An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2006 Hurricane PreparednessJune 5, 2006Sumter Electric Cooperative, Inc R. Ben Brickhouse: Director of Engineering & IT John J. LaSelva: Director of Reliability & Operations

  2. SECO Overview • 7 Counties in Central Florida • 150,000+ members • 8.7% member growth rate 2

  3. SECO Electrical System Overview • Overhead Distribution: • 4537 circuit miles • 149,000 poles – median pole age is 17 yrs • Underground Distribution (URD) • 1845 circuit miles • Transmission Facilities: • 72 miles of 69kv transmission circuits • 1250 structures • 43 Substations 3

  4. Steps to Hurricane Preparedness: • Reliability Based Design • On-going Asset Management • Vegetation Management • Restoration Plan 4

  5. SECO Reliability Based Design • Transmission: • Joint transmission planning with Progress Energy Florida for capacity and reliability • Minimize all radial transmission delivery points • All new transmission structures are “Spun Concrete” versus wood • Designed per NESC “Extreme” wind loading criteria 5

  6. SECO Reliability Based Design • Substation: • All new and renovated substations: • “Low Profile” steel • “Ring Bus” configured and designed for multiple power transformers with load transfer capability • All existing and new substations: • Connections for SECO’s mobile transformers • SCADA control including individual feeder telemetry 6

  7. SECO Reliability Based Design • Distribution: • Designed per “Rural Utility Service (RUS)” and “National Electric Safety Code (NESC)” specifications for 100 mph wind loading • ~80% of new subdivision construction is URD • New OH feeder circuits are constructed to reliability based model feeder standards for maximizing both conductor sizing and sectionalizing capability 7

  8. SECO On-Going Asset Management • Asset Inspections: • Transmission: Ground / climbing inspection completed in 2006 • 56 structures will be replaced with spun concrete poles • 5 year cycle • Thermographic Inspections: • Transmission: Annually • Substation: Bi-monthly • “ALL” OH Feeder Lines: Every 18 months • URD Facilities: Reliability dictates 8

  9. SECO On-Going Asset Management • Distribution: • Pole inspections: • Ground line & visual - Current 9 year cycle begun in 1990. Going to 8 yr in 2007. • 2003 – 2005: • 37,599 Inspected • 255 Rejected and replaced (0.7% rejection) • URD Inspections: • Full inspection was complete in 2000. Will implement an 8 yr cycle in 2007. • “State of the Art” fully integrated GIS / Design / OMS / Storm Center Systems – General Electric 9

  10. SECO – Vegetation Management • 3 year trim cycle of all OH facilities since 1996 • Hurricanes in 2004: Trees - Primary cause of outages • SECO lost 662 poles in 3 hurricanes (0.4%) Poles Up Wires Down 10

  11. Post Hurricane Evaluation of Trim Policies: Conclusions: • Trees were major cause of outages • Increased tolerance by members for aggressive trimming • Increase budget expenditures for long term gains (Increased 30% in 2006) Actions Taken: • Entire system assessed by ACRT (Consultant) • 2% trees contacting lines (industry 10%) • Revised specifications: • Species specific • Increase to remove trees vs. trim • Implemented “Ground to Sky” for new circuit projects 11

  12. BEFORE 12

  13. AFTER 13

  14. BEFORE 14

  15. AFTER 15

  16. BEFORE 16

  17. AFTER 17

  18. BEFORE 18

  19. AFTER 19

  20. SECO: Disaster Recovery Plan 20

  21. Restoration Model PERSONNEL PLAN LOGISTICS MATERIAL 21

  22. SECO’s Emergency Plan Prior to Storm Season • Plan Reviewed / Updated • Planning with Local EOC’s • Materials Staged • Logistics Pre-Arranged • Caterers, fuel, hotels, buses, tents, ice, water, etc. • Personnel • Florida / Southeast Mutual Aid, establish contracts with vegetation crews and line crews 22

  23. SECO Restoration Priority • Transmission Lines • Substations • Feeders • Emergency Services (Hospitals, Special needs Shelters and Shelters) • Fused Laterals / Taps • Individual Homes 23

  24. Customer Newsletter: Explains restoration process at the beginning of storm seasonPaid Advertisements: Appear in the daily newspapers 1 & 2 days prior to storm impact 24

  25. SECO’s Emergency Plan Hurricane Predicted • Activate Plan (Pull the Trigger) • Run “Damage Prediction and Manpower” Model: Based on historical damage • Materials / Manpower / Logistics Activated pre-landfall 25

  26. Sept 2004 - Daily MWH Sales“Stick to the Plan” Storm Impact 26

  27. Conclusions • SECO currently designs a reliable transmission, substation, and distribution system based on RUS and NESC standards • SECO currently performs inspections on all its assets – frequency is increasing in 2007 • SECO has an aggressive vegetation management program that was revised post 2004 hurricanes • SECO has a disaster recovery plan that is reviewed, revised, and institutionalized based on “Lessons Learned” by both SECO and the industry 27

  28. Questions? 28