ISE 6 Phase 2 Demo Scenario. Nov 20, 2008. Stakeholders. ISEA NSWC PHD (Combat Systems) NSWCCD SSES (HM&E) Program Offices PMS 500, etc. IWS 1 (Combat Systems) IWS 2 (Above Water Sensors) PEO Ships Policy Makers NAVSEA 04L OPNAV N40 Shipyards (Acquisition and Planning Yard).

Download Presentation

ISE 6 Phase 2 Demo Scenario

An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -

Presentation Transcript


Ise 6 phase 2 demo scenario

ISE 6 Phase 2 Demo Scenario

Nov 20, 2008


Stakeholders

Stakeholders

  • ISEA

    • NSWC PHD (Combat Systems)

    • NSWCCD SSES (HM&E)

  • Program Offices

    • PMS 500, etc.

    • IWS 1 (Combat Systems)

    • IWS 2 (Above Water Sensors)

    • PEO Ships

  • Policy Makers

    • NAVSEA 04L

    • OPNAV N40

  • Shipyards (Acquisition and Planning Yard)


Invitation list

Invitation List

  • Jim Colson (Army LOGSA)

  • 04L - Bernie Coval, Tim Kriegal, Bucky Buchanan

  • ISW1 – Jolene Marshall, CAPT Mall

  • ISW2 – Noel Smith,

  • PMS 500 – Cheryl Smorto,

    • Claude Barrens (CGX ship design manager)

  • NAVSSES – Joe Picossi

  • PHD – Troy Sutton, Fabio Vitale, CAPT Ruehlin

  • PEO Ships

  • PEO Subs

  • PEO Carriers


Demo date

Demo Date

  • Phillys in DC April 13-16

  • Easter is April 12


Process improvements

Process Improvements

  • Exchange of integrated design and logistics product data

    • Between Design and Logistics

    • Between ISEA, NAVSEA 05, Shipyards, and OEMs

    • Throughout full life cycle (currently only in acquisition)

  • Standardized data exchange formats

    • Neutral format IDE data

    • Improved quality and reduced cost through standardized schema and automated validation/exchange

    • Enable data reuse

  • Automated identification of change impacts

    • Reduce costs to evaluate changes

    • Support cost benefit analysis, design trade studies, etc.

    • Impact of design or logistics changes

  • Enables Virtual Navy Enterprise


As is scenario

As-is Scenario

Program

Office

Authorization,

Funding

OEM

(RSC)

Authorization,

Funding

LSAR

Collaboration

Develop

ECR

Revised

Radar

Shipyard

/ NAVSSES

Revised

HM&E Data

Update

Design and

Logistics

Revised

Radar Data

Update

Design and

Logistics

ISEA

(PHD)

LSAR

Identify

Changes

Program IDE

Changes

Mod 2

Radar

NDE-FMP

NAVICPWSF

Navy S1000D

Database (Content@)

LEAPS

CDMD OA

TDMIS


Demo scenario

Demo Scenario

Program

Office(s)

Authorization,

Funding

OEM

(RSC)

Authorization,

Funding

LSAR

Collaboration

Develop

ECR

Revised

Radar

AP 239

+ S1000D

Update Design

and Logistics

Shipyard

/ NAVSSES

Revised

HM&E Data

ISEA

(PHD)

Revised

Radar Data

Update

Design and

Logistics

AP 239

+ S1000D

AP 239

+ S1000D

LSAR

Program IDE

Identify

Changes

Changes

PLCS

AP 239

+ S1000D

AP 239

+ S1000D

NDE-FMP

NAVICPWSF

Navy S1000D

Database (Content@)

LEAPS

CDMD OA

TDMIS


Demo scenario by system

Demo Scenario by System

Need to add

S1000D repository

From OEM and Shipyard

Program

Office(s)

Authorization,

Funding

OEM

(SIR)

S1000D

modules

Authorization,

Funding

LSAR

Collaboration

Develop

ECR

AP 239

+ S1000D

Revised

Radar

Update Design

and Logistics

Shipyard

/ NAVSSES

Revised

HM&E Data

ISEA

(episTree)

Revised

Radar Data

Update

Design and

Logistics

AP 239

+ S1000D

AP 239

+ S1000D

LSAR

Program IDE

(Teamcenter)

Identify

Changes

Changes

PLCS

AP 239

+ S1000D

AP 239

+ S1000D

NAVICPWSF

LEAPS

Navy S1000D

Database (Content@)

CDMD OA

TDMIS

NDE-FMP


In service ship alt

In-service Ship Alt

  • PEO authorization

  • SHIPMAIN coordinates development of Alt

    • ISEA develops Alt for radar system

      • ISEA submits ECR to OEM

      • Update design (drawings)

      • Update logistics (ILS)

    • Planning yard / NAVSSES develop Alt for HM&E

      • Update design (drawings)

      • Update logistics (ILS)


