PRAC Project Phase III: Sour Service Evaluation of ISO TR 10400 FAD Equation. API Production Research Advisory Committee Pete Moore – API PRAC Chairman Peter Ellis – Program Manager. PRAC III C110 Test Pipe Were Donated and Shipped to Honeywell by Tenaris. Detailed Mill Test Report

Download Presentation

PRAC Project Phase III: Sour Service Evaluation of ISO TR 10400 FAD Equation

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Prac project phase iii sour service evaluation of iso tr 10400 fad equation

PRAC Project Phase III: Sour Service Evaluation of ISO TR 10400 FAD Equation

API Production Research Advisory Committee

Pete Moore – API PRAC Chairman

Peter Ellis – Program Manager


Prac project phase iii sour service evaluation of iso tr 10400 fad equation

PRAC III C110 Test Pipe Were Donated

and Shipped to Honeywell by Tenaris

Detailed Mill Test Report

Documenting the Pipe

Characterization Attributes


Prac iii phase 3 details

PRAC III – Phase 3 Details

  • Testing Details:

    • NACE Standard TM0177 Method A – Tensile tests complete

    • NACE Standard TM0177 Method D – DCB tests complete

    • Mini/Tiny-Pipe SSC Tests

      – Machining Complete

      – EDM Notch cutting Complete

      – H2S Depletion test Complete

      – Klimit in 7% H2S solution, In-progress

      – Tiny Pipe testing, expected to begin 4th Qtr 2013

    • Full Scale Tests with Man-made OD Surface Imperfections

      • ID/OD and OD only or ID only H2S Exposure – Pressurized ID environment and OD exposure with replenishment/purging of 7% H2S in solution held in annular volume between plastic sleeve and OD of sample.

        – Testing to begin 2nd quarter 2014


Prac project phase iii sour service evaluation of iso tr 10400 fad equation

~ 4 inches

EDM OD Notch

Machining of Tiny Pipe Complete EDM Notching Complete


Prac project phase iii sour service evaluation of iso tr 10400 fad equation

Tiny Pipe H2S Depletion Test

Soaked in 100% H2S for 17.72 hours, then flushed with distilled H2O

60% Depletion

40% Depletion


Prac project phase iii sour service evaluation of iso tr 10400 fad equation

7% NACE A Enviroment


Prac project phase iii sour service evaluation of iso tr 10400 fad equation

Testing of Full Size PipeTo Begin 2nd Quarter 2014