Riverside Overpass Master Planning

Loading in 2 Seconds...

play fullscreen
1 / 26

Riverside Overpass Master Planning - PowerPoint PPT Presentation


  • 123 Views
  • Uploaded on

Riverside Overpass Master Planning. Riverside Elementary School West Contra Costa Unified School District. Presenters: Sally Swanson & Magdy Abdalla June 11, 2013. SALLY SWANSON ARCHITECTS, INC . 220 Sansome Street, Suite 1100, San Francisco CA 94104 | T: 415-445-3045 | www.swanarch.com.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Riverside Overpass Master Planning' - felcia


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

Riverside Overpass Master Planning

Riverside Elementary School

West Contra Costa Unified School District

Presenters: Sally Swanson & Magdy Abdalla

June 11, 2013

SALLY SWANSON ARCHITECTS, INC.

220 Sansome Street, Suite 1100, San Francisco CA 94104 | T: 415-445-3045 | www.swanarch.com

slide2

Agenda

  • Existing School Site
  • Master Plan Objectives
  • Caltrans Proposed Solution
  • Alternative Locations
  • Desired District Outcomes
  • Conclusion
  • Questions and Answers
slide4

Master Plan Objectives

The School’s Master Plan focuses on three elements

slide5

Master Plan Objectives

  • Open Space
    • Designate open spaces and create policies to ensure preservation and maintenance
    • Identify safe areas and pleasant open spaces
    • Landscape elements
    • Incorporate accessibility
    • Design standards that will increase safety and comfort
slide6

Master Plan Objectives

Transportation & Circulation

  • Minimal conflicts between pedestrians and vehicles
  • Increase parking facilities- visitor and disabled parking
  • Clearly identify entries into school- including signage and security

2

slide7

3

Master Plan Objectives

  • Buildings
    • High quality architecture and open space
    • In harmony with immediate surroundings
    • Facilitate accessibility and pedestrian circulation
    • Environmentally sustainable landscape
    • Economically feasible and functional
    • Support green and sustainable techniques
slide10

Caltrans Proposed Solution

at I-80 and San Pablo Dam Road

slide11

Caltrans Proposed Solution

Parking Lots and Spaces

  • Design not to ADA codes:
    • Path of Travel
      • In vehicular way
      • No designated path
    • Location to Administrative Entrance – 380 feet
    • Accessible space not compliant
      • Not Van accessible
      • Aisle not on passenger side
  • Reconfiguration of parking necessary
slide12

Caltrans Proposed Solution

Design Security Concerns

  • 4- story structure
  • Creates danger zone
  • Parking - Pedestrian movement in conflict
  • Location hides parking

Danger Zone

Fire Lane

slide13

Caltrans Proposed Solution

Space Concerns

  • Four- story structure
    • reduces site square footage
  • Reduces available parking

The scale of the overpass is not compatible with the height and design of Riverside Elementary

slide14

Caltrans Proposed Solution

Compromised Community

  • Cars, copper piping, & Computers
  • Disabled access in conflict with vehicular traffic
  • Lack of site control
slide15

Caltrans Proposed Solution

Noise Concerns

  • Landscaping removed
  • Does not improve site acoustics
  • Overpass traffic on school site cannot be controlled
slide18

Alternative Locations

Alternative #1: West side of Amador on Caltrans property

slide20

Alternative Locations

Alternative #2: Corner property at Riverside Avenue

slide23

Conclusion

  • Decision needs to be made due to cost constraints
  • Save Overpass Funding
  • Construct Overpass
  • Finalize Master Plan
  • Provide Best Development Outcomes
slide24

QUESTIONS

AND

ANSWERS

slide25

Alternate 3

Alternative #3: Acoustic barrier adjacent to Amador Street

slide26

Alternate 4

Alternative #4: Acoustic barrier adjacent to Amador Street