1 / 10

Item 5D Marysville Ring Levee Supplemental IS/EA/MND April 27, 2018

Item 5D Marysville Ring Levee Supplemental IS/EA/MND April 27, 2018. Presented by: Daniel Bremerman , P.E. (DWR) David Moldoff (DWR). Project Sponsors. Federal Sponsor: United States Army Corps of Engineers (USACE) ( NEPA lead ) Sacramento District (USACE-SPK) Non-federal Sponsors:

fullilove
Download Presentation

Item 5D Marysville Ring Levee Supplemental IS/EA/MND April 27, 2018

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Item 5DMarysville Ring LeveeSupplemental IS/EA/MNDApril 27, 2018 Presented by: Daniel Bremerman, P.E. (DWR) David Moldoff (DWR)

  2. Project Sponsors Federal Sponsor: • United States Army Corps of Engineers (USACE) (NEPA lead) • Sacramento District (USACE-SPK) Non-federal Sponsors: • Central Valley Flood Protection Board (Board) (CEQA Lead) • Department of Water Resources Flood Projects Office • Marysville Levee District (MLD) • MBK Engineers

  3. Project Location Yuba River Basin Reaches • At the confluence of the Yuba and Feather Rivers

  4. Design and Construction Status Phase 4B Phase 4A Phase 1 Phase 2A-North Phase 3 Phase 2A-South Construction Year Phase 2A North = 2018 Phase 2A South = 2019 Phase 2C = 2020 Phase 2B = 2020,2021 Phase 3 = 2021 Phase 2B Phase 2C

  5. Supplemental Environmental Assessment/Initial Study Phase 2A South-Phase 2C

  6. Environmental Background • 2010: Joint EA/IS Completed • CVFPB – Mitigated Negative Declaration (MND) adopted • USACE – Finding of No Significant Impact (FONSI) adopted

  7. Phase 2A-S & 2C Environmental Effort • Supplemental EA/IS – Phase 2A South and 2C • Key design refinements: • Alignment in 2A-S  Waterside Toe • Staging Area  Additional 1.9 acres • Construction Method  Deep Mix Method

  8. Phase 2A-S & 2C Environmental Effort • February 16 – March 22: Public Comment Period • 3 Comments • February 28: Public Meeting in Marysville • 7 members of public

  9. Questions Presented by: Daniel Bremerman, P.E. (DWR) David Moldoff (DWR)

  10. Design and Construction Status Phase 4A Phase 1 Phase 2A-North Phase 3 Phase 2A-South Construction Year Phase 2A North = 2018 Phase 2A South = 2019 Phase 2C = 2020 Phase 2B = 2020,2021 Phase 3 = 2021 Phase 2B Phase 2C

More Related