An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Costs of Managing NORM Brett Young

  2. Infrastructure • Replacement of contaminated equipment • Xmas trees, esp’s, tubulars, valves, pumps • Dedicated NORM Storage facility • Interim storage areas (Other locations) • Decontamination facility (fixed/mobile) • Long term disposal options • (Shallow burial/deep well/bioremediation) • Transportation of contaminated equipment

  3. Administration • Specifications e.g. PDO SP 1170 • Guidelines or Local Rules • Development/Review of NORM mgt system • Review and renewal of contracts (V.o.C.) • Hoists/rigs, pigging, tank/vessel cleaning, plant maintenance, NORM & WTF Management • Contractors implementing Corporate NORM Mgt system into their HSE mgt systems • System Audits/inspections (Contract Holder and Company self assessments/audits)

  4. Identification, Assessment and Control, Recovery • NORM meters - 3 types required • Each asset & various contractors • Activity Analysis e.g. sludge/sands/wax • PPE • Medical surveillance

  5. Human Resources • CRFP or SRPS • RPS • RPT’s • External consultants e.g. RPA • Training • 5000 Awareness @ 1 hour = 5000 hrs • 200 RPT @ 4 hours = 800 hrs • 20 RPS @ 2-3 days = 480 hrs Total = 5880 hrs or 735 days

  6. Examples • Production losses • Well head closed for 2 months (150m3/day) • Well closed for 3 weeks (300 m3/day) • Hoist and camp moved • Tanks not emptied for nine years • Known to contain NORM • Then delays with NORM storage facility • Confusion as to how to transport/store the sludge • Unable to collect sample prior to emptying tank contents

  7. Hidden Costs • Meetings/Correspondence • Radiation Advisory Committee • Emails/phone calls/Advice and assistance • Morale - fear of exposure, uncertainty • Failing to comply with systems • Legal Responsibility & Moral issues • Health of Workforce • Occupational Illnesses (lung cancer) • Loss of income earner • Reputation