Patrick Kearon The Bristol Port Company

Patrick Kearon The Bristol Port Company. Background. Global warming – we all need to reduce CO 2 output from our activities UK Target = 20% reduction in 1990 CO 2 levels by 2010 South West Target = 11-15% of electricity from renewable sources

ellie
Download Presentation

Patrick Kearon The Bristol Port Company

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Patrick KearonThe Bristol Port Company

  2. Background • Global warming – we all need to reduce CO2 output from our activities • UK Target = 20% reduction in 1990 CO2 levels by 2010 • South West Target = 11-15% of electricity from renewable sources • Dependence on finite fossil fuels & increasing energy costs • UK is Europe’s windiest country - average mean wind speeds >7m/s (18mph)

  3. The Answer Imperative for The Bristol Port Company to develop a local renewable energy source to supply port demand

  4. Outline of Proposals • Erect 3 wind turbines (up to 3 MW), including associated bases and cables • Construct control building & access ways • Combined 9 MW = up to 75% of port’s electricity demand • Development site is 8.5 hectares of reclaimed land in Avonmouth Dock • Adjacent to Severn Estuary

  5. Site Location

  6. Site Selection - Alternatives • 9 potential locations short-listed and tested against 3 key factors: • Wind generating potential • Aviation safety (Filton Airfeld) • Possible impacts on birds using the estuary • This location in Avonmouth Docks was identified as optimum site • Turbine location finely adjusted to not interfere with air safety & bird migration routes

  7. The Preferred Site

  8. Rotor diameter 70 metres (35m radius) 120m 393 ft Hub height 85 metres 279 feet Typical Wind Turbine Dimensions

  9. Environmental Issues • Geology/Ground Conditions • Hydrology/Hydrogeology • Ecology • Landscape and visual impacts • Archaeology • Traffic and transport • Noise and vibration • Telecommunications • Air traffic • Marine navigation

  10. Landscape and Visual Impacts • Evaluate effect on local landscape • Turbines located in low-lying, heavily industrialised landscape, with many tall structures & buildings • Landform, structures & woodlands restrict visibility • Turbines will be visible from: • Avonmouth Village (partial, restricted views, change inevitable in places) • Pill (noticeable, but not intrusive) • Higher elevations e.g. Lawrence Weston & Shirehampton (more visible, but distant & panoramic, not intrusive)

  11. Photomontage of Landscape

  12. Ecology and Birds • No valuable habitats on site, but next to Severn Estuary SPA, SSSI and Ramsar site • Ecological surveys to inform assessment of impacts on wildlife, including • Extended Phase 1 habitat survey • Bird surveys (e.g. High tide/low tide counts, night time, migration and breeding surveys) • Key potential impacts on birds are Disturbance & Collisions • With mitigation no adverse impact during construction • 5 years monitoring (review in 2 years)

  13. Bird Movements

  14. Archaeology • Assessment of archaeological remains in the vicinity of the development site: • Terrestrial archaeology • Maritime archaeology and historic activity • Borehole assessment • No known sites or monuments affected by the development • Construction of turbines includes 30 metre piles into made ground • Mitigation/Monitoring – archaeological recording

  15. Historic Mapping

  16. Balance of Effects • No major adverse environmental impacts • Potential disturbance of SPA birds and changed views from areas of Avonmouth Village • All other negative impacts avoided or reduced by mitigation and design measures • 17-26% of south west’s renewable energy target • Provision of up to 75% of Port’s electricity • Significant reduction in green house gasses (18,319 tonnes CO2 /plus SO2 & NOx)

  17. Construction & Operation • Construction end 2006 • Construction programme about 36 weeks • In operation this time in 2007 • Operational life of 25 years • Turbines then either replaced, refurbished or removed & site reinstated

  18. The Way Forward • BPC agreement with Ecotricity who will construct, own and operate the turbines • BPC provided with energy for life of turbines • “Overspill” electricity is publicly available - see (http://www.ecotricity.co.uk) • We all need to do more to tackle global warming problem • Wind turbines can contribute to the renewable energy solution