1 / 10

Calvert Cliffs Unit 3

Calvert Cliffs Unit 3. Status Summary for PPRAC Meeting 26 August 2008. CPCN Case Background. Unit 3 proposed for Calvert Cliffs site, Calvert Co.

finola
Download Presentation

Calvert Cliffs Unit 3

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Calvert Cliffs Unit 3 Status Summary for PPRAC Meeting 26 August 2008

  2. CPCN Case Background • Unit 3 proposed for Calvert Cliffs site, Calvert Co. • New unit would have net output of about 1600 MW, nearly doubling the capacity of the existing Units 1 and 2 combined – if constructed it would be the world’s largest reactor • Applicant for CPCN is Calvert Cliffs 3 Nuclear Project, a wholly owned subsidiary of UniStar Nuclear Energy (which is a joint venture of Constellation and Electricité de France) • PPRP filed initial recommended license conditions on 16 July 2008 • PSC evidentiary hearings held 11-12 August; also 3 public hearings in August

  3. Key Issues • Water use • Ecology • Air Impact • Socioeconomics/Traffic

  4. Water Use • During construction, use of ground water for uses such as concrete mixing and sanitary water supply • During operation, withdrawal of >50 mgd for cooling water • Operational water use is much less than Units 1 and 2 (which withdraw >3,000 mgd combined), but a greater percentage of the Unit 3 will be lost to evaporation and not returned to the Bay

  5. Ecology • Calvert Cliffs 3 must construct facility in a way that minimizes impacts to wetlands, streams, forests • USACE and MDE actively reviewing joint state/federal wetlands permit • DNR’s review of Forest Conservation Plan near completion • Critical Area Commission provided project approval in early August

  6. Air Impact • Use of Bay water in cooling tower gives rise to emissions with relatively high levels of dissolved solids – which constitutes particulate matter (PM) and requires detailed modeling of air quality impacts, use of Best Available Control Technology • Other sources include oil-fired emergency generating units • Much smaller emissions profile compared to similar-sized fossil fuel fired facility • PPRP and MDE currently evaluating revised air emissions data that Calvert Cliffs 3 submitted at the PSC hearings earlier this month

  7. Socioeconomics/Traffic • Fiscal benefits to Calvert County and So. Maryland • ~4000 construction jobs • ~360 permanent jobs • Estimated $20 million in tax revenue to County • Calvert Cliffs 3 working on detailed traffic study; will require SHA approval of road upgrades to support increased construction traffic • MHT approval required for mitigation plans associated with impacts to historic resources on the site

  8. Public Reaction • Public comments at hearings showed strong local support for Unit 3 project • Concerns raised by members of the public are being addressed by State’s recommended conditions, and/or through NRC licensing process • NRC has federal jurisdiction for radiological emergency planning, radiological health and safety, nuclear waste disposal

  9. Current Status • PPRP and Calvert Cliffs 3 actively working to reach agreement on as many recommended license conditions as possible • PPRP/MDE evaluation of air quality impacts and water appropriations ongoing • Additional coordination also continuing with SHA, DNR Forestry, USACE/MDE • Expected date for CPCN issuance not yet determined, but we should be able to support Calvert Cliffs 3 proposed construction start date of May 2009

  10. “Coming Attractions’ CP Crane Barge Unloader Catoctin Coal Testing at CP Crane

More Related