IMPACT OF UNSCHEDULED INTERCHANGE CHARGES AND RELATED MATTERS AMENDMENT REGULATIONS, ISSUED BY CERC ON 28.04.2010 APPLIC - PowerPoint PPT Presentation


  • 265 Views
  • Uploaded on

IMPACT OF UNSCHEDULED INTERCHANGE CHARGES AND RELATED MATTERS (AMENDMENT) REGULATIONS, ISSUED BY CERC ON 28.04.2010 APPLICABLE FROM 03.05.2010 IN THE INTRASTATE ABT OPERATION IN DELHI. Significant Definitions .

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'IMPACT OF UNSCHEDULED INTERCHANGE CHARGES AND RELATED MATTERS AMENDMENT REGULATIONS, ISSUED BY CERC ON 28.04.2010 APPLIC' - fell


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Slide1 l.jpg


Significant definitions l.jpg
Significant Definitions MATTERS (AMENDMENT) REGULATIONS, ISSUED BY CERC ON 28.04.2010 APPLICABLE FROM 03.05.2010 IN THE INTRASTATE ABT OPERATION IN DELHI.

  • actual injection in a time-block means electricity generated or supplied by the generating station or seller, as the case may be, measured by the interface meters

  • scheduled generation at any time or for any period or time block means schedule of generation in MW or MWh ex-bus given by the concerned Load Despatch Centre


Slide3 l.jpg

  • time-block MATTERS (AMENDMENT) REGULATIONS, ISSUED BY CERC ON 28.04.2010 APPLICABLE FROM 03.05.2010 IN THE INTRASTATE ABT OPERATION IN DELHI.means block of 15 minutes, for which specified electrical parameters and quantities are recorded by special energy meter, with first time block starting at 00.00 Hrs

  • Unscheduled Interchange in a time-block for a generating station or a seller means its total actual generation minus its total scheduled generation and for a beneficiary or buyer means its total actual drawal minus its total scheduled drawal


Slide4 l.jpg


Slide5 l.jpg

Buyer make an undue commercial gain thru UI charges: Means a person, other than the beneficiary, buying electricity, through a transaction scheduled in accordance with the regulations applicable for short term open access, medium term open access and long term access.

Seller: Means a person, other than a generating station, supplying electricity, through a transaction scheduled in accordance with the regulations applicable for short term open access, medium term open access and long term access.

Beneficiary : Means the person purchasing electricity generated from the generating station.


Slide6 l.jpg

Permissible frequency band operation and Commercial impact for the violations

  • Permissible operating range has been narrowed down by 0.38 Hz i.e. 49.5 Hz to 50.2 Hz against the previous operating range of 49.22 Hz to 50.3 Hz

  • Entities over drawing from the grid below the permissible freq. of 49.5 Hz, to pay an additional UI charge

  • Entities under injecting into the grid below the permissible freq. of 49.5 Hz, to pay an additional UI charge


Slide7 l.jpg

  • UI rates for coal or lignite or APM fuel generators are symmetrical for over generation and under generation

  • Injection by generating station other than hydro in excess of 105% of DC in a time block or in excess of 101% of DC not to be construed as gaming

  • UI charges and additional UI surcharge rate to be re-notified every six months

  • Any surplus amount left in UI pool to be utilized for supporting transmission schemes


Slide8 l.jpg

  • Charges for UI for all the time blocks when grid frequency is between 50.2 Hz and 49.5 Hz

    -payable for over- drawl by beneficiary or buyer and under injection by generating station or seller

    - receivable for under-drawl by the beneficiary or buyer and over-injection by generating station or seller


Determination of ui rates l.jpg
Determination of UI rates is between 50.2 Hz and 49.5 Hz


Ui cap rate l.jpg
UI Cap Rate is between 50.2 Hz and 49.5 Hz


Slide12 l.jpg

  • when freq. is below 49.7 Hz is between 50.2 Hz and 49.5 Hz

  • Over-drawl of electricity from schedule by any beneficiary during a time block shall not exceed 12% of its scheduled drawl or 150MW(which ever is lower), and 3% on a daily aggregate basis

  • Under- injection of electricity from schedule by a generating station during a time block shall not exceed 12% of its scheduled injection and 3% on a daily aggregate basis


Additional ui charges l.jpg
Additional UI Charges is between 50.2 Hz and 49.5 Hz


Net ui rate for under injection l.jpg
Net UI Rate for Under Injection is between 50.2 Hz and 49.5 Hz


Od ud limits for discom with in delhi l.jpg
OD /UD LIMITS FOR DISCOM WITH IN DELHI is between 50.2 Hz and 49.5 Hz

To drive the UD limit for Discom in term of MW compare to Delhi as a whole under drawing 250 MW ,the same methodology is apply (i.e. in the OD proportion) as adopted by DERC for OD limits of Discom


Slide16 l.jpg
In consonance with the UI Regulations at Regional level, the Intrastate UI Accounts preparation as under :

  • A) Draw out UI accounts at intrastate level by applying inter state UI regulations in TOTO effective from 03.5.10.

  • B) Separate out additional UI amounts for overdrawal and under generation.

  • C) Separate out differential cap amount for underdrawing discoms / over injection of generators.

  • D) Draw out the weekly statement of Inter sate UI account issued by NRPC for the same week for to make Intra State UI account to match with the interstate UI amount.

  • E) Settle the Unadjusted Additional UI of Delhi utilities with Additional UI of Delhi as a whole as per NRPC account on daily basis in proportion to additional amount to be paid by the utilities & restrict the additional UI amount of Utilities upto the amount of additional UI charges to be paid by Delhi as a whole as per NRPC account. Since the additional amount to be paid by the intra state utilities would be more than the additional amount to be paid by Delhi, It reduces the accumulation of extra Additional UI amount in the pool account being operated by SLDC.


