LPA – Utility Coordination
This presentation is the property of its rightful owner.
Sponsored Links
1 / 32

LPA – Utility Coordination Natalie Parks, P.E. American Structurepoint , Inc. December 19, 2013 PowerPoint PPT Presentation


  • 100 Views
  • Uploaded on
  • Presentation posted in: General

LPA – Utility Coordination Natalie Parks, P.E. American Structurepoint , Inc. December 19, 2013. Today’s Topics. Basic INDOT/LPA Program Key People Utility Coordination Process Submittals Agreements Work in Contract Case Studies Utility Company Comments. INDOT/LPA Program.

Download Presentation

LPA – Utility Coordination Natalie Parks, P.E. American Structurepoint , Inc. December 19, 2013

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Lpa utility coordination natalie parks p e american structurepoint inc december 19 2013

LPA – Utility Coordination

Natalie Parks, P.E.

American Structurepoint, Inc.

December 19, 2013


Today s topics

Today’s Topics

  • Basic INDOT/LPA Program

  • Key People

  • Utility Coordination Process

  • Submittals

  • Agreements

  • Work in Contract

  • Case Studies

  • Utility Company Comments


Indot lpa program

INDOT/LPA Program

  • Mission:To empower Local Public Agencies (LPA) through excellent education and collaborative relationships, to plan, build and maintain a superior transportation system that promotes economic growth, ensures safety, and complies with all local, state, and federal regulations.


Indot lpa program1

INDOT/LPA Program

  • INDOT is Involved on an LPA Project When Federal Dollars are Spent

    • District LPA Project Manager to secure federal funds.

    • District Utility Coordination when there is a reimbursable utility relocation.

    • Must follow federal regulations for utilities CFR 645 (http://www.fhwa.dot.gov/programadmin/utility.cfm

    • Must follow 105 IAC 13

    • Utility Accommodation Policy (July 2013)

    • INDOT Design Manual

    • LPA Design Guidance Document - Chapter 10


Lpa utility coordination

LPA Utility Coordination

  • Key people

    • LPA Employee in Responsible Charge (ERC)

    • LPA Design Project Manager

    • Utility Coordinator

    • Utility Personnel

    • INDOT Project Manager

  • Ultimately the Utility Coordinator and the Design PM are both responsible for ensuring 105 IAC 13 is followed.


Lpa utility coordination process

LPA Utility Coordination Process

  • Process is the same – (105 IAC 13)

    • Research – 1 to 2 weeks

    • Initial Notice – 1 to 2 months

    • Verification Plans – 2 to 4 months

    • Conflict Analysis – 2 to 4 months

    • Work Plan Development – 1 to 6 months

    • Reimbursable Agreements – 2 to 4 months

    • Notice to Proceed/Construction


Research

Research

  • Many municipalities do not have a permit program

  • Rely more on:

    • Indiana 811

    • Field visits

    • Field surveys

  • Use previous project information if available

  • Talk to the LPA utility/engineering dept.


Standard utility submittals

Standard Utility Submittals

  • Follow the 105 IAC 13 rules and allow the appropriate time for response

  • Copy project owner representative on all submissions

  • INDOT’s District Utility Coordinator is involved in a LPA projects Utility Coordination process, only when there are Reimbursable Agreements.


Ready for contracts

Ready for Contracts

  • Per Section 10-4.03 LPA Guidance Document: Submission prior to RFC should include:

    • Utility Work Plan/Relocation Drawings from each utility or Letter of No Conflict

    • LPA/Utility Reimbursement Agreement for each reimbursable utility

    • Utility FMIS authorization letter or e-mail

    • Utility Certification

    • Utility Special Provisions


Stage 3

Stage 3

  • The biggest difference between LPA and INDOT projects:

    • Utility Certification, Work Plans & Relocation Drawings are due at Stage 3 Submission to INDOT


Who do i call

Who do I call?

