Level 1 muon trigger status and commissioning
Download
1 / 6

Level 1 Muon Trigger Status and Commissioning - PowerPoint PPT Presentation


  • 99 Views
  • Uploaded on

Level 1 Muon Trigger Status and Commissioning. Rob McCroskey University of Arizona for the L1 Muon Group. L1MU Hardware. MTCM (Crate Manager) Production card testing in progress MTCxx (Trigger Card) Production cards beginning fabrication MTFB (Flavor Boards)

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Level 1 Muon Trigger Status and Commissioning' - dillon


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Level 1 muon trigger status and commissioning

Level 1 Muon Trigger Status and Commissioning

Rob McCroskey

University of Arizona

for the

L1 Muon Group


L1mu hardware
L1MU Hardware

  • MTCM (Crate Manager)

    • Production card testing in progress

  • MTCxx (Trigger Card)

    • Production cards beginning fabrication

  • MTFB (Flavor Boards)

    • Production MTM boards ready for fabrication

    • Production MTC10 board design in progress (finish in couple weeks)

    • Preproduction MTC05 board in fabrication

  • SLDB’s (Gbit/s Serial Links)

    • Production board testing in progress


Mcen hardware
MCEN Hardware

  • MCCM (Crate Manager)

    • Preproduction card layout in progress

  • MCEN (Centroid Finder Card)

    • Preproduction card testing in progress

  • MCPB (Physics Boards)

    • Preproduction board testing in progress


L1mu infrastructure
L1MU Infrastructure

  • Custom VME backplanes

    • Complete

  • Power supplies

    • Prototype assembled and tested

    • VICOR supplies ordered but with 20-22 week lead time

  • Platform services

    • On hold pending final cable plant design

  • Cabling

    • Production at Fermilab and NIU in progress


Near term commissioning goals
Near Term Commissioning Goals

  • mid-August

    • Stable operation of one (sparse) L1MU trigger crate and the L1MU MTM crate

      • Still using preproduction cards

  • early October

    • Add L1CFT MTM crate to the above

  • mid-October

    • Begin commissioning production L1MU crates and cards

Done

Underway

Underway

Aiming for stable L1MU operation for

commissioning by mid to late October


Longer term commissioning goals
Longer Term Commissioning Goals

  • Begin full crate testing in late December or early January

    • Two octant triggering until then

    • MCEN cards ~ 2 months behind above

    • Temporary power supplies for full crate tests