Mandatory Prepaving Conference. Chipseal Construction. Section 37.2 Seal Coats . Keys to Success. Proper surface preparation Use of right asphalt binder, asphaltic/polymer modified emulsion and clean aggregate screenings

Download Presentation

Mandatory Prepaving Conference

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Mandatory prepaving conference

MandatoryPrepaving Conference

Chipseal Construction

Section 37.2 Seal Coats


Keys to success

Keys to Success

  • Proper surface preparation

  • Use of right asphalt binder, asphaltic/polymer modified emulsion and clean aggregate screenings

  • Adherence to the project specifications, including traffic control

  • Check equipment before start

  • Chip seal in good weather conditions


Mandatory prepaving conference

Topics to be covered

  • Materials

  • Equipment

  • Construction Procedures

  • Quality Control

  • Quality Assurance

Section 37-2.01A Summary


Mandatory prepaving conference

MATERIALS

  • Asphalt Binder, Asphaltic Emulsion, Polymer Modified Emulsion (PME)

  • Screened Aggregates

Section 37-2.01A Summary


Mandatory prepaving conference

Equipment

  • Distributor Trucks

  • Screened Aggregate Spreaders

  • Self Propelled Screened Aggregate Spreader

  • Self Propelled Power Brooms & Vacuums

  • Pneumatic Tired Rollers

    • Width ≥ 4’

    • Weight ≥ 3000 lbs. per Wheel

Section 37-2.03 Equipment


Mandatory prepaving conference

  • ConstructionProcedures

  • Proper Surface Preparation

  • Apply Binder/Asphaltic Emulsion/Polymer Modified Emulsion at Specified Rates & Temperatures

  • Apply Screened Aggregates at Specified Rates

  • Roll-as Specified Number of Coverages

  • Allow Mat to Cure or Cool

  • Broom Loose Aggregate

  • Apply a Flush Coat

  • Open to Traffic After Curing Flush Coat.


Mandatory prepaving conference

Sweeping (before and after)

Hot Binder Application

Rolling

AggregateApplication


Mandatory prepaving conference

Construction-Surface Preparation-Existing Pavement

Section 37-2.03D Surface Preparation


Mandatory prepaving conference

Construction-Surface Preparation-Existing Pavement

  • Cover all exposed facilities before seal coat application.

  • Reference all covered facilities properly for easy location.

  • After seal coat application, expose the covered facilities.

Section 37-2.03D Surface Preparation


Mandatory prepaving conference

Construction-Surface Preparation-Existing Pavement

  • Remove all loose and extraneous material by brooming and vacuuming.

  • Ensure clean, dry surface before applying seal coat.

Section 37-2.03D Surface Preparation


Mandatory prepaving conference

Construction –Applying asphaltic Emulsion

Section 37-2.03F


Mandatory prepaving conference

Construction –Applying asphaltic Emulsion

  • In confined areas apply the emulsion with a squeegee, rake or other means authorized by the Engineer.

  • Cover adjacent areas not intended for sealing with suitable material.

  • At longitudinal joints, emulsion overlap must be dispersed with squeegees before the application of screenings or rakes.

Section 37-2.03F Applying Emulsion


Mandatory prepaving conference

Construction –Applying asphaltic Emulsion

  • Align longitudinal seal coat joints with designated traffic lanes. Ensure adequate overlap (4”-8”), as directed by engineer.

  • Plan emulsion application with lane closure requirements, stop an hour before darkness.

Section 37-2.03F Applying Emulsion


Mandatory prepaving conference

Construction-EMULSION/BINDER

Application

Section 37-2.03F(3) &(4)


Mandatory prepaving conference

h

Construction – TYPES of

EMULSION Overlap

Single Overlap

Double Overlap

Triple Overlap

Roadway Surface

Section 37-2.03F(3) &(4)


Mandatory prepaving conference

Construction – EMULSION Application


Mandatory prepaving conference

APHALTIC EMULSION

APPLICATION RATES

  • Asphaltic Emulsion or Polymer Modified Asphaltic Emulsion Application (Residual) Rates

Section 37-2.03F(3) &(4)


Mandatory prepaving conference

APHALT BINDER APPLICATION RATES

  • Asphalt (Paint)Binder Application Rates


Mandatory prepaving conference

Construction – SCREENED Aggregate Application

Section 37-2.03G (1), (2) &(3)


Mandatory prepaving conference

Construction – SCREENED Aggregate Application

Section 37-2.03G (1)(2) &(3)


Mandatory prepaving conference

Screened Aggregates

SPREAD RATES

Section 37-2.03G (1), (2) &(3)


Mandatory prepaving conference

  • Construction – SCREENED Aggregate Application

  • No Traffic on emulsioned areas

  • Uniform spread rates per specifications over entire lane width

  • Broom Excess screenings.

  • Aggregate screenings no roll after dropping.

