Answering the cry of the poor
Download
1 / 28

ANswering the Cry of the Poor - PowerPoint PPT Presentation


  • 77 Views
  • Uploaded on
  • Presentation posted in: General

CFC ANCOP ROTARY HOMES. ANswering the Cry of the Poor. Shelter Program. INSTALLATION OF FORMS. INSTALLATION OF FORMS. Progress Report July 18, 2012. First Cluster-Maynilad Funded Houses. CONCRETE POURING. SITE DEVELOPMENT. FACTORS THAT CONSTRIBUTED TO THE DELAY

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'ANswering the Cry of the Poor ' - fifi


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Answering the cry of the poor

CFC ANCOP ROTARY HOMES

ANswering the Cry of the Poor





Progress report july 18 2012

Progress Report July 18, 2012

First Cluster-Maynilad Funded Houses




Answering the cry of the poor

  • FACTORS THAT CONSTRIBUTED TO THE DELAY

  • Condition of the site.

  • Difficulty in mobilization considering the simultaneous

  • work going on in the same area (house construction

  • and site development)

  • Lack of power supply.

  • Beneficiaries need to support the financial and material

  • requirements of their family.

  • Weather

  • Suitable site for forms fabrication.

  • Familiarization with the new technology.


What progress have we accomplished after june 18

WHAT PROGRESS HAVE WE ACCOMPLISHED AFTER JUNE 18?

FIRST CLUSTER CONSISTING OF 14 HOUSES



Answering the cry of the poor


Answering the cry of the poor

  • Program of works:

  • JULY

  • 3rd week-finish the wall partition for the 2nd floor of the first row.

  • 4th week-finish the walls of the 2nd row.

  • AUGUST

  • 1st week-put the c-parlenes and possibly the long span color roof.

  • 2nd week-fabrication and installation of doors and windows.

  • 3rd week-installing the kitchen zink and labatory and other finishing works.

  • Aug.24-BUILD DAY. (PAINTING)


Answering the cry of the poor

DAYS WORK/UNIT

MONTHACTIVITY NO. OF DAYS

FEB-GROUNDBREAKING/CLP

MARCH-CLP/EXCAVATION

APRIL-CLP/EXCAVATION 15

MAY-FOOTING AND TIE BEAM26

JUNE-CONSTRUCTION OF GROUND FLOOR25

JULY-GROUND FLOOR, 2ND FLR BEAM AND

WALL PARTITION13

___

TOTAL NO. OF DAYS WORK79

===

NO. OF DAYS SPEND PER UNIT TO THIS DATE:

(79 DAYS DIVIDED BY 14 UNITS)5.642857