Mod 0130 the provision of ex post demand information for nts offtakes
Download
1 / 5

Mod 0130 – ‘The Provision of Ex-Post Demand Information for NTS Offtakes’ - PowerPoint PPT Presentation


  • 88 Views
  • Uploaded on

Mod 0130 – ‘The Provision of Ex-Post Demand Information for NTS Offtakes’. Richard Fairholme E.ON UK. Modification Proposal 0130 - Overview. Based on Mod 0121, with two key differences: Aggregates data into market ‘sectors’ (as per Mod 0121 Annex): (i) Aggregated ex-post LDZ offtake flows;

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about ' Mod 0130 – ‘The Provision of Ex-Post Demand Information for NTS Offtakes’' - dasha


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
Mod 0130 the provision of ex post demand information for nts offtakes

Mod 0130 – ‘The Provision of Ex-Post Demand Information for NTS Offtakes’

Richard Fairholme

E.ON UK


Modification proposal 0130 overview
Modification Proposal 0130 - Overview for NTS Offtakes’

  • Based on Mod 0121, with two key differences:

  • Aggregates data into market ‘sectors’ (as per Mod 0121 Annex):

  • (i) Aggregated ex-post LDZ offtake flows;

  • (ii) Aggregated ex-post power station offtake flows;

  • (iii) Aggregated ex-post storage offtake flows;

  • (iv) Aggregated ex-post industrial load offtake flows.

  • 2. Publication of data on National Grid’s website, by 11:00am for the previous Gas Flow Day.


Why aggregate the data
Why Aggregate the Data? for NTS Offtakes’

  • Response to our I&C customer’s concerns

  • Risk of undue discrimination between offtakes:

  • Under Mod 0121, similar-sized industrial loads which are DN connects will not have their daily gas demand data published.

  • Many NTS connected industrial load customers operate in commodity-based markets.

  • Gas demand data illustrates when a customer is producing.

  • Production data gives market intelligence and may influence market pricing and behaviour.

  • Aggregation of data gives sufficient transparency without unfairly revealing the trading position of customers.


Why publication by 11 00am
Why Publication by 11:00am? for NTS Offtakes’

  • Consistent with Mod 0097/0097a – ‘Modification to release aggregated ex-post information for pipeline interconnector offtake flows’.

  • To be published in the same place as interconnector offtake flows – under ‘Operational Data’ section of website.


Next steps
Next Steps… for NTS Offtakes’

  • Encourage Mod Panel to approve a ‘fast-track’ consultation process for Mod 0130.

  • Aim is for Ofgem to be able to make a decision on Mods 0121 and 0130 at the same time.