Slide17 l.jpg

F) Intrastate UI Accounts preparation as under : Settle the unadjusted Differential UI _cap Amount (difference of amount calculated on normal UI rate and caped UI rates) of Delhi utilities as per intrastate UI accounts with the Differential UI_cap amount of Delhi as a whole as per NRPC accounts on daily basis. The adjustment of difference of the two (interstate differential amount and intrastate differential amount) is done in 50:50 basis in proportion between paying & receiving utility on pro rata basis.

It reduces the accumulation of extra differential UI cap amount in the pool account and capping is applied only the same is applied to Delhi

G) Settle the unadjusted capped UI Amount of Delhi utilities as per intrastate UI accounts with UI_cap amount of Delhi as a whole as per NRPC accounts on daily basis by adjusting the Difference of two (interstate UI amount and intrastate UI amount) is done in 50:50 basis in proportion between paying & receiving utility on pro rata basis.

H) Make the final statement of Net UI amount of paying/receiving utilities on the daily basis as under:

Net UI payable/receivable by Utilities at intrastate level

= Additional UI amount (with reference to interstate (para ‘E’) +/- Differential cap Amount (with reference to interstate (para ‘F’) +/- Capped UI amount (with reference to interstate UI account (para ‘G’)



Intra state ui a c for delhi utilities as per new regulation all figures are in rs lacks l.jpg
Intra State UI A/C for Delhi Utilities as per new Regulation previous slides is as follows:all figures are in Rs lacks


Intra state ui a c for delhi utilities as per new regulation all figures are in rs lacks20 l.jpg
Intra State UI A/C for Delhi Utilities as per new Regulation previous slides is as follows:all figures are in Rs lacks


Intra state ui a c for delhi utilities as per new regulation all figures are in rs lacks21 l.jpg
Intra State UI A/C for Delhi Utilities as per new Regulation previous slides is as follows:all figures are in Rs lacks


Intra state ui a c for delhi utilities as per new regulation all figures are in rs lacks22 l.jpg
Intra State UI A/C for Delhi Utilities as per new Regulation previous slides is as follows:all figures are in Rs lacks


Intra state ui a c for delhi utilities as per new regulation all figures are in rs lacks23 l.jpg
Intra State UI A/C for Delhi Utilities as per new Regulation previous slides is as follows:all figures are in Rs lacks


Intra state ui a c for delhi utilities as per new regulation all figures are in rs lacks24 l.jpg
Intra State UI A/C for Delhi Utilities as per new Regulation previous slides is as follows:all figures are in Rs lacks


Intra state ui a c for delhi utilities as per new regulation all figures are in rs lacks25 l.jpg
Intra State UI A/C for Delhi Utilities as per new Regulation previous slides is as follows:all figures are in Rs lacks


Intra state ui a c for delhi utilities as per new regulation all figures are in rs lacks26 l.jpg
Intra State UI A/C for Delhi Utilities as per new Regulation previous slides is as follows:all figures are in Rs lacks


Intra state ui a c for delhi utilities as per new regulation all figures are in rs lacks27 l.jpg
Intra State UI A/C for Delhi Utilities as per new Regulation previous slides is as follows:all figures are in Rs lacks


Intra state ui a c for delhi utilities as per new regulation all figures are in rs lacks28 l.jpg
Intra State UI A/C for Delhi Utilities as per new Regulation previous slides is as follows:all figures are in Rs lacks


Ui account for delhi as per nrpc w e f 03 05 10 l.jpg

UI Account for Delhi AS PER NRPC W.E.F 03.05.10 previous slides is as follows:


Methodology for settlement of intra state ui a c for delhi utilities inter state ui account l.jpg
Methodology for settlement of Intra State UI a/c for Delhi Utilities & Inter State UI account

1. Additional UI amount

a) As per UI Regulations

all figures are in Rs lacs


Methodology for settlement of intra state ui a c for delhi utilities inter state ui account31 l.jpg
Methodology for settlement of Intra State UI a/c for Delhi Utilities & Inter State UI account

1. Additional UI amount

b) Adjustment as per Para ‘E’

all figures are in Rs lacs


Methodology for settlement of intra state ui a c for delhi utilities inter state ui account32 l.jpg
Methodology for settlement of Intra State UI a/c for Delhi Utilities & Inter State UI account

2. Differential Cap Amount

a) As per UI Regulations

all figures are in Rs lacs


Methodology for settlement of intra state ui a c for delhi utilities inter state ui account33 l.jpg
Methodology for settlement of Intra State UI a/c for Delhi Utilities & Inter State UI account

2. Differential Cap Amount

a) Adjusted as per para ‘F’ of previous slides

all figures are in Rs lacs


Methodology for settlement of intra state ui a c for delhi utilities inter state ui account34 l.jpg
Methodology for settlement of Intra State UI a/c for Delhi Utilities & Inter State UI account

3. UI Amount for Utilities

a) As per intrastate accounts

all figures are in Rs lacs


Methodology for settlement of intra state ui a c for delhi utilities inter state ui account35 l.jpg
Methodology for settlement of Intra State UI a/c for Delhi Utilities & Inter State UI account

3. UI amount matching with the Interstate UI account

a) As per para ‘G’

all figures are in Rs lacs


Slide36 l.jpg

Net UI payable/receivable by Utilities at intrastate level Utilities & Inter State UI account= Additional UI amount (with reference to interstate (para ‘E’) +/- Differential cap Amount (with reference to interstate (para ‘F’) +/- Capped UI amount (with reference to interstate UI account (para ‘G’) all fig in Rs Lacks


Slide37 l.jpg

THANK Utilities & Inter State UI accountYOU