CKOV Progress 5-4-07
This presentation is the property of its rightful owner.
Sponsored Links
1 / 7

CKOV Progress 5-4-07 PowerPoint PPT Presentation


  • 50 Views
  • Uploaded on
  • Presentation posted in: General

CKOV Progress 5-4-07. PMT Shields completed. Awaiting paint job - @Mississippi. PMT Enclosures parts @IIT begun (delrin material ordered). PMT selection at Trieste begun (April). LED Pulser Electronics and PMT HV Supply in hand. PMT Base v-1 @ FNAL complete.

Download Presentation

CKOV Progress 5-4-07

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Ckov progress 5 4 07

CKOV Progress 5-4-07

  • PMT Shields completed. Awaiting paint job - @Mississippi.

  • PMT Enclosures parts @IIT begun (delrin material ordered).

  • PMT selection at Trieste begun (April).

  • LED Pulser Electronics and PMT HV Supply in hand.

  • PMT Base v-1 @ FNAL complete.

  • CKOV Box Machining to begin @Iowa in May.

  • CKOV Steele Ordered IIT+Iowa (3wk delivery).

  • Nickel Plating company in hand. (2 wk turn around

  • Aerogel Order Placed by Dan. (April)

  • Aerogel Box dimensions checked- machining in May.

  • Schott Glass Window Vendor in hand.

  • Lexan Slumping Oven completed.

  • Oven Temperature Controller Completed.

  • Mirror slumping prototype tests completed.

  • Slumping of MICE prototypes to begin.

  • Fermilab Mirror coating schedule needs work. Eileen Hahn.

  • CKOV detectors ~600lb (270Kilo) ea

  • Fedex OxfordMississippi-OxfordUK ~$1000/500lb

CKOV Progress Report, L. Cremaldi, 5-4-07


Ckov progress 5 4 07

Back cover

Steele frame(down)

Steele sides

Steele frame(up)

front cover

front mirrors

side mirrors

aerogel

Schott glass window

CKOV Exploded View

window frame

CKOV Progress Report, L. Cremaldi, 5-4-07


Ckov progress 5 4 07

CKOV to Solid Works Translation- Checking

  • M. Reep has converted all drawings to Solid Works and has performed

  • dimensional checks.

CKOV Progress Report, L. Cremaldi, 5-4-07


Ckov progress 5 4 07

Aerogel Compartment

  • Delrin in hand

  • Matsushita will slice 6 corner panels  at 45deg.

  • Machining to begin soon.

CKOV Progress Report, L. Cremaldi, 5-4-07


Ckov progress 5 4 07

Base Layout V1 - Sten Hansen - FNAL

Sten has made first layout and we will begin prototype. Sockets

on order.

CKOV Progress Report, L. Cremaldi, 5-4-07


Ckov progress 5 4 07

CKOV Progress Report, L. Cremaldi, 5-4-07

FiberGlass Oven Enclosure

  • Simple Fiberglass enclosure with heating elements- D. Summers design.

  • Lexan Slumping temperature ~ 150C

  • Temperature controller regulates to +-2 degC.

  • Preliminary testing finished and bending of MICE prototypes to begin.

  • Mirroring at FNAL ASAP.

CKOV Progress Report, L. Cremaldi, 5-4-07


Ckov progress 5 4 07

Commissioning Plan

  • Plan-A

  • - Mechanical parts to Mississippi ( June).

  • Practice Assembly + Light Leak Checking.

  • Begin shipping to RAL >July 4)

  • Cremaldi+Sanders to RAL July 15 - Aug 1.

  • Aerogel Assembly week-1

  • Mechanical Assembly and Install week-2

  • Plan-B

  • - Mechanical parts to FNAL ( June).

  • Practice Assembly + Light Leak Checking.

  • Begin shipping to RAL >July 4)

  • Cremaldi+Sanders to RAL July 15 - Aug 1.

  • Aerogel Assembly week-1

  • Mechanical Assembly and Install week-2

CKOV Progress Report, L. Cremaldi, 5-4-07


  • Login