1 / 16

PRESENTATION TO THE STANDING COMMITTEE ON APPROPRIATION

PRESENTATION TO THE STANDING COMMITTEE ON APPROPRIATION. EXPENDITURE REPORT AS AT THE END OF 3 RD QUARTER (31 DECEMBER 2011). OVERVIEW OF THE PRESENTATION. 1. Introduction 2. Departmental Expenditure Analysis per Programme 3. Departmental Expenditure per Economic Classification

dragoo
Download Presentation

PRESENTATION TO THE STANDING COMMITTEE ON APPROPRIATION

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PRESENTATION TO THE STANDING COMMITTEE ON APPROPRIATION EXPENDITURE REPORT AS AT THE END OF 3RD QUARTER (31 DECEMBER 2011)

  2. OVERVIEW OF THE PRESENTATION 1. Introduction 2. Departmental Expenditure Analysis per Programme 3. Departmental Expenditure per Economic Classification 4. Analysis of the under expenditure for 2011/12 Financial Year per economic classification 5. Measures to improve expenditure 6. Conclusion

  3. 1. INTRODUCTION The purpose of the presentation is to brief Standing Committee on Appropriations on the Departmental Financial Expenditure including measures put in-place to improve expenditure trends.

  4. 2. Departmental Expenditure Analysis per Programme

  5. 3. Departmental per Economic Classification

  6. 4. ANALYSIS OF THE UNDER EXPENDITURE 4.1. Overall Expenditure: • The departmental overall expenditure performance depicted 65.5% spending and a standard norm is projected at 75% which reflects 10% under spending. This is largely due to transfers to municipalities that are not transferred every month, but according to payment schedules which the norm is not applicable. • Therefore, according to our projected cash flow, transfers are in line with the payment schedule at 65.6% while Disaster Relief is at 0% due to outstanding assessments reports.

  7. 4.2 Compensation of employees: • Allocation: R248 809 • Actual expenditure R173 598 • Variance R75 211 • % Spent 69.7% • The department was able to spend 69.7% of its budget allocation as at the end of the 3rd quarter, the under expenditure was due to vacant posts that were filled late in the year such as posts within NDMC, MISA and CWP.

  8. 4.3. Goods and services: • Allocation: R478 605 • Actual expenditure R275 278 • Variance R203 327 • % Spent 57.5% Our spending on goods & services reflects 17.5% under-spending. The under-spending is due to projects that were either withheld or deferred to the next financial year. During the Adjusted Estimates of National Expenditure (AENE) funds to the value of R17 million were set aside to implement the establishment of cooperatives through SANACO. The process to renew the contract was only adjudicated in February 2012

  9. 4.4 Payments of Capital Assets: • Allocation: R19 779 • Actual expenditure R 4 563 • Variance R15 216 • % Spent 23.1% The department spending reflects an under spending of 51.9%. This is due to R5.6 million within CWP that is not spent due to the implementing agents being appointed late in the financial year, where the older ones did not want to invest in capital towards the end of their term. The other allocation is on office furniture and office equipment not procured or delayed as the department is busy trying to acquire office accommodation for TSU.

  10. 4.5. Transfers and subsidies: The following Transfers have been paid according to the payment schedule after the institutions have fulfilled all the conditions and requirements for the transfers: • Municipal Infrastructure Grant 62.7% • Municipal Improvement System Grant 93.4% • South African LG Association 75.0% • Municipal Demarcation Board 75.1% • CRL Commission 75.1% • South African Cities Network 66.7% • Community Works Program The program is currently at 69.7% spending; The program is divided into two categories: 10% on Program management (R65.3 mil) and 90% (R588.1 mil) site costs, but the 10% on Program management was reduced to R15.6 million to increase an allocation on site costs to R637.8 mil. The under spending is due to late receipt of invoices from service providers.

  11. Transfers and subsidies continue: The following Transfers are indicating symptoms of under spending: • LG Equitable Share = 68.4% The LG Equitable Share currently reflects an under-spending of 68.4% whereby National Treasury has indicated an intention to withhold R949 million for non performance of municipalities on other conditional grants in the previous financial years. • Councillor once-off Gratuity = 0% The process of gazetting, verification of councillors, Tax directive etc took too long to complete. The process was intensified during the 4th quarter of the financial year and there is tangible progress registered • United Cities of LG in Africa = 8.9% Transfers to UCLGA have been suspended pending discussions between the department and the entity on how to disburse this allocation in future.

  12. Transfers and subsidies continue: The following Transfers also indicates symptoms of under spending : • Municipal Infrastructure Support Agency = 54.7% The Department signed a contract with Development Bank of Southern Africa (DBSA). The contract entails that most of the procurement processes would be done by DBSA. And the department is invoiced after work is completed. The late billing by DBSA is the reason for the under spending. • Municipal Disaster Relief = 0% The NDMC has over the period played an active part in assisting the Provinces to process their applications to ensure that the immediate relief funding is processed within the shortest possible period.This is due to assessments processes that took too long to complete. The department and the National Treasury are currently working on best way that can make funds distributed speedily and appropriately in the current financial year.

  13. 5. MEASURES TO IMPROVE EXPENDITURE • Budget Committee: The Budget Committee will serve as an advisory committee to management in reference to their respective responsibilities for the preparation, adoption, administration and monitoring of the budget. The budget committee will mainly be concerned with the overall financial planning and management issues including assessment of the way the department will be operating and a focused attention on performance against budget and service delivery plans.

  14. MEASURES TO IMPROVE EXPENDITURE cont • Project management approach: The project management approach has been enforced at the level of the budget process thereby linking the budget to performance management. All approved projects have been allocated budgets linked to the various milestones. This will ensure that expenditure movement is in accordance with the projections. • Approved procurement plan: A procurement plan has been developed linked to the project management model, the timeframes for projects are synchronised with the procurement requirements to ensure that the service providers are in place when required. The approval of the procurement plan early in the financial year will ensure timeously procurement as well as consistent monitoring at executive management level. • Forward Planning Concept: The department has committed itself to this concept for all its operations and procurement processes.

  15. 6. CONCLUSION 1. Improvement plans were implemented with success. 2. Interim expenditure as at 31st March 2012 stood as follows (R2 billion under expenditure, R1,947 billion of which is transfers and subsidies) 2.1 Transfers and Subsidies - 97% 2.2 Compensation of employees-96% 2.3 Good and Services – 91% 2.4 Capex – 42%

  16. THANK YOU

More Related