Current issues

Current Issues

  • Investigate LOGSA LSAR DEX – Tim, Ted, Mike


Clarifciations

Clarifciations

  • Separate Ship Constructor demo

    • Maybe ShipTech

    • Different audiuence – 2nd tier yards


Demo data

Demo Data

  • Content@ DB

    • John Crehan to work with Bernie

    • End of Jan – link from RSC is operational to deliver modules

      • Fall back plan – manually add to Content@

  • Dual Band Radar

    • Receiver Exciter (REX) Spy 3

      • 30 data modules

      • Functional description, Removal, Procedure, graphics

    • John Crehan provide metadata by Dec 5

    • Matt P. – acquire LCB data, including HSC numbers


Demo data1

Demo Data

  • HM&E system

    • Use AC system (514)

    • Use AC Plant #1 (51421)

    • Change the motor (514212122) and compressor (514212121)

    • Mike talk to Harold Roll about S1000 DM for AC plant

    • Ben – find additional VFI tech data for motor and compressor

      • Tim – find out who has S1000D data for LPD 17 motors

    • Populate data sheet

    • CAD model for equipment

      • Could export from CATIA

      • Need GUIDS for LEAPS

      • Mike – Provide STEP files for distributed systems


Previous demo planning slides

Previous Demo Planning Slides


Ise 6 phase 2 demo scenario1

ISE 6 Phase 2 Demo Scenario

  • Initial Data Exchange and Load

    • Export selected HVAC system from LPD IDE as PLCS data with links to S1000D data modules

    • Export selected Dual Band Radar (DBR) system from NSWC PHD/Raytheon (System TBD) as PLCS data with links to S1000D data modules

    • PLCS data modified to allow import into DDG 1000 IDE

    • PLCS data imported into DDG 1000 IDE

    • S1000D data and publication modules for HVAC and DBR delivered to Navy Common Source Data Base (CSDB)

  • Change Management

    • New Mod of Dual Band Radar is developed and authorized for use

    • New radar cabinets generate more heat, require additional cooling in the space

    • New cooling requirements passed to Shipyard Engineering

    • HVAC system is redesigned

    • Affected S1000D data modules for HVAC and DBR system Technical Manuals are updated

    • HVAC and DBR system Technical Manuals updated

    • Updated design passed to LEAPS


Plcs s1000d functional scenario

PLCS & S1000D: Functional Scenario

Shipyard A IDE

(Design, Logistics, Support)

Navy IDE

(Design & Analysis)

Data Prep & QA

(Design, Logistics, & CAD)

Shipyard B Design

(3D CAD Data)

Navy ISEA

(GFE Change)

Shipyard B IDE

(Update Tech Pub)


Plcs s1000d exchange scenario

Shipyard A IDE

Navy IDE

LEAPS

Navy Design & Analysis

episTree

Repository

Shipyard B IDE

AIM/SIR

LPD 17 IPDE Software

NAVSEA / Navy ISEA

CAD Tool

PLCS & S1000D: Exchange Scenario

AP 239

+ S1000D

S1000D

Modules

Knowledge Management

AP 239

+ S1000D

Software

AP 214

HVAC

3D Design

NAVSEA / NSWCCD

Teamcenter

Common Source DB

DDG 1000 IDE Software

Candidate Data Module Updates

Content@

Ship Alt

Changes

S1000D

Modules

AP 239

+ S1000D

Design Shipyard

TBD System

New Support

Requirements


Plcs s1000d data scenario

HVAC Sys

DM 1.1

HVAC Sys

TM 2

HVAC Ducts

HVAC Sys

Drawing1

HVAC Sys

TM 1

DM 1.2

HVAC Sys

Drawing2

DM 2.2

Chillers

Duct 2

DM 1.1

Mod 1

Radar

TM

DM 1.3

Chiller 1

Mod 1

DM 1.2

DM 2.3

Chiller 2

DM 1.3

Mod 2

Mod 2

Radar

TM

DM 2.1

DM 2.2

PLCS & S1000D: Data Scenario

Shipyard Design & IDE

ISEA IDE (Radar)

Duct 1

Updated

Requirements


Demo data2

Demo Data

  • HVAC and DBR system PLCS data

    • Similar to last year’s demo

    • Equipment – chiller?

    • AP 227 implications

  • HVAC and DBR system Tech Manual / Data Modules

    • Need to define minimal TM content, divide into DM

    • Define DMC structure

    • Define necessary metadata


Backup

Backup


Ise 6 phase 2 demo scenario

AP239/PLCS (ISE-6 Phase 1) Demo Scenario

LEAPS

Navy Design & Analysis

Repository

AP 214

AP 239

Shipyard A

-

IDE

AP 239

AIM/SIR

LPD 17 IPDE Software

Navy IDE

Design

ShipConstructor

2008

AP 227

CATIA

ShipConstructor

AP 227

(V4 AEC)

2006

3D Design

Design & Logistics

episTree

Knowledge Management

Software

Shipyard B

-

IDE

AP 239

Design & Logistics

AP 214

Teamcenter

Design & Logistics,

including 3D Design

DDG 1000 IDE Software


Plcs s1000d functional scenario1

PLCS & S1000D: Functional Scenario

Navy ISEA

(GFE Change)

Navy IDE

(Design & Analysis)

Shipyard A Design

(3D CAD Data)

Shipyard A IDE

(Update Tech Pub)

Data Prep & QA

(Design, Logistics, & CAD)

Navy Depot

(Design, Logistics, Support)