Production EVM Working Group Outbrief August 2010 PMSC. Production EVM Working Group Charter. Charter Analyze EVM practices and processes on production contracts and provide a common understanding of terminology, processes and earned value application used in a production environment.

Download Presentation

Production EVM Working Group Outbrief August 2010 PMSC

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Production evm working group outbrief august 2010 pmsc

Production EVMWorking Group OutbriefAugust 2010 PMSC


Production evm working group charter

Production EVM Working Group Charter

Charter

Analyze EVM practices and processes on production contracts and provide a common understanding of terminology, processes and earned value application used in a production environment

Planned Output

  • Documenting production EVM issues, typical company practices, difference in production process versus typical development program process (and/or outputs), and perceived expectations of production EVM process

  • Consolidate individual issue documentation into a white paper summarizing production EVM issues


Major effort accomplished review from prior pmsc

Major Effort Accomplished – Review From Prior PMSC

  • Defined terms to ensure common understanding

  • Identified approximately 120 various issues encountered when executing and/or reviewing production contracts with EVM

    • Grouped like items and will address similar items together

  • Formed 11 sub groups to take lead in documenting identified issues:

    1. Change Management7. Part Movement

    2. EVM Application in Production8. Scheduling

    3. Level of WBS/Detail9. Scrap/Rework

    4. Material10. Support Labor

    5. Manufacturing Labor11. Work Authorization

    6. Organization

3


Activities since last pmsc

Sub groups have begun writing draft documents with drafts sent to WG members

10 drafts to date have been completed and circulated

Anticipate around 30 to 40 total documents to discuss all issues identified

Just identified a sub group leader for Scrap/Rework topic (all areas now have a sub group leader)

Activities Since Last PMSC


Work in progress

Work In Progress

  • Sub group documentation continues

  • Summary/main body of white paper will start soon

  • Goal is to complete all drafts by end of year

  • Plan will be to incorporate WG member comments and update in 1st Qtr 2011 (on going process completing in then)

  • Target final product in mid-2011 to be made available to PMSC membership for final review and comment

5


Challenges help needed

Challenges/Help Needed

  • Lots of writing effort from scratch, require lots of time and resources to accomplish

  • Working group members have had numerous conflicts to deal with

  • Not all sub groups are adequately staffed

  • More participation from existing WG members or new members is needed

  • A period of significant edits will have to be accomplished to incorporate all industry and government perspectives