1 / 19

LCS Objectives

LCS Objectives. Provide a standard interface for lane closure operations, closure tracking, and data retrieval for WisDOT regional offices statewide

garry
Download Presentation

LCS Objectives

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCS Objectives • Provide a standard interface for lane closure operations, closure tracking, and data retrieval for WisDOT regional offices statewide • Facilitate data sharing with WisDOT applications that require lane closure data such as 511 Traveler Information, the STOC Incident Management System (IMS), Inconvenience Map production, and Oversize/Overweight (OSOW) permitting • Improve the completeness, reliability, and timeliness of lane closure data on state highways • Archive LCS data in the WisTransPortal system for future analysis and integration with other WisDOT / TOPS Lab traffic engineering applications and research • Integrate historical traffic flow data and capacity information to calculate available closure thresholds

  2. LCS Benefits • Coordinates activities to reduce back-ups and potential conflicts • Multiple activities can utilize the same closure • Avoid lane closures during a special event • Avoid right lane closure near a left lane closure on the same roadway • Eliminates duplications and inefficiencies by streamlining information into one system • Provides link to historical data that can be used to make informed decisions

  3. LCS Data Flows LCS Users Request / Accept 511 Travel Info STOC ATMS Email List WisDOT Contracts, STN, Traffic Data WisTransPortal Data Archive LCS OSOW Construction Map WisDOT Website Special Project Websites

  4. System Use What closures should be tracked? • All let projects (information formerly entered into Traffic Impediment Module) • Any planned closure or restriction on Corridors 2030 roadways • All major special events When should closures be entered? • 14 days - Project start or full roadway closure • 7 days - System ramp closure • 3 days - Lane and service ramp closure

  5. System Use • Closure / Restriction Types • Construction – Let projects • Maintenance • Permit – Utility work • Special Event – Summerfest Fireworks, Harley Parade, Farm Progress Days • Emergency

  6. Closure Information • General Section – includes attributes that pertain to the entire closure and once entered cannot be changed (with limited exception) • Facility Section – used to group closure specific attributes within the same closure. Facilities come in four types: • Mainline • Ramp • Bridges • System Interchanges

  7. Closure Duration Types • Daily/Nightly – Closures that will occur once on the day(s) or night(s) defined • Weekly – Closures that will occur on the same days of the week for a number of weeks • Continuous – Closures that will last for longer than 24 hours, but less than two weeks • Long Term – Closures that will last for more than two weeks

  8. System Users • System can be accessed via the Internet – therefore people outside of WisDOT can log on with a username and password • LCS User Roles • Supervisor • Regional Traffic Engineer (RTE) - Regional Coordinator • Statewide Traffic Operations Center (STOC) • Project Manager (PM) • Permit Coordinator (PC) • Maintenance Coordinator (MC) • Project Leader (PL) • Public Information (PUBLIC) • Inspector (INSP) • Requestor (REQ) • Viewer (VIEWER)

  9. Acceptance Process • Closures that will typically be automatically accepted include: • Let project information that was formally entered into the Traffic Impediment Module of FIT • Closures that meet requirements outlined in the TMP • Closures that should follow the approval process include: • Maintenance work • Short-term project closures – i.e. overnight work

  10. LCS Work Flow Closure REQUEST Return / Reschedule FORWARD ACCEPT Complete

  11. Acceptance Process • Special events will typically be entered by a Traffic Engineer who has already approved the closure and the closure will not go through the acceptance process • Acceptance authority can be delegated to anyone by their supervisor • Users with acceptance authority are allowed to, but not required to, immediately accept a closure they have entered into the system

  12. System Interfaces • Request – Enter a closure into the system • Accept – Edit, advance or accept a closure • Modify – Modify or reschedule accepted closures • Search – Search for closures • Reports – Run closure reports • Capacity – Evaluate lane closure • Calendar – View calendar of events (i.e. Packer Games) • E-mail – Add, edit or delete e-mail preferences • Preferences – Update user information

  13. LCS Key Points • April 1, 2008 - LCS go live date • Does not replace person to person communications • Can be run from almost any web browser using any internet connection • Flexible, statewide system developed to accommodate a variety of business needs

  14. http://transportal.cee.wisc.edu/closures

More Related