Breaching the Mahar Regional School Dam

Breaching the Mahar Regional School Dam. Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011. Presentation Outline. Introductions – Derek Schipper, P.E. and Greg Hunt GZA GeoEnvironmental , Inc., Norwood, MA Existing Site Information

enid
Download Presentation

Breaching the Mahar Regional School Dam

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Breaching the Mahar Regional School Dam Presentation to Ralph C. Mahar Regional School Committee GZA GeoEnvironmental, Inc. February 9, 2011

  2. Presentation Outline • Introductions – Derek Schipper, P.E. and Greg Hunt • GZA GeoEnvironmental, Inc., Norwood, MA • Existing Site Information • Project Background • Summary of Dam Breach Feasibility Study • Proposed Dam Breach Design • Permitting & Construction • Preliminary Cost Estimate • Timeline • Example Project • Questions

  3. Existing Site

  4. Existing Dam Spillway & Low-level Outlet with Culvert through Dam Concrete Core Wall Around Spillway Pond / Impoundment Dam

  5. Dam Information • Mahar Regional School Dam: • Dam Size: Small • Hazard Rating: Significant • Condition: Poor • Main Deficiencies: • Growth of trees throughout dam • Erosion on top of dam and near waterline • Embankment seepage

  6. Project Background • 1950s: Dam constructed • 1960: Dam repaired following spillway damage • 2005: New MA Dam Safety Regulations go into effect • 2008: DCR Office of Dam Safety (DCR/ODS) ordered that dam be inspected by professional engineer • July 2009: GZA performed Phase I Inspection/ Evaluation of Dam; found dam to be in Poor condition • Sept. 2009: School District ordered by DCR/ODS to repair, breach, or remove dam by March 11, 2011and continue to have dam inspected every 6 months.

  7. Project Background (Cont.) • 2009 – present: GZA has performed three 6-month inspections, dam found to be in similar condition • 2010: School Committee approves plan to address condition of dam through dam removal/breach • 2010: GZA prepares Dam Breach Feasibility Study to evaluate potential dam breach

  8. Dam Breach Feasibility Study • GZA Scope of Work: • Extension request from DCR/ODS (11/30/2012 New Date) • Field Work – Site Survey, Wetland Resource Evaluation, Sediment Analysis • Technical Analysis – Hydrologic & Hydraulic Modeling, Conceptual Breach Design • Permitting Investigation – Estimate of project impacts and required local, state, and federal permits • Cost Estimate & Funding Sources – Cost estimate to perform dam breach & potential grants

  9. Existing Site

  10. Proposed Conditions – Conceptual Design Remove Existing spillway/culvert. Excavated Breach Channel. Partial Removal of Core Wall Restored Gulf Brook Stream Channel Restored Wetland & Upland Vegetation

  11. Proposed Conditions – Conceptual Design Restored Gulf Brook Stream Channel Excavated Section of Dam for Breach Channel Grassed Slopes Concrete Core Wall to Remain Below Ground Stone Erosion Protection

  12. Permitting & Construction • Environmental Permitting: • Numerous Local, State, and Federal permits required to work in wetland resource areas • Permit process will likely lasts 9 months – 1 year • Final Design and Specifications: • Prepare final design plans and specifications suitable for contractor bidding and construction • Construction: • Once Final Design is complete and permits are in place, work awarded to Contractor to perform breach work • Construction to take about 4 weeks

  13. Preliminary Cost Estimate • Permitting & Final Design Engineering $ 85,000 • Construction Work $ 170,000 • Construction Contingency (25%) $ 43,000 • Construction Engineering (5 weeks) $ 35,000 • Total Estimated Cost $ 333,000

  14. Preliminary Timeline • Spring 2011: Submit Environmental Permitting • Summer 2011: Final Engineering Design & Specifications • Spring 2012: Award Construction Contract • Summer 2012: Perform Dam Breach Work • Fall 2012 - 2013: Revegetation Monitoring & Maintenance by Contractor • Note: Under current timeline, dam breach work must be completed by November 30, 2012, and Six-Month Follow-Up Inspections of Dam must continue until work is completed.

  15. Questions?

  16. Example Project: Champlin Pond Dam Breach Before Dam Breach One Year After Dam Breach

  17. Champlin Upper PondDam Removal Construction

  18. From Left Abutment – April, 2005

  19. From Left Abutment – September, 2005

  20. From Left Abutment – November, 2005

  21. From Left Abutment – August, 2006

  22. Mouth of Channel – November, 2005

  23. Mouth of Channel – November, 2005

  24. Mouth of Channel – June, 2006

  25. From Right Abutment – September, 2006

  26. Discussion/ Questions….