1 / 13

Soal Review sistem persediaan

Soal Review sistem persediaan. Calculate EOQ. 2DS. 2(Annual Demand)(Order or set-up cost). Q eoq. =. =. H. Annual Holding Cost. when to place an order. Reorder point R=DL D = Avg daily demand (constant) L = Lead time (constant). Exercise EOQ and reorder point?

gali
Download Presentation

Soal Review sistem persediaan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Soal Review sistem persediaan

  2. Calculate EOQ 2DS 2(Annual Demand)(Order or set-up cost) Qeoq = = H Annual Holding Cost when to place an order. Reorder point R=DL D = Avg daily demand (constant) L = Lead time (constant) • Exercise EOQ and reorder point? • Annual demand = 2,000 units • Days/year in average daily demand = 365 • Cost to place an order = £10 • Holding cost /unit p.a. = £2.50 • Lead time = 7 days • Cost per unit = £15

  3. EOQ Solution 2DS 2(1,000 )(10) Q = = = 89.443 units or 90 units eoq H 2.50 1,000 units p.a. d = = 2.74 units/day 365 days p.a. Reorder point D L = 2.74 units/day = 19.18 or 20 for 7 day lead time EOQ order = 90 units. When only 20 units left, place next order for 90 units.

  4. 10,000 units/year D = = 27.397 units/day 365 days EOQ and ROQ example 2 Annual Demand = 10,000 units Days per year considered in average daily demand = 365 Cost to place an order = £10 Holding cost per unit per year = 10% of cost per unit Lead time = 10 days Cost per unit = £15 2DS 2(10,000)(10) Q = = = 365.148 (366 units) H 1.50 eoq If lead time = 10 days, ROL= 273.97 = 274 units Place order for 366 units. When 274 left, place next order for 366.

  5. Demand 2 x unit cost x Hc% + Oc 1200 2 x £3 x 25% = £450 + £10 Once per year = £460 1200/52 2 x £3 x 25% = £9 + £510 Once per week = £519 approx Total variable cost Avg.stock Find point of minimum TVc

  6. EOQ Table – minimum TVc Avg.stock x item £ x hc % Oc + Hc

  7. Minimum point of Total Inventory Costs • EOQ = • minimum TVc point Total variable costs £ Costs Total Hc Total Oc EOQ* Order Size (Q)

  8. £6.40 x 18.75% EOQ Example Cheapo Bags wants to calculate the EOQ for tapestry cloth used to produce hand bags. • Last year demand = 10,000 metres (constant rate). • Value per metre of tapestry = £6.40 • Oc – each order = £250. • Hc = £1.20 per metre = 18.75% What is the EOQ? 2 x 10,000 x £250 = 2042 metres

  9. 2(Demand p.a.)(Order or Setup-cost) QOPT = = 2DS Holding cost per annum iC Price-Break Model Assumptions similar to as EOQ model i = % of unit cost as carrying cost C = cost per unit “C” varies for each price-break so apply the formula to each price-break cost value.

  10. 2DS iC Price-Break Example • Brunel University can reduce ordering costs for photocopy paper by placing larger quantity orders. What is the optimal order quantity? • e-mail order cost = £4 • carrying cost % = 2% • Demand p.a. = 10,000 units? Quantity price breaks

  11. Solution Put data into formula for each price-break of “C”. D = 10,000 units Order cost (S) = £4 Carrying cost % (i) = 2% Cost per unit (C) = £1.20, £1.00, £0.98 Are Qopt values feasible for the price breaks? 2(10,000)(4) 2(10,000)(4) 2DS = =2,000 = = 1,826 units 0.02(1.00) iC 0.02(1.20) 2(10,000)( 4) = =2,020 0.02(0.98) Qopt 0 - 2499 Feasible 2500-3999 and 4000+ Not feasible

  12. U-shaped function True Qopt values occur at the start of each price-break interval.The total annual cost function is a “u” shaped function Total annual costs Price-breaks 0 1826 2500 4000 Order Quantity

  13. Price-Break Solution Now apply the Qopt values to total annual cost & identify the total cost for each price-break. TC(0-2499)= (10000x1.20)+(10000/1826)x4+(1826/2)(0.02x1.20) = £12,043.82 TC(2500 -3999) = £10,041 TC(4000+) = £9,949.20 Least cost Qopt = 4000

More Related