The state of implementation of CIM in MAVIR

The state of implementation of CIM in MAVIR. CIM Users Group 2011 Prague. Bence BAJI Process Control IT DEP. Presentation Contents. ENTSO-E business processes MAVIR Market processes MAVIR Planning processes MAVIR Operational processes MAVIR CIM tools Open issues. 2.

Download Presentation

The state of implementation of CIM in MAVIR

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The state of implementation of CIM in MAVIR CIM Users Group 2011 Prague Bence BAJI Process Control IT DEP

  2. Presentation Contents ENTSO-E business processes MAVIR Market processes MAVIR Planning processes MAVIR Operational processes MAVIR CIM tools Open issues 2

  3. ENTSO-E business processes • 2009 - ENTSTO-E TSOs have been underlining their commitmet to apply the CIM-based data exchange format in all data exchange processes Source:ENTSO-E CIM MEP v1. 2014. november 18.

  4. MAVIR’s market processes MAVIR implemented most of the ENTSO-E EDI data exchange formats Scheduling process (ESS) Capacity allocation and nomination process (ECAN) Settlement process (ESP) Reserve resource process (ERRP) MAVIR is affected by CIM Market integration (CME) Source: ENTSO-E EDI Library 4 2014. november 18.

  5. Planning processes CIM-based data exchange format is required by ENTSO-E MAVIR sends PSS/E (binary) format now Decided to buy or develop a CIM-based tool in the near future Source:ENTSO-E CIM MEP v1. 5 2014. november 18.

  6. Operational processes CIM-based data exchane format is in test phase. MAVIR sends UCTE-DEF ASCII files as usual MAVIR sends CIM-XML for every wednesday Source:ENTSO-E CIM MEP v1. 6 2014. november 18.

  7. UCTE-DEF -> CIM-XML Converter 1st Goal: replace EDF Converter Own converter since the end of 2010 Developer: Astron Infomatika Kft. JAVA based application Fulfils MAVIR’s needs Doesn’t support the previously unused functionalities (e.g. #E and #TT) Validated with CIMdesk only 7 2014. november 18.

  8. New CIM XML generator module Siemens Spectrum upgrade from 3.4 to 3.11 Now: Spectrum 3.8 Some modules are CIM-based, some NOT Network Analyzer module works with text based database only (DBNETD) We needed a new solution to generate CIM/XML for DACF Developer: Astron Infomatika Kft. In the site acceptance phase Some open issues 8 2014. november 18.

  9. What is needed for CIM DACF Load Flow solution Node Voltage and angle Power flow Limit violation • Transmission system model • Generation schedules • Load schedules • Switching schedules • Transformer info • Equipment Topology State Variables 9 2014. november 18.

  10. Generating method 1 • Populate CMMS with power system model • Generate MRIDs • Common Model Management System + • Information Model Manager +Transmission Network App. • CIM-based master model repository and model manager and user interface and network analyzer • Model export back to text based database (DBNETD) • Model export to CIM-based RDF or XDF files 10 2014. november 18.

  11. Generating method 2 • New JAVA application pre-process the model • Create Equipment and Static Topology • Populate the NA Dadabase from DBNETD • Copy EQ + static TP to Network App. servers • New FORTRAN procedure • Create Dynamic Topology and State Variables 11 2014. november 18.

  12. Generating method 3 • New JAVA-based generator • Process the created models • Generate ENTSO-E CIM-XML files 12 2014. november 18.

  13. MAVIR’s CIM Solution +/- • Based on ENTSO-E MEP v1 and ready for the Profile v2 • Manual and Automatic mode • Provides CIM-XML for DACF and 2DACF • Provides „full” model for CAO (Central Allocation Office) • Generates EQ+TP+SV or ME • Configuration files (e.g. important network parts) • Does complete topological processing (e.g. Topological islands) • Supports incremental model exchange (just need headers) • One way converter (only CIM-XML export) • CMMS is new for us • Validated with CIMdesk only • 3W Transfomer = 3 * 2W Transformer 13 2014. november 18.

  14. Open issues • X-nodes, Common Objects? • Profile v1 referenced on draft standards • System modeling issues • What should we keep under 120 kV? • No live or default value for a mandatory attribute? • Lack of complete validation tool (functionally) • ENTSO-E Network Modeling Database? • Is CIMdesk enough? • Lack of examples • We need stronger CIM community 14 2014. november 18.