1 / 22

Overview: Phased approach and scientific reach Funding and schedule Experimental layout and detailed infrastructure ne

Majarana double beta decay program. Overview: Phased approach and scientific reach Funding and schedule Experimental layout and detailed infrastructure needs Change in strategy and schedule given LAr option. Peter Doe, on behalf of the Majorana collaboration.

fagan
Download Presentation

Overview: Phased approach and scientific reach Funding and schedule Experimental layout and detailed infrastructure ne

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Majarana double beta decay program • Overview: • Phased approach and scientific reach • Funding and schedule • Experimental layout and detailed infrastructure needs • Change in strategy and schedule given LAr option Peter Doe, on behalf of the Majorana collaboration SNOLab-Majarana Aug. ‘05

  2. Phased approach and scientific reach • Scalable  3 phases: M180… 180 kg, 86% enriched 76Ge, 60 kg 120 kg 180 kg “conventional” technology m≥ 120 meV (degenerate hierarchy) M500/M1000…500-1000 kg, LAr/LN2 collaboration with GERDA? m≥ 50 meV (inverted hierarchy) MX000… Technology unknown? m≥ 10 meV (normal hierarchy) SNOLab-Majarana Aug. ‘05

  3. Possibility of early activity U/G in FY-06 Funding from Majorana institutional support No federal funding before FY-07 Funding Expect NuSAG response at end of August ?  SNOLab-Majarana Aug. ‘05

  4. 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 R&D Module Construction Enriched Ge 1st 60 kg running 2nd 60 kg running 3rd 60 kg running M180 Operating Phase Schedule SNOLab-Majarana Aug. ‘05

  5. 57 crystal module (60 kg) Conventional vacuum cryostat made with electroformed Cu. Three-crystal stack are individually removable. Vacuum jacket Cap Cold Plate Tube (0.007” wall) Cold Finger Ge (62mm x 70 mm) 1.1 kg Crystal Tray (Plastic, Si, etc) Thermal Shroud Bottom Closure 1 of 19 crystal stacks Majorana modular approach SNOLab-Majarana Aug. ‘05

  6. Allows modular deployment, early operation contains up to eight 57-crystal modules (M180 populates 3 of the 8 modules) four independent, sliding units 40 cm bulk Pb, 10 cm ultra-low background shield active 4 veto detector Veto Shield Sliding Monolith LN Dewar Inner Shield 57 Detector Module Majorana shield - conceptual design Top view SNOLab-Majarana Aug. ‘05

  7. Experimental layout/infrastructure - M180 • Three areas of underground activity: • Fabrication Electroforming copper parts • Assembly Putting it together Making it work • Data taking - staged by module 60 kg  120 kg  180 kg SNOLab-Majarana Aug. ‘05

  8. Layout - Fabrication areas Dimensions in meters SNOLab-Majarana Aug. ‘05

  9. Layout - Detector area Dimensions in meters SNOLab-Majarana Aug. ‘05

  10. Low background electroformed copper Electroformed cold finger and signal wires for MEGA Mass, M180 copper components 2 crystal thermal shroud, 250 mm wall thickness SNOLab-Majarana Aug. ‘05

  11. Electroforming copper - key elements Electroforming copper C C A A B B CuSO4 • Semiconductor-grade acids • Copper sulfate purified by recrystallization • Baths circulated with continuous microfiltration to remove oxides and precipitates • Continuous barium scavenge removes radium • Cover gas in plating tanks reduces oxide formation • Periodic surface machining during production minimizes dendritic growth • H2O2 cleaning, citric acid passivation 232Th<8Bq/kg Current density ~ 40mA/cm2 Plating rate ~ 0.05 mm/hr SNOLab-Majarana Aug. ‘05

  12. Electroforming copper - Infrastructure • HEPA-filtered air supply • Radon-scrubbed air for lowest-level work • Fume extractor for etching • Flammable and hazardous gas sensors • Radon-proof storage lockers with purge gas and vacuum capability • Etching and acid storage • Spill containment lining • Milli-Q water system w/DI supply water • Air-lock entry, washable walls • Air-conditioning to ~ 20 C • 10-6 Torr dry vacuum system Cold plate for the MEGA feasibility study at WIPP, NM. SNOLab-Majarana Aug. ‘05

  13. Infrastructure (continued) SNOLab-Majarana Aug. ‘05

  14. M180 - Special considerations • Cryogens (1000 liters) • Waste gasses (electroforming, etching) • Acids (electroforming) • Solvents (alcohol, acetone…) • Oxidizers (dilute H2O2 cleaner) • Lead (shielding) • Flammable plastics (veto) • Compressed gasses • Radon-free inert cover gasses (LN2?) • Radioactive sources SNOLab-Majarana Aug. ‘05

  15. LAr option - strategy change and schedule Decision • 2 year LArGe R&D  • Crystal, light stability in Lar • Detector Monte Carlo studies • Detector design • Engineering design • Estimate 3m Ø cryogenic vessel (~20 ton LAr) • Requires underground fabrication of dewar ( schedule) • Less electroformed copper parts ( schedule) • Would not change enrichment schedule • Would not change staging plan (~60120180 kg) • Would need higher overhead clearance (≥8 m ?) SNOLab-Majarana Aug. ‘05

  16. Summary • Majorana is modular, 60120180 500X,000 kg • M180 employs demonstrated, “conventional” technology • Material purity is critical, but achievable • Significant underground fabrication, assembly • Optimistically, enrichment late 2007, first data 2009/10 • LAr option being investigated, little schedule impact(?) SNOLab-Majarana Aug. ‘05

  17. SNOLab-Majarana Aug. ‘05

  18. Electroforming numbers Bath size: Cryostat 40 cm high x 40 cm  Tank 50cm x 75cm x 50cm 225 liters x 8 tanks 1800 liters Plating time: Cryostat 3mm / 0.05 mm hr-1 = 60 hr @50% efficiency, 12 hr/day = 10 days (2 weeks) Bath power: Cryostat Area =  x 202 x 40 = 5030 cm2 power = 5030 cm2 x 40 mA cm-2 2 kA Assume 4 kW/bath  32 kW total SNOLab-Majarana Aug. ‘05

  19. Cu parts count 54 bath weeks, 100% contingency, 8 baths  4 months electroforming @ 2 shifts/day, 5 days/week SNOLab-Majarana Aug. ‘05

  20. Plating Bath Process Parameters • Plating is done onto polished, cleaned, stainless steel mandrels in the shape of the desired parts • Current density is ~40 mA/cm2 • Plating rate is ~0.05 mm/h • BaSO4 collects in the micro-filtration stage and acts as radium scavenge • CoSO4 was added as a holdback carrier for the cosmogenic 56,57,58,60Co present in the starting copper • HCl and Thiourea affect copper crystal nucleation and grain size SNOLab-Majarana Aug. ‘05

  21. SNOLab-Majarana Aug. ‘05

  22. SNOLab-Majarana Aug. ‘05

More Related