An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    1. 1 Petroleum Engineering 406 Floating Drilling Lesson 9c Wellheads and Casing

    2. 2 Lesson 9c - Wellheads and Casing Temporary and Permanent Guide Bases Subsea Cementing Casing Seals

    3. 3 Wellheads and Casing A subsea wellhead, just like a land wellhead: Must support the BOP’s while drilling Must support the suspended casing while cementing, and Must seal off between casing strings during drilling and production operations.

    4. 4 Wellheads and Casing, cont. In floating drilling, the casing hangers, casing seals and cementing heads differ from land and platform operations in the following manner:

    5. 5 Wellheads and Casing 1. The first and second casing strings are cemented with returns to the seabed. 2. Casing is run with the last joint made- up on a casing hanger and permanently suspended prior to cementing. Mud returns flow through fluting in the hanger.

    6. 6 Wellheads and Casing 3. Usually, cementing plugs are located at the wellhead and released remotely. The cementing string from the vessel to the wellhead is drill pipe. 4. Casing seals are run and set remotely.

    7. 7 Wellheads and Casing 5. Special test tools are required for remotely testing the casing seals. 6. Wear bushings are essential for protecting the wellhead.

    8. 8

    9. 9

    10. 10

    11. 11

    12. 12

    13. 13

    14. 14

    15. 15

    16. 16 Typical specific gravity variations in a blowout boil have increasing effect nearer the water’s surface. Fortunately for a semi-submersible, the rig’s primary flotation members are situated below the zones where specific gravity has been reduced the most.

    17. 17

    18. 18 If there is sufficient length to the mooring system cables/ chains, the rig will be pushed off location and out of harm’s way. However, the plume can also cause the rig to list, which reduces its freeboard and makes it more susceptible to capsizing.

    19. 19

    20. 20

    21. 21 Metal-to-Metal Casing Annulus Seal

    22. 22

    23. 23 Casing Hanger and Pack-off Assembly Single trip installation The pack-off seal assembly is run simultaneously with the casing hanger body. All operations - installing the casing hanger, cementing the casing string and actuating and testing the pack-off seal are performed in a single trip of the running string.

    24. 24 Large Flow-By Areas Large flow-by areas can handle most drilling fluid applications with a minimal drop in pressure. Deep 2" wide flow-by slots in the casing hanger body, and ample porting through the pack-off nut assembly, provide clear passage for cuttings and mudcake without plugging.

    25. 25 Shallow Gas Plan After the rig is properly anchored the following steps will be followed as there is a potential for shallow gas in this area:

    26. 26 Shallow Gas Plan 1. Leave mooring line pawls or stoppels unset until the 20” casing has been set and cemented. 2. Mooring winches will be manned while the 8 1/2” pilot holes for the 30” and 20” casings are being drilled.

    27. 27 Shallow Gas Plan 3. Mooring winches will be manned while the 8 1/2” pilot holes for the 30” and 20” casings are being opened up or under reamed. 4. The moonpool and seafloor will be observed for gas bubbles until the 20” casing is set and cemented.