POCANTICO HILLS CENTRAL SCHOOL. BOARD OF EDUCATION PROJECT UPDATE AUGUST 6, 2009. Schedule. SED Approval…………………Within 2 weeks Health Dept Approval…….Within 2 weeks Bidding/Award..…………………..Sept 2009 Construction ………. Oct 2009 – Feb 2011 Closeout …………………………….. Mar 2011

Download Presentation

BOARD OF EDUCATION PROJECT UPDATE AUGUST 6, 2009

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Board of education project update august 6 2009

POCANTICO HILLS CENTRAL SCHOOL

BOARD OF EDUCATIONPROJECT UPDATEAUGUST 6, 2009


Schedule

Schedule

  • SED Approval…………………Within 2 weeks

  • Health Dept Approval…….Within 2 weeks

  • Bidding/Award..…………………..Sept 2009

  • Construction ………. Oct 2009 – Feb 2011

  • Closeout …………………………….. Mar 2011

    *Approval times are estimated based on past history


Design status

Design Status

  • Pool

    • Presentation of rendering

    • Recommending removal of slide and water feature

  • Gymnasium

    • Added locker room toilets and showers as alternate