  • Concurrently – contact:

    • Supervisor/UAR of Utility

    • Design Project Manager

    • LPA ERC

  • Contact INDOT Project Manager

  • Contact INDOT LPA Liasion

  • Contact INDOT Central Office Manager of Utilities and Railroads


Additional charges and invoices

Additional Charges and Invoices

  • Assist the ERC in determining if a scope change to the existing agreement, or a cost overrun requested by the utility are appropriate.

  • Make sure that all scope changes and cost overruns have been approved by the ERC prior to the utility company proceeding with work. If not, and the utility does any of this work without prior approval, these charges are not reimbursable.

  • Assist the ERC in ensuring that the charges are per the agreement and the utility invoices are correct.

  • If an invoice is incorrect or inappropriate, advise the ERC in resolving the issues with the utility.


Lpa utility coordination natalie parks p e american structurepoint inc december 19 2013

Case Study


Lpa utility coordination natalie parks p e american structurepoint inc december 19 2013

Case Study

  • Project involves:

    • Municipal utility relocation

    • Right-of-way limitations

    • Lift station AND Booster Station

  • Portions of utility on documented, exclusive easement

  • Project owner owns the utility

  • Utility requires relocation due to new roundabout & MSE walls


Lpa utility coordination natalie parks p e american structurepoint inc december 19 2013

Case Study

  • Is the utility reimbursable?

    • If so, by whom?

  • Does the utility need to secure permanent right-of-way?

    • If so, why?

    • If not, why not?


Lpa utility coordination natalie parks p e american structurepoint inc december 19 2013

LPA – Utility Coordination

Tom Rueschhoff

LPA/Railroad/Utility Engineer, INDOT

December 19, 2013


Today s topics1

Today’s Topics

  • Relocations that threaten project

  • Need for escalation

  • Subconsultants

  • Agreements

  • Work in Contract

  • Case Study

  • Utility Company Comments


Reimbursable relocations

Reimbursable Relocations

  • Too often a local public agency will find out TOO late in a project that there is an sizeable REIMBURSABLE utility that negatively impacts the project.

    • Utility coordinator should provide a list of all confirmed reimbursable utility relocations at the end of Stage 1.

    • One (1) large reimbursable utility can create a critical cost that may have a severe impact such that a LPA cannot move forward with their project.

    • Or worse, become a burden afterward


Escalation chain

Escalation Chain

  • Become well educated in ALL state and federal documents

  • Work with utility company.

  • Work with LPA. (ERC)

  • INDOT District LPA project manager

  • INDOT Central Office – Kenny Franklin, Statewide Director


Subconsultant utility coordinator

Subconsultant Utility Coordinator

  • When to use a subconsultant when your firm is prequalified?

  • 1.) Relatively low experience level

  • 2.) Difficult project

  • 3.) Many reimbursable utility relocations

  • 4.) Accelerated project development schedule


Lpa utility relocation agreements

LPA Utility Relocation Agreements

  • When is an LPA/Utility agreement required?

    • Only when a utility relocation is required due to being in direct conflict. There are 3 scenarios:

      • Reimbursable: When the utility company relocates their own facilities.

      • Reimbursable : Work in Contract - The utility relocation is constructed as part of the road contract.

      • Non-reimbursable: Work in Contract - The utility agrees to include the utility relocation as part of the road contract. These bid items should be identified as “non participating” and 100% of the successful bid will be paid up front by the utility company.


Work in contract

Work in Contract

  • Early on (Stage 1) ask the utility companies to consider including their relocations in the LPA project.

  • Benefits – Why do we recommend WIC :

    • Allows better overall construction coordination with the contractor in control of the scheduling

    • Reduces, and hopefully can eliminate, utility delays

    • Saves on overall construction costs (Mobilization, pavement cuts, shoring, overall efficiency…)

    • Eliminates claims, contractor responsible for the x, y and z location

    • Saves on overall construction time

    • “The Contractor knows where everyone went”.


