1 / 16

ALMA Integrated Computing Team Coordination & Planning Meeting #2 Santiago, 28-29 January 2014

Control Group Planning Rafael Hiriart, Control Group Lead. ALMA Integrated Computing Team Coordination & Planning Meeting #2 Santiago, 28-29 January 2014. Status since ICT-CPM1(Apr 2013).

darcie
Download Presentation

ALMA Integrated Computing Team Coordination & Planning Meeting #2 Santiago, 28-29 January 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Control Group Planning Rafael Hiriart, Control Group Lead ALMA Integrated Computing TeamCoordination & Planning Meeting #2 Santiago, 28-29 January 2014

  2. Status since ICT-CPM1(Apr 2013) • 2 open positions filled (Rachel & Patrick), one remaining open. CONTROL/OBOPS position now under NRAO's Web App Group. Alexis hired by NRAO SW test group. • 3 releases delivered (10.2, 10.4, 10.6), which included • Correlator support for more than 16 calibrations. • TMCDB versioning improvements (CLI interface to retrieve history). • Address DataCapturer memory issues with Pointing table. • Fast scanning (delivered with Ralph's mission to the OSF). • Full correlator data rates (Rodrigo's mission to the OSF). • DataCapturer relational database. • First version of the phasing loop (Matias' mission to the OSF). • New Quicklook GUI. • ASDM Ephemeris table.

  3. Cumulative New Features

  4. Cumulative Bugs

  5. Status (2), about testing • New NRAO testing group was formed, covering ALMA and CASA testing (i.e., this group will cover both ALMA data production and validation). • Socorro and Charlottesville STEs now have same configuration than OSF. They are also synchronizing with the same build. Problems can be more easily reproduced. • Simulation improvements allow us to test more, more easily. Simulation tests running daily in Socorro. • We are working with IRM on the automatization of tests, and the inclusion of CSV test SBs and scripts. This should help freeing ADC resouces, which can then help us on getting more bugs fixed.

  6. Risks & Issues • Since April 2013, 237 bug tickets have been submitted, we have resolved 105 and 20 are in progress. Delta = 112. • More tickets have been submitted that we have been able to handle. What to do about it? • We haven't reached a stable point in the project lifecycle. Rate of tickets should decrease at some point. • New hires (Patrick & Rachel) are coming up to speed. When APP ramps down, Matias can also help. • Implement code reviews with ADC. Improve their knowledge of some areas of the Control SW.

  7. Risks & Issues (2) • Avoid introducing more bugs with new features. Implement internal code reviews. • A second pair of eyes will be reviewing software modifications, and policing documentation and code test coverage. • This will also help on decreasing risk on areas where only one developer have been involved. • It will also help getting our new hires up to speed. • With CSV reducing its activities (2 week ES, 1 CSV block), the project is reaching a point where stability is becoming more important than pushing new capabilities.

  8. Risks & Issues (3) • Emphasis will be on getting longer baselines working. We may need to improve algorithms used for WVR correction. We may discover hitherto hidden timing problems. • BL correlator subarrays is a big capability! • The End of Commissioning worry us some. We do have good communication/relationships with CSV. We should maintain this in full operations. • ADC doesn't have resouces for new FrontEnd developments. We need to take over these modules.

  9. Pending Features &Tentative Schedule • See JIRA filter http://ictjira.alma.cl/issues/?filter=10511. It shows 31 candidate features for 2014.

  10. Antenna, LO & Timing HW • Release 10.8 • ICT-959, “Develop the software to implement fast scanning”. • ICT-1797, “Implement focus Z axis correction term using temperatures from antenna metrology sensors”. • ICT-899, “Implement storage of proper WVR parameters in ASDM”. • ICT-1867, “Add sequencing to the total-power processor”. • ICT-1019, “Array band management”. • Release 2014.2 • ICT-719, “Improve error handling in Control's observing mode layer”. • ICT-2288, “Implement flagging for antenna shadowing”. • ICT-693, “LS and WCA failure reports”. • ICT-136, “Operational State confidence”.

  11. Antenna, LO & Timing HW (2) • Release 2014.4 and 2014.6 (2nd semester 2014) • ICT-52, “Support for Observations of Fixed Calibration Source”. • ICT-54, “Scan sequences II”. • ICT-2285, “Review SOS scripts”. • For 2015 • ICT-2287, “Integrate Nutator Device with the Observing Modes”. • ICT-2282, “Sideband Separation for Single-dish Data”.

  12. HW monitor/control points and alarms • Release 10.8 • Release 2014.2 • Release 2014.4 and 2014.6 (2nd semester 2014) • ICT-2281, “Monitoring and alarm improvements”. • Not yet accepted • ICT-1445, “Request to add monitor points and alarms from the power system to the on-line system”.

  13. HW configuration database • Release 10.8 • Release 2014.2 • ICT-2286, “Refactor tmcdb-explorer”. • Release 2014.4 and 2014.6 (2 nd semester 2014)

  14. Other Tasks • Release 10.8 • XXX, “Estimate effort to port Control/Correlator to RedHat 6 in 64 bits”. • APP features. • Release 2014.2 • ICT-2290, “Integrate CASA in the Control subsystem”. • APP features. • Release 2014.4 and 2014.6 (2 nd semester 2014) • ICT-2289, “Port Control/Correlator software to RedHat 6 in 64 bits”.

  15. DataCapturer & QuickLook • Release 10.8 • Release 2014.2 • Release 2014.4 and 2014.6 (2 nd semester 2014)

  16. BL Correlator • Release 10.8 • ICT-273, “Concurrent sub-arrays – preconditions”. • ICT-2284, “DC bias and archive data scaling in TDM”. • Release 2014.2 • ICT-1764, “Concurrent sub-arrays – completion”. • ICT-1683, “Quantization correction for 3 bit sampler in FDM”. • Release 2014.4 and 2014.6 (2 nd semester 2014) • ICT-153, “LO offsetting (sideband separation)”. • Pending modes (ICT-152, ICT-155, ICT-156, ).

More Related