1 / 57

Claims Administration and Procedure Under the AIA and EJCDC

Claims Administration and Procedure Under the AIA and EJCDC. Adrianne Huffman Chillemi September 19, 2008. EJCDC. 1. Reference to “EJCDC” is to the Engineers Joint Contract Document Committee of the National Society of Professional Engineers 1.1 EJCDC General Conditions is form C-700. AIA.

elina
Download Presentation

Claims Administration and Procedure Under the AIA and EJCDC

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Claims Administration and Procedure Under the AIA and EJCDC Adrianne Huffman Chillemi September 19, 2008

  2. EJCDC • 1. Reference to “EJCDC” is to the Engineers Joint Contract Document Committee of the National Society of Professional Engineers • 1.1 EJCDC General Conditions is form C-700

  3. AIA • 2. Reference to “AIA” is to The American Institute of Architects • 2.1 General Conditions is AIA Document A201 – 2007

  4. “CLAIM” • 3. “Claim” Defined • 3.1 EJCDC General Conditions, Paragraph 1.01A • 11. Claim - A demand or assertion by OWNER or CONTRACTOR seeking an adjustment of Contract Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim.

  5. 3.2AIA-201 General Conditions, Section 15.1.1 Definitions • A Claim is a demand or assertion by one of the parties seeking, as a matter of right, payment of money or other relief with respect to the terms of the Contract. The term "Claim" also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. The responsibility to substantiate Claims shall rest with the party making the Claim.

  6. OWNER CAUSED CLAIMS • 4. Reasons for Claims arising under construction contracts • 4.1 Owner caused: • 4.1.1 Additions to plans; • 4.1.2 Changes to plans; • 4.1.3 Delays; • 4.1.4 Misrepresentations; and • 4.1.5 Interference 4.1.6 Delay or Failure to Make Payment

  7. ENVIRONMENTALCLAIMS • 4.2 Environmental • 4.2.1 Unexpected site conditions • 4.2.2 Weather delays • 4.2.3 Other • 4.3.1 Prime Contractor Delays • 4.3.2 Subcontractor Delays

  8. 5. Continuance of Work

  9. 5.1 EJCDC General Conditions, Paragraph 6.18 Continuing the Work • A. CONTRACTOR shall carry on the Work and adhere to the progress schedule during all disputes or disagreements with OWNER. No Work shall be delayed or postponed pending resolution of any disputes or disagreements, except as permitted by paragraph 15.04 or as OWNER and CONTRACTOR may otherwise agree in writing.

  10. 5.2 AIA General Conditions, Section 15.1.3, 15.1.4 and 15.1.5 • Continuing Contract Performance. Pending final resolution of a Claim, except as otherwise agreed in writing or as provided in Subparagraph 9.7 and Article 14, the Contractor shall proceed diligently with performance of the Contract and the Owner shall continue to make payments in accordance with the Contract Documents. The Architect will prepare Change Orders and issue Certificates for Payment in Accordance with the decisions of the Initial Decision Maker.

  11. AIA General Conditions, Section 15.1.4, Claims for Additional Cost • If the Contractor wishes to make a Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Section 10.4.

  12. AIA General Conditions, Section15.1.5.1, Claims for Additional Time • If the Contractor wishes to make Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay, only one Claim is necessary.

  13. AIA General Conditions, Section 15.1.5.2, Claims for Additional Time/Weather-Related • If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time, could not have been reasonably anticipated and had an adverse effect on the scheduled construction.

  14. NOTICE • 6. Notice of a Claim. • 6.1 EJCDC General Conditions, Paragraph 10.05 • A. Notice: Written notice stating the general nature of each Claim, dispute, or other matter shall be delivered by the claimant to ENGINEER and the other party to the Contract promptly (but in no event later than 30 days) after the start of the event giving rise thereto.

  15. Notice of the amount or extent of the Claim, dispute, or other matter with supporting data shall be delivered to the ENGINEER and the other party to the Contract within 60 days after the start of such event (unless ENGINEER allows additional time for claimant to submit additional or more accurate data in support of such Claim, dispute, or other matter)

  16. D. No Claim for an adjustment in Contract Price or Contract Times (or Milestones) will be valid if not submitted in accordance with this paragraph 10.05.