Work in contract1

Work in Contract

  • SECTION 5 – REIMBURSEMENT

  • (a) 20 % of the cost to design and prepare construction plans, specifications and preliminary itemized cost estimate for relocation of the Utility’s facilities shall be borne by the Local Public Agency.

  • (b) 20 % of the cost to provide testing and inspection services for relocation of the Utility’s facilities shall be borne by the Local Public Agency.

  • (c) The Local Public Agency shall bear 20 % of the cost of relocating the Utility’s facilities. (See exhibit “B”).


Work in contract2

Work in Contract

  • The reimbursements paid for under SECTION 5: (a), (b), and (c) shall include the cost sharing that is paid with federal funds. This project shall be split in accordance with the funding established, which is typically paid with 20% LPA funding and 80% Federal funding.

  • How the payments are made:

    • Prior to the awarding of the contract, the LPA submits their 20% of the Utility Relocation per the Construction estimates.

    • Contractor actual cost invoices are reviewed and approved by the project manager and paid for with 20% LPA funds / 80% Federal funds.

    • Any cost overruns or claims should be approved and paid for at the same percentages as the original contract.


Lpa utility coordination natalie parks p e american structurepoint inc december 19 2013

Case Study

  • Case Study

  • Case Study


Case study existing

Case Study – Existing

  • Pipeline Company has a 14” diameter gas pipeline that crosses an existing road that the LPA is proposing to add a lane.

    • Existing pipeline has a casing pipe that extends 5 ft. beyond the existing paved shoulder.

    • New pavement will extend beyond the end of the casing.

    • Pipeline Profile: The top of the pipeline is 6 ft. below the proposed pavement.

    • Existing pipe is structurally inadequate for the loading without a casing pipe.


Case study exercise

Case StudyExercise

  • Pipeline Company requested 100% reimbursement.

    • Claim – Lose the ability to access the end of the casing pipe, therefore will not be able to slide the pipe out for future maintenance.

    • They proposed 2 possible options and relocation costs:

      • Option #1: Bore and install a new pipeline with thicker walls under the new wider pavement.

      • Option #2: Open cut pavement, remove the existing casing, and provide maintenance to the existing pipeline, and install a no-load slab over pipeline.


Case study

Case Study

What costs are reimbursable?

Option 1: New pipe bored in place

Option 2: Remove Casing

  • Inspect and provide maintenance to coating under casing.

  • Install no-load slab

    Note: Current Industry Design Standards no longer recommend a casing pipe be used due to cathodic corrosion.


Case study actical exercise

Case Studyactical Exercise

  • INDOT’s Response:

    • Pipeline is in conflict with the roadway improvements due to the inadequate structural capacity of the pipe.

    • Option 1: Onlythe segment of the pipeline between the existing roadway right-of-ways is within an easement with property interests, and therefore is eligible for reimbursement.

    • Option 2: Removing the casing and inspecting the pipe’s outer wall coating is a maintenance item, and therefore is notreimbursable.

    • Neitherof these options proposed by the utility company will allow for future maintenance.


Case study practical exercise

Case StudyPractical Exercise

  • INDOT’s Response:

    • Therefore only the no-load slab over the section of pipeline within the easement is reimbursable.

    • It is the Utility Company’s decision on either boring and installing a new line, or open cutting and removing casing, and installing the no-load slab.

    • The Utility Company should coordinate with LPA’s contractor to schedule open cut when road is shutdown.


Utility companies

Utility Companies

  • Several issues utilities have had with LPA utility coordination

    • Wide range of experience levels

    • Do not know to follow the 105 IAC 13 when federal aid projects

    • LPA’s often will claim their projects are Minor Projects to attempt to hold utility companies to shorter response time

    • Utility companies receive notification to attend a “Pre-construction” meeting when they had not received a Notice to Proceed


Questions

Questions?


  • Login