An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CF Organization & Schedule Status Scope CF Organization FY 05 CF Organization FY 06 Construction Schedule

  2. Status • Sector 20 – Title III to commence June 1, 2005 • MMF – Title III to commence June 15, 2005 • Title II – (RSY-CLOC) is underway • Geotechnical Baseline Report award is imminent • Environmental analysis of site characterization • CMGC to award June 2005

  3. CF Organization FY 05

  4. CF Organization FY 06-08

  5. SLAC Site Plan SLAC Main Gate Pep Ring Road Bldg #081 - MMF Sector 25 Sector 20 Upstream LCLS General Work Boundary Research Yard

  6. Below Grade Plan Beam Transport Hall Near Hall Undulator Hall XRTDT Far Hall

  7. New Facilities (below grade)

  8. LCLS Site Plan Spear Future Office Space Pep Ring Road SLC Office Complex Undulator Hall Research Yard Survey Tower NEH Beam Transport Hall SLC Tunnel Beam Dump Front End Enclosure Future Beam Lines X-Ray Transport Pep Tunnel

  9. CLOC Floor Plans CLOC Exterior Elevations • Headcount of CLOC Personnel = 284 • Capacity of Conf Center = 150 • Gross square footage of CLOC (offices and labs) = 68,800sf

  10. CLOC Exterior Elevations

  11. CLOC Exterior Elevations

  12. LCLS CF Construction Schedule • Added additional time for CM/GC procurement phase • DOE approval for CM/GC SOW – (in progress – request return date April 20, 2005) • Major construction phase FY 06 at 30 months duration • Beneficial Occupancy dates are key to technical system interfaces • Site-work at NEH is key!