  17. 6.2AIA-201 General Conditions, Section 15.1.2 • Notice of Claims. Claims by either the Owner or the Contractor must be initiated by written notice to the other party and to the Initial Decision Maker. Claims by either party must be initiated within 21 days after occurrence of the event giving rise to such Claim or within 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. • 6.2.1 Concept of “reserving” a Claim versus “real-time” Claims

  18. 6.3 Does failure to give timely written notice in accordance with the terms of the contract bar a Claim under North Carolina law?

  19. 6.3.1 Generally. See, e.g. Blankenship Constr. Co. v. State Highway Comm’n, 28 N.C. App. 593, 222 S.E. 2d 452 (1976) (denying a contactor’s claim for additional work for failure to give written notice to the contracting authority even though the contracting authority was on actual notice of the unanticipated conditions). See also Biemann and Rowell v. Donohoe Companies, 147 N.C. App 239, 556 S.E. 2d 1 (2001), which required compliance with the written notice provision of the contract because:

  20. ▪ failure to give proper notice to the architect prevented the architect from performing as an arbiter of disputes; • ▪ acceptance of final payment was a waiver of a Claim under the general conditions of the contract; and • ▪ failure to give proper notice was a breach of [Biemann’s] duty to mitigate damages and prejudiced the other party’s ability to cure any problem.

  21. But see, Davidson and Jones, Inc. v. N.C. Dept. of Admin., 315 N.C. 144, 337 S.E. 2d 463 (1995) (apparently relaxing the notice requirements in the public contracting area).

  22. WAIVER OF NOTICE • 6.3.2 Can the contract’s notice requirements be waived?

  23. 6.3.2.1 It has been well-established in North Carolina that “[t]he provisions of a written contract may be modified or waived by a subsequent parol (oral) agreement, or by conduct which naturally and justly leads the other party to believe the provisions of the contract are modified or waived.” W.E. Garrison Grading v. Piracci Construction,27 N.C. App. 725, 221 S.E. 2d 512 (1975) quoting J.R. Graham v. Randolph County, 212 S.E. 2d 542, 544-45 N.C. App. 1975). See also Childress v. Trading Post, 247 N.C. 150, 100 S.E. 2d391 (1957); Son-Shine Grading v. ADC Construction, 68 N.C. App. 417, 315 S.E. 2d 346 (1984); Triangle Air v. Caswell County, 57 N.C. App 482, 291 S.E. 2d 808 (1982).

  24. 6.3.3 What if a contract may only be amended in writing?

  25. 6.3.3.1 EJCDC General Conditions, Paragraph 3.04 • A. The Contract Documents may be amended to provide for additions, deletions, and revisions in the Work or to modify the terms and conditions thereof in one of more of the following ways: (i) a Written Amendment; (ii) a Change Order; or (iii) a Work Change Directive.

  26. B. The requirements of the Contract Documents may be supplemented, and minor variations and deviations in the Work may be authorized, by one or more of the following ways: (i) a Field Order; a (ii) ENGINEER’s approval of a Shop Drawing or Sample; or (iii) ENGINEER’s written interpretation or clarification.

  27. 6.3.3.2 AIA -201 General Conditions, Section 1.1.2 The Contract

  28. The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a Modification. The Contract Documents shall not be construed to create a contractual relationship of any kind

  29. (1) between the Contractor and the Architect or the Architects Consultants, • (2) between the Owner and a Subcontractor or a Sub- subcontractor, • (3) between the Owner and the Architect or the Architect’s consultants or

  30. (4) between any persons or entities other than the Owner and the Contractor. The Architect shall, however, be entitled to performance and enforcement of obligations under the Contract intended to facilitate performance of the Architect’s duties.

  31. Paragraph 1.1.1 …….A Modification is • (1) a written amendment to the Contract signed by both parties, • (2) a Change Order, (3) a Construction Change Directive or (4) a written order for a minor change in the Work issued by the Architect.

  32. WAIVER • 6.3.3.3 Waiver can occur by oral agreement or conduct even where a change, modification or amendment has to be in writing by the contract terms. See Garrison and Graham, supra. See in particular General Specialties Company v. Nello Teer Company, 41 N.C. App. 273, 54 S.E. 2d 658 (1979).

