North Truckee Drain Relocation Project

Loading in 2 Seconds...

play fullscreen
1 / 13

North Truckee Drain Relocation Project - PowerPoint PPT Presentation


  • 147 Views
  • Uploaded on

North Truckee Drain Relocation Project . Update to Flood Project Working Group Shawn Gooch, P.E. City of Sparks February 27, 2008. North Truckee Drain Relocation Project. JoAnn Meacham, P.E. Utility Manager City of Sparks. City of Sparks/HDR Engineering, Inc. Final Project Update

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'North Truckee Drain Relocation Project' - fausta


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
north truckee drain relocation project
North Truckee Drain Relocation Project
  • Update to Flood Project Working Group
  • Shawn Gooch, P.E.
  • City of Sparks
  • February 27, 2008
north truckee drain relocation project2

North Truckee Drain Relocation Project

JoAnn Meacham, P.E.

Utility Manager

City of Sparks

City of Sparks/HDR Engineering, Inc.

Final Project Update

December 18, 2007

Shawn K. Gooch, P.E. Jay Aldean, P.E.

Flood Control Manager Project Manager

City of Sparks HDR

what has happened since our last meeting
What has happened since our last meeting?
  • Corps decided to check/review their hydrology for the North Truckee Drain
    • Changed calculation methods
    • Found inconsistencies with application of original method
    • HDR performed hydrologic update
  • Changed design criteria for the Truckee River Flood Project from the 100-yr to the 117-yr storm
    • Resulted in a significantly larger conveyance structure (from 2: 10’ x 10’ culverts to 2: 22’ x 10’ culverts)
alignments characteristics
Alignments Characteristics
  • ALIGNMENT 1 – PURPLE (NDOT – VISTA)
  • Runs east along Brierley Way to Vista
  • Located in UPRR R/W (north of tracks) east of Vista
  • 3 Jack & Bore Crossings: Vista, I-80, UPRR
  • Overall Length: ~6,400 LF
  • ALIGNMENT 2 – GREEN (UPRR TO LARKIN CIR)
  • 300 LF J&B under I-80 to the South
  • People’s Drain flow combined w/ NTD on the south side of UPRR
  • Stays in back yards of private property
  • Crosses Greg Street with 40’ deep open cut
  • Follows Larkin Circle to outfall at the Truckee River
  • Overall Length: ~ 5,900 feet
  • ALIGNMENT 3 – BLUE (KLEPPE LN TO LARKIN CIR)
  • 300 LF J&B under I-80 to the South
  • People’s Drain flow combined w/ NTD on the south side of UPRR
  • Alignment follows existing NTD to Kleppe Ln
  • From Kleppe Ln across parking lot to Greg St
  • Crosses Greg Street with 40’ deep open cut
  • Follows Larkin Circle to outfall at the Truckee River
  • Overall Length: ~ 5,300 feet
project costs
Project Costs
  • Costs presented are in million dollars and do not include land costs
  • Alignment 1 $67
    • Land Requirements (PERM) (TEMP)
      • UPRR 3.4 ac 6.0 ac
      • NDOT 2.9 ac 4.3 ac
      • Other Private 0.1 ac 0.9 ac
      • # Lots Impacted 1 5
  • Alignment 2 $45
    • Land Requirements
      • UPRR 0.4 ac 1.1 ac
      • NDOT 0.4 ac 0.6 ac
      • Other Private 3.0 ac 7.5 ac
      • # Lots Impacted15 18
  • Alignment 4 $46
    • Land Requirements
      • UPRR 0.4 ac 1.2 ac
      • NDOT 0.4 ac 0.6 ac
      • Other Private 2.3 ac 6.2 ac
      • # Lots Impacted 15 23
north truckee drain realignment
North Truckee Drain Realignment
  • Next Steps
    • Value Engineering Analysis
    • Environmental Assessment
    • Utilities
    • Geotechnical Engineering
    • Surveying
    • Right-of-Way
    • Design Build vs Design Bid Build
    • 104 Cost Sharing and Authorization