn from PI about any possible way forward given the UC stance of no work until all funds on deposit • Can subset of work begin on specific subsystems to the value of what funds are already committed? • How will UC respond to RFP? 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  14. 5.2 Project Scientists Report 5.2.5 FIF Status Report • Contracted with SAAO Machine shop to fabricate mechanical parts • PI acknowledges DOD’s support • Three stages of the translation stage completed • Revised BOM (Bill-of-Materials) received • Ordering of other components (precision rails, lead screws, etc.) underway • Assembly once items received • FIF S/W control on Payload schedule for later in 2006 • Design of interface for HRS fibre ferrules agreed to be responsibility of HRS Team • Modification required to original “bare fibre” interface due to HRS proposing A/R coated “window” cemented to fibre • Will manufacture one pair of bare fibre ferrules for testing • No revisions to FIF Cost-to-Completion 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

  15. 5.2 Project Scientists Report 5.2.6 Other Business • Delivery this week of “Dibnobcam” (aka Buckleycam) as replacement for the Clemenscam/DanCam. At last can return to Chris/Dan (with our thanks)! • MASS-DIMM instrument arrived (measures seeing as function of altitude) • Plan to build automated DIMM-MASS instrument, mounted on Meade LX200, atop ~5m tower (as at HET) • Measure Cn2 profile through atmosphere in real time • Useful to predict good seeing conditions • Future potential applications for A-O • May have some funds to purchase two RSS interference filters in UV • Good to test throughput • Science applicability • Motivating to purchase reflectometer/scatterometer to measure mirror reflectance/scattering from remaining construction funds • Useful to monitor mirror coatings • May be useful in measuring RSS throughput • Cost ~$9000 19th SALT Board meeting: 8 & 9 May 2006. Cape Town

More Related