  33. General incurred additional off-site storage costs and submitted a claim to Nello Teer. Nello Teer refused the claim because written notice was not given within 72 hours of the claim arising as provided in their contract. The Court concluded the written notice provision had been waived because an Assistant V.P. of Nello Teer orally agreed to the off-site storage.

  34. 6.3.3.4 How can this apparent contradiction in court decisions be reconciled?

  35. 6.4 How can notice issues be avoided? • 6.4.1 THE PARTIES SHOULD BE ADVISED TO READ AND STRICTLY COMPLY WITH THE NOTICE PROVISIONS OF THE CONTRACT BEFORE THE WORK IS COMMENCED

  36. 6.4.2 If a contractor has not strictly complied with the notice provisions, then as soon as possible the contractor should make a Claim in writing by including the following: • a. A recital of the specific contract provisions being relied upon in the contract;

  37. b. Identify and describe the extra work that is, was or will be performed; • c. Set forth the facts upon which the contractor relied showing that the owner had knowledge or directed the work be performed; • d. State the facts regarding the authority or the apparent or actual authority of the representative who directed the work be performed;

  38. e. State any facts which suggest the Owner ratified its representative’s directions; • f. State any facts that indicate the owner had actual knowledge that the contractor claimed the work to be extra work prior to the contractor performing;

  39. g. State any facts which suggest the contractor performed the disputed work under protest and reserved its rights to be paid or have the contract amended or modified at a later date; and • h. Consult with an attorney.

  40. CLAIM RESOLUTION • 7. Claim Resolution • 7.1 Claims generally have to first be submitted to the Engineer/Architect in accordance with the terms of the contract between the owner and contractor. • 7.1.1 EJCDC General Conditions, Paragraph 10.05

  41. A. Notice: Written notice stating the general nature of each Claim, dispute, or other matter shall be delivered by the claimant to ENGINEER and the other party to the Contract promptly (but in no event later than 30 days) after the start of the event giving rise thereto.

  42. Notice of the amount or extent of the Claim, dispute, or other matter with supporting data shall be delivered to the ENGINEER and the other party to the Contract within 60 days after the start of such event (unless ENGINEER allows additional time for claimant to submit additional or more accurate data in support of such Claim, dispute, or other matter).

  43. A Claim for an adjustment in Contract Price shall be prepared in accordance with the provisions of paragraph 12.01B. A Claim for an adjustment in Contract Time shall be prepared in accordance with the provisions of paragraph 12.02B. Each Claim shall be accompanied by claimant’s written statement that the adjustment claimed is the entire adjustment to which the claimant believes it is entitled as a result of said event.

  44. The opposing party shall submit any response to ENGINEER and the claimant within 30 days after receipt of the claimant’s last submittal (unless ENGINEER allows additional time).

  45. 7.1.2AIA-201 General Conditions, Section 15.2,Initial Decision • 15.2.1. Claims, excluding those arising under Sections 10.3, 10.4, 11.3.9, and 11.3.10, shall be referred to the Initial Decision Maker for initial decision. The Architect shall serve as the Initial Decision Maker, unless otherwise indicated in the Agreement.

  46. Except for those Claims excluded by this Section 15.2.1, an initial decision shall be required as a condition precedent to mediation of any Claim arising prior to the date final payment is due, unless 30 days have passed after the Claim has been referred to the Initial Decision Maker with no decision having been rendered. Unless the Initial Decision Maker and all affected parties agree the Initial Decision Maker will not decide disputes between the Contractor and persons or entities other than the Owner.

  47. 15.2.2 The Initial Decision Maker will review Claims and within ten days of the receipt of the Claim take one or more of the following actions: (1) request additional supporting data from the claimant or a response with supporting data from the other party,

  48. (2) reject the Claim in whole or in part, • (3) approve the Claim, • (4) suggest a compromise, or

  49. (5) advise the parties that the Initial Decision Maker is unable to resolve the Claim if the Initial Decision Maker lacks sufficient information to evaluate the merits of the Claim or if the Initial Decision Maker concludes that, in the Initial Decision Maker ’s sole discretion, it would be inappropriate for the Initial Decision Maker to resolve the Claim. • 7.2 Party making the claim has the burden of proof (of convincing) the Initial Decision Maker .

  50. 7.3 Decision by Architect/Engineer • 7.3.1 EJCDC General Conditions, Paragraph 10.05

More Related