  • Aggregate screenings should stop when the spreader stops

  • Do not spread aggregate screenings ≥ 2500’ ahead of completed initial rolling

Section 37-2.03G (1) & (3)


Mandatory prepaving conference

  • Construction – SCREENED Aggregate Application –BEST PRACTICES

  • The application always starts with neat straight edges.

  • The aggregate spreader follows closely behind the distributor truck (50ft.)

  • Screened aggregates for Polymer Modified Asphaltic Emulsion application are in a damp condition.

  • The application looks uniform.

  • Enough trucks are on hand to keep steady supply of chips.

  • Check for streaks and gate plug.

  • Screened aggregate sample is secured from the middle of stockpile or chip machine belt for testing.


Mandatory prepaving conference

Construction - Rolling

Section 37-2.03H(1)


Mandatory prepaving conference

Construction- Rolling

Section 37-2.03H(1)


Mandatory prepaving conference

Construction - Rolling

  • Correct all ridges, piles, bumps or depressions.

  • Ensure straight joints, no more than 4” overlap

  • Longitudinal joints at lane lines

  • Use pneumatic rollers

  • Initial rolling with pneumatic roller one coverage

  • Three coverages of pneumatic roller for final rolling

  • Broom excess aggregate screenings before opening to traffic

Section 37-2.03H(1)


Mandatory prepaving conference

Construction - Curing of Emulsion

  • Curing time depends on ambient temperature and relative humidity

  • Emulsion break should begin just after first roller pass

  • Emulsion curing might take 2 to6 hours, depending upon asphaltic emulsion type & base asphalt


Mandatory prepaving conference

Construction - Brooming Loose Aggregate

Section 37-2.03I Seal Coat Maintenance


Seal coat maintenance

Seal coat maintenance

  • Seal coat surfaces must be maintained for 4 consecutive days from the day screened aggregates are applied.

  • Remove excess screened aggregates from surface by brooming. Exact brooming time & intervals determined by engineer

  • Use pilot cars to control traffic.

  • Schedule placement to ensure end of 1 way traffic control an hour before darkness.

Section 37-2.0I Seal Coat Maintenance


Mandatory prepaving conference

QualityCONTROL-CONTRACTOR

  • Polymer Modified Emulsions

    • Viscosity (AASHTO T59)

    • Sieve Test (AASHTO T59)

    • Demulsibility (AASHTO T59)

    • Torsional Recovery (California Test 332)

Section 37-2.0ID (3)


Mandatory prepaving conference

Quality CONTROL-CONTRACTOR

  • Screened Aggregates

    • CT 211, Loss at 100 revolutions ≤ 10%

    • Loss at 500 revolutions ≤ 40%

    • CT 302, Film Stripping ≤ 25%

    • C T 227 Cleanliness Value ≥ 80 for Asphaltic Emulsions

    • C T 227 Cleanliness Value ≥ 86 for PMEs

Section 37-2.0ID (3)


Mandatory prepaving conference

Quality CONTROL-CONTRACTOR

  • Screened Aggregates- CT 202 Gradation-Asphaltic Emulsion

Section 37-2.02H (2)


Mandatory prepaving conference

Quality CONTROL-CONTRACTOR

  • Screened Aggregates- CT 202 Gradation-Polymer Modified Emulsion

Section 37-2.02H (3)


Mandatory prepaving conference

Quality CONTROL - Preliminary Responsibilities

  • Projectreview-Contractor

    • Alignment, geometrics, shoulders, turnouts

  • Document review-Joint

    • Plans & Specifications

  • Equipment & Material checks-Contractor


Mandatory prepaving conference

Quality Control Pre-Application Inspection (cont.)

  • Weather requirements

  • Check the local weather conditions for the proposed paving day.

  • Ensure that the proposed paving operation can be completed, including the emulsion cure within the favorable weather window.

  • Reschedule paving operations if rain is predicted within the next 48 hours.

Section 37-2.03C Unsuitable Day


Mandatory prepaving conference

Quality Control

Pre-Application Inspection

  • Surface preparation

  • Equipment inspection

    • Asphaltic emulsion distributor

    • Chip spreader

    • Haul trucks

    • Rollers- Adequate number of pneumatic rollers

    • Brooms

Section 37-2.01(D) Quality Control


Mandatory prepaving conference

Quality Control Pre-Application Inspection (cont.)

  • Determining asphaltic emulsion & screened aggregate application rates

  • Traffic control plan and setup

Section 37-2.03F(3) & (4) Application Rates


Mandatory prepaving conference

Quality ASSURANCE - construction Inspection

  • Asphaltic emulsion application & rates

    • California Test 339

  • Screened aggregate application & rates

    • Vialit (French)Test ≥ 90% Retention

  • Traffic control & trucking operation

  • Rolling


Mandatory prepaving conference

Quality ASSURANCE - construction Inspection

  • Longitudinal joints – ensure no aggregate buildup

  • Transverse joints – ensure clean joints, start and stop on construction paper

  • Brooming to ensure absence of loose aggregate


Mandatory prepaving conference

Quality Control /ASSURANCE

Post-Application Inspection

  • Cleanup

  • Opening to traffic