IARC Milestones completed. Sept 2011: End of Tevatron Run, FESS obtains ~full access to infrastructure at CDF, PPD begins D&D in CDF assembly bldg Sept 2011: HOK submits engineering drawings & bid documents for state funded OTE building

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' IARC Milestones completed' - etan


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
iarc milestones completed
IARC Milestones completed
  • Sept 2011: End of Tevatron Run, FESS obtains ~full access to infrastructure at CDF, PPD begins D&D in CDF assembly bldg
  • Sept 2011: HOK submits engineering drawings & bid documents for state funded OTE building
  • Oct 2011: Industrial Area upgrade project near completion, $ 350 K under budget, excess funds transferred to Feynman sanitary project
  • Nov 7, 2011: HOK submittal checked by FESS, bid documents ready, signed requisition for $ 14.5 M… OTE building soon out for bids!
proposed iarc timeline ote building
Proposed IARC timeline (OTE building)
  • Nov-Jan,2012:OTE bldg bid response & evaluate
  • Feb, 2012: Director’s review prior to bid award, set scope of initial contract and award contract
  • Nov-Feb 2012: PPD clears out majority of West end of CDF for OTE building construction
  • Mar 2012 Dec 2013 OTE construction
  • May 2013: Provide detailed plan for first occupants of OTE building (Project X, APC, IARC, etc)
  • Dec 2013: beneficial occupancy of OTE, final build out of FNAL supplied systems (e.g partitions)
  • Apr 2014: FNAL OTE occupants begin to move in
proposed iarc timeline cdf building
Proposed IARC timeline (CDF building)
  • Dec 2011, FESS request for FY12 funds to estimate FY13-14 assembly bldg refurbishment
    • Determine required life safety and fire upgrades
    • Determine changes for ADA compliance
    • Determine plan for CDF tours and plan stairwells
    • Detailed IARC requirements, plan for various infrastructure
    • Plan for CDF office rework
    • What is paid for with D&D funds vs GPP
  • Jan-July 2012: PPD removes cable carrier and cleans out CDF counting rooms & deep pit area
  • Oct 2012: Transfer ownership of CDF building to Technical Division ? PPD continues to occupy East end of first floor except (cryo) & tour area.
proposed iarc timeline cdf building1
Proposed IARC timeline (CDF building)
  • Mar 2012- Sept 2012: FESS makes plan for refurbishment of CDF building (can we start design ?)
  • Oct 2012-Mar 2013: Refurbishment GPP design
  • Apr 2013 refurbishment contracts out for bid, Notice to proceed in Jun 2013
  • Jun 2013: PPD initial D&D complete, office areas, deep pit, west end and perimeter of east end all available to FESS contractors for refurbishment
  • Jun 2013 – Jun 2014 Refurbishment CDF building and IARC infrastructure installation
  • Jun 2014: IARC program officially begins and industry occupants begin to move in