1 / 26

start and break slide

Baltic Sea Region Programme 2007-2013 project “Baltic Challenges and Chances for local and regional development generated by Climate Change“ BalticClimate. start and break slide. Kick-Off-Meeting April 1 st – 3 rd 2009 Large Conference Hall of Hotel Riga Riga/ Latvia host:.

Download Presentation

start and break slide

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Baltic Sea Region Programme 2007-2013 project“Baltic Challenges and Chances for local and regional development generated by Climate Change“BalticClimate start and break slide Kick-Off-Meeting April 1st – 3rd 2009 Large Conference Hall of Hotel Riga Riga/ Latvia host:

  2. „Progress Reports“ On project level and on Project Partner level Dennis Ehm, ARL

  3. What is a „Progress Report“? A progress report documents e.g. • the activities carried out, • milestones achieved, • outputs produced, • expenditures occurred, • expenditures controlled, and • budget used and remaining in a pre-defined period of time passed by.

  4. Who to whom? A) on „project level“ LP  JTS/ IB B) on „partner level“ PP  LP (or WP coordinator) C) extra, informal: Subcontractor  PP/LP

  5. Why a Progress Report to the JTS/IB? • To monitor the progress of planned project activities • Base for further activities • As justification and base for the bi-annual payment of co-financing from ERDF to the project

  6. Reporting periods and due date on project level Reports are due 3 months after end of each reporting period. Exactly defined in the Grant Contract:

  7. Subjects of the progress reports Every Progress Report: • activities = Activity progress Report (AR) • finances = Financial Report (FR) remark: so far only a draft version of the progress report exists, thus amendments are still possible

  8. Extra contents of the 1st progress report • Partnership Agreement signed by all Project Partners • Outputs defined, their indicators and their targets • communication plan (due already July 31st 2009) • preparation activities and expenditures (remark: so far only a draft version of the progress report exists, thus amendments are still possible)

  9. Extra content of the 4th progress report Mid-term self evaluation • Required but no formal structure set by EU • Process, structure, indicators must be planned and defined by the project • separate attachment to the 4th progress report

  10. Content of the Activity Report (AR) to JTS/IB probably (so far only a draft version of the progress report exists, thus amendments are still possible): • project summary (for official website) • achievements • overview of the work plan‘s progress • progress per WP (activities and milestones) • main outputs • marketing information and material

  11. Content of the Financial Report (FR) to JTS/IB probably (so far only a draft version of the progress report exists, thus amendments are still possible): • Eligible expenditures occurred per WP/ per BL • specification of external services, equipment and investments • total expenditures per Project Partner • interests/ revenues (if applicable) • complementary activities • First Level Control (FLC) confirmation on project level

  12. Progress reports on „partner level“ PP  LP (or to WP coordinator) • activities = Activity progress Report (AR) • in more detail than on project level • selected topics for report on project level • finances = Financial Report (FR) • expenditures basing on partner budget • First Level Control (FLC) on partner level

  13. Timing/ Schedule Allow one month for the LP • to summarize single reports, • to possibly ask for additional information and documents from single PPs and • to get First Level Control Certification on project level.

  14. Report due dates on partner level Reports incl. First Level Control certification are due the latest 2 months after reporting period end (= 1 month prior to reports on project level!)

  15. Reporting „system“ • reporting system is a puzzle of single reports (activity, financial) • sum of each level is base for next higher level

  16. Vertical reporting „system“  Level 1 (JTS/IB)  Level 2 (LP)   Level 3 (PPs)  (control/ check with application/contracts) deliver

  17. Horizontal reporting „system“ e.g. output/activity WP1+WP2+WP3 = project outputs/activities BL 2 of PP1 + PP2 + PP3-n = BL 2 of project

  18. „System“ Every single reporting partner is part of the whole reporting system. Only functions if everybodydelivers its report(s).

  19. Demand Deliver • in requested quality • in requested volume • in due time

  20. Correct delivery to ensure next higher reporting level can sum up and deliver requested quality and volume in due time!

  21. Subsidy Payment base Keep in mind: Reports are the base for payment of the subsidy!

  22. Responsibility in the TEAM Low-quality, late, or incomplete reports from LP to IB/JTS:  late or no payment of subsidy to the whole project  later or no payment to all partners!

  23. Consequences E.g. Financial report of one partner missing/ not accepted:  IB will not pay out any subsidy for the reporting period! (even though all other partners delivered AR and FR in requested quality, volume and time!)

  24. Awareness for work-flow • Timing • Every single report is base for higher level report • Subsidy for whole project only if all single reports delivered in correct quality, volume and time

  25. clue for success: TEAM-work EVERYBODY must be aware of that! WE are a project TEAM! We rely on each others! Let’s act this way!

  26. Baltic Sea Region Programme 2007-2013 project“Baltic Challenges and Chances for local and regional development generated by Climate Change“BalticClimate start and break slide Kick-Off-Meeting April 1st – 3rd 2009 Large Conference Hall of Hotel Riga Riga/ Latvia host: