LRS Report to PCC. Wally Gibson, NWPCC Planning Coordination Committee Spokane, WA June 26-27, 2008. PSA Status - 1. Will post draft for earlier review this year Generally same approach as last year Keeping same building block but updating calculations Contingency reserves

Download Presentation

LRS Report to PCC

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Lrs report to pcc

LRS Report to PCC

Wally Gibson, NWPCC

Planning Coordination Committee

Spokane, WA

June 26-27, 2008


Psa status 1

PSA Status - 1

  • Will post draft for earlier review this year

  • Generally same approach as last year

    • Keeping same building block but updating calculations

      • Contingency reserves

      • Regulating reserves

      • Additional forced outage reserves

      • Reserve for 1-in-10 weather driven load

  • Addressing additional temperature issues with scenarios

  • Unpredictable plant retirements (California cooling water)

    • Goal: Phase out once-through cooling, ~20,000 MW

    • Implementation schedule, details, effects unknown

    • Narrative on magnitude and issues, no full scenario


Psa status 2

PSA Status - 2

  • Breaking out planned resource classes further

  • 2007 PSA:

    • Class 1: Under construction, in service Jan 2011

    • Class 2: Active regulatory review, in service by Jan 2013

  • 2008 PSA

    • Class 1: Under construction, in service Jan 2012

    • Class 2: All permits approved and interconnection agreements signed and in service Jan 2014 -- small class

    • Class 3: Under regulatory review and facility study done with active negotiation of interconnection agreement and in service Jan 2014


Nerc adequacy reports

NERC Adequacy Reports

  • Long-Term Reliability Assessment (LTRA)

    • NERC asking for more detail on status of future resources, demand side and energy efficiency programs

      • Additional data requests – a likely future pattern

  • LTRA Scenarios

    • New emphasis for NERC – a big issue for them

    • 2009 Scenario: Accelerated renewable integration – 15% total energy from renewables by 2018

    • Build off TEPPC 2017 WIRAB case (20% CO2 reduction from 2005 levels)

    • Bring in results of other studies (e.g., CAISO, WWSIS)

    • Study plan approved by NERC PC, report due spring 2009


Future work

Future Work

  • Following NERC developments and working with Western participants on NERC resource adequacy-related task forces and subcommittees

    • Expect additional data requests for NERC studies

  • Expand analysis of energy constraints

  • Evaluating future use of Promod for adequacy assessments

  • Continuing to work with TEPPC on getting most efficient data gathering process