Katy Freeway. 40 mile section of IH 10 from downtown Houston to the Brazos River Constructed in the 1960’s Design capacity of 79,200 vehicles per day Pavement design life of 20 years Part of Interstate Highway System Maintenance cost $ 49,375 per mile. Katy Freeway - Reality GRIDLOCK.

Download Presentation

Katy Freeway

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Katy freeway

Katy Freeway

  • 40 mile section of IH 10 from downtown Houston to the Brazos River

  • Constructed in the 1960’s

  • Design capacity of 79,200 vehicles per day

    • Pavement design life of 20 years

  • Part of Interstate Highway System

  • Maintenance cost $ 49,375 per mile


Katy freeway reality gridlock

Katy Freeway - RealityGRIDLOCK

  • 207,800 vehicles per day

  • 11 hours daily congestion

  • 30 to 40 year old pavement

  • Annual maintenance costs of $ 197,500/mile (4 times normal highway maintenance costs)


Katy freeway

  • 23 mile section from IH 610 to Fort Bend County line

  • 8 main lanes, 2 managed lanes, 6 feeder lanes

  • Construction 2003 - 2009

  • 10 Sections

  • Beginning at east and west ends working to center

  • First construction contract awarded June 11, 2003


Katy freeway

$ 2,400,000,000

CONSTRUCTION COST

(excludes ROW,utilities)


Utility adjustments

UTILITY ADJUSTMENTS

  • Expense of TxDOT’s ROW Division

  • ROW acquisition,relocation assistance,utility relocation $599,000,000

  • Construction period spans 2003-2009

  • Annual Statewide Budget - $300,000,000 for all TxDOT ROW Division

  • Katy utility adjustments alone will be one-third of ROW Division’s budget for three years running


Centerpoint energy work

CenterPoint Energy Work

  • 40 miles of OH distribution

  • 42 underground distribution crossings

  • 21.5 miles of Entex gas lines

  • Fiber optic reroute and one T-comm antennae

  • 5.7 miles OH Transmission 138kV double circuit converted to UG

  • 3 Substations modified for UG Transmission


110 000 000

$ 110,000,000

  • Transmission

  • Substation

  • Overhead Distribution

  • Underground Distribution

  • Fiber Optics

  • Entex

    28 Contracts over 2003 - 2006


Bureaucratic red tape

Bureaucratic Red Tape

  • Unprecedented amount of Bureaucratic red tape

  • Extended review/approval time for Utility Adjustment contracts

  • Hesitant to make decisions

  • Disconnect between TxDOT’s local office and Austin


Txdot

TXDOT

  • Contract required for relocations prior to start of any construction

  • Austin-TXDOT review/approval of contracts

  • Construction overhead cost issue

  • 431 parcels required for project .Not all parcels acquired prior to construction letting

  • GEC (PB) controls project

  • Project Website established


Centerpoint energy underground distribution

CenterPoint Energy Underground Distribution

  • 45 locations with proposed underground

  • 42 crossings of I-10 (Katy Freeway)

  • 90 estimates/work orders

  • Plan & profile drawings and traffic control plans - 120 drawings, 80 traffic control [plans


Katy freeway

CEHE

  • Drawing review required by all utilities through GEC - PB

  • Project crossed ROW of several governmental agencies

    • TXDOT

    • Harris County Flood Control

    • Army Corp of Engineers

    • City of Houston

    • Hedwig Village

    • Spring Valley

    • Hunters Creek


Katy freeway

CEHE

  • TXDOT lacked numerous parcels but still expedited construction schedule

  • Directional bores

  • 3 dry bore crossings

  • Existing easements, required temporary construction easements for work area

  • City permits - lane closures,street cuts


Cehe distribution underground status

CEHE Distribution Underground Status

  • 10 Sections (42 crossings total)

    • 24 crossings complete

    • Sections 1,2,8,9,10 - 100% complete

    • 8 crossings under construction

    • 7 on hold - require ROW by TXDOT

    • 3 crossing scheduled for 2006