PHENIX Run-13 status. Hubert van Hecke. Commissioning continues. VTX stripixels. Commissioning was going well in December, but Massive leaks were seen in the outer barrel layer of the VTX ( stripixels )

Download Presentation

PHENIX Run-13 status

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Phenix run 13 status

PHENIX Run-13 status

Hubert van Hecke

Hubert van Hecke - 19 Feb 13 Time meeting


Commissioning continues

Commissioning continues

VTX stripixels

  • Commissioning was going well in December, but

  • Massive leaks were seen in the outer barrel layer of the VTX (stripixels)

  • Removed the East half of the detector, disassembled it, reassembled with only the FVTX, and reinstalled in the IR

  • Investigation identified galvanic corrosion between carbon and Aluminum as the cause

  • VTX pixels (inner 2 barrels) and FVTX don’t use Aluminum

FVTX

VTX pixels

FVTX

VTX stripixels

Hubert van Hecke - 19 Feb 13 Time meeting


Commissioning continues1

Commissioning continues

  • FVTX back and operating (>98% live channels)

  • Flammable gas is on since Feb 1, 2-person watch shifts started Jan 22

  • Cosmicstakensince 4 Feb, ongoing when no beam

  • Shielding wall rolled in on7 Feb, area closed up on 8th

  • Test runs with all (~20) subsystems today

Hubert van Hecke - 19 Feb 13 Time meeting


Near term objectives

Near-term objectives

  • When no beam, run cosmics

    • Cosmics are needed to study momentum smearing, charge-sign efficiencies, trigger issues, backgrounds etc.

    • Cosmics will be collected in beam down-time periods throughout the run

  • Commission with beam as it arrives

  • Access during the day, as needed