Tariff Language Clarification regarding the Establishment of Resource Capability for Existing Genera...
This presentation is the property of its rightful owner.
Sponsored Links
1 / 6

Al McBride Project Manager – System Planning PowerPoint PPT Presentation


  • 39 Views
  • Uploaded on
  • Presentation posted in: General

Tariff Language Clarification regarding the Establishment of Resource Capability for Existing Generators. Al McBride Project Manager – System Planning. Hierarchy to Identify Interconnection Capability.

Download Presentation

Al McBride Project Manager – System Planning

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Al mcbride project manager system planning

Tariff Language Clarification regarding the Establishment of Resource Capability for Existing Generators

Al McBride

Project Manager – System Planning


Hierarchy to identify interconnection capability

Hierarchy to Identify Interconnection Capability

  • The proposed hierarchy language is unchanged from earlier ISO presentations and committee discussion regarding the appropriate hierarchy

  • The proposed hierarchy language is consistent with the ISO implementation of the grandfathering provision


Hierarchy to identify interconnection capability1

Hierarchy to Identify Interconnection Capability

  • The interconnection capability of the generator shall be:

    • The summer and winter MW quantities expressed in the Interconnection Agreement (“IA”), where available

    • If there is no expression of MW quantities in an IA then the interconnection capability will be the summer and winter MW quantities expressed in the I.3.9 or 18.4 or 10.4 approval for the generator

    • If both IA and I.3.9 exist and differ then the lower will govern

  • If the above quantities do not exist, the interconnection capability will be the higher of the following:

    • The highest recorded summer and winter Claimed Capability Audit – Establish test result for the generator; or

    • The maximum claimed capability for the generator as recorded in a CELT report


Interconnection capability definitions

Interconnection Capability - Definitions


Interconnection capability identification examples using summer ratings

Interconnection Capability Identification: Examples using Summer Ratings

*Summer Demonstrated Capabilities are stated at 90degF for temperature-corrected units


Al mcbride project manager system